General Construction Co. v. Hering Realty Co.

201 F. Supp. 487, 1962 U.S. Dist. LEXIS 3982
CourtDistrict Court, E.D. South Carolina
DecidedJanuary 18, 1962
DocketCA/6748
StatusPublished
Cited by15 cases

This text of 201 F. Supp. 487 (General Construction Co. v. Hering Realty Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Construction Co. v. Hering Realty Co., 201 F. Supp. 487, 1962 U.S. Dist. LEXIS 3982 (southcarolinaed 1962).

Opinion

WYCHE, District Judge (sitting by designation).

This is an action brought by the plaintiff to foreclose a mechanic’s lien on certain real estate in Marlboro County, South Carolina, and is now before me on seven separate motions, two made by the plaintiff and five made by the defendant.

The action is based upon a contract between plaintiff and Bennettsville Realty Company, defendant’s predecessor in ownership of the real estate. The present defendant is a Pennsylvania corporation into which Bennettsville Realty Company was merged and consolidated on March 10, 1958, and which assumed all the liabilities of the latter, as well as taking all of its rights. Plaintiff (the contractor) agreed to construct a building for Bennettsville (the owner) and to complete it within 210 days after receiving notice to proceed from the owner’s engineer/architect The McPherson Company. “Owner” refers to both Bennettsville Realty Company and its successor Hering Realty Company, the defendant here.

The contract price to be paid the contractor was $645,620.00, and during the course of construction the engineer/architect issued certain change orders which increased the contract price by $5,-766.67, a total of $651,386.77. Of this amount the owner has paid $582,267.45, leaving a balance of $69,117.32.

The contractor started work on January 2, 1957, and the building was delivered to the owner on February 12, 1958, which is beyond 210 days after the commencement of the work, whether the beginning date be November 29, 1956, as contended by the owner, or January 2, 1957, when the work actually started, and the parties are in complete disagreement as to which of them is responsible for the delay.

Many and almost constant differences existed between these parties from shortly after the commencement of the work until the building was delivered to the owner. During the course of construction the date of completion was extended from time to time, and, on October 23, 1957, a conference between the parties was held, at which time it was agreed that it would take approximately four weeks thereafter to complete the building. It was not completed within that time, but the contractor continued the work until the latter part of January, 1958, when the owner gave notice it was terminating the contract seven days thereafter.

The owner did not terminate the contract at that time, but extended the time for completion from day to day until January 13, 1958, by telegrams from its president. The contractor delivered the building to the owner on January 12, 1958.

At that time the engineer/architect certified the building as being complete, with the exception of certain items needing completion or correction, shown on what the trade calls a “punch list” and at that time issued its certificate for payment that the balance of the contract price $69,117.32 was then due the con *489 tractor by the owner, subject to completion of the items on the “punch list”.

The contractor contends that the “punch list” items were corrected within thirty days after the certificate for payment, when, under the contract, final payment was due. The owner contends that they had not been completed.

In March, 1958, the contractor filed its claim for extra work and labor beyond the contract requirements, totalling $20,447.-12. In April, 1958, the engineer/architect notified the contractor that it approved $512.28 of these claims and disapproved the remainder.

In March, 1958, Globe Ticket Company filed a number of claims against the contractor, some of which were approved or disapproved by the engineer/architect but others of which were not passed upon by it, although they constituted ninety per cent, or more of the total amount claimed by Globe Ticket Company.

The engineer/architect gave the contractor notice of its rulings on these claims on April 10, 1958. For the remainder of April, and into the early part of May, the parties conferred in an attempt to settle their conflicting claims but without success.

On May 12, 1958, the contractor filed its mechanic’s lien upon the owner’s property, setting out the indebtedness secured thereby to be $69,117.32 for the balance due under the contract, and $20,447.12 for additional labor and materials, a total of $89,564.44.

On June 2, 1958, the owner mailed to the contractor and the engineer/architect a demand for arbitration of the thirteen items constituting the contractor’s claims for extras, and of the forty-four items which constituted the owner’s claims, stating in that demand that claims Nos. 1-33, inclusive, of the owner’s claims, and all claims of the contractor, having been ruled upon by the engineer/architect, were not subject to arbitration in its opinion, but that its claims Nos. 34-44, inclusive, should be referred to arbitrators.

The contractor declined to agree to any arbitration and its complaint dated June 6, 1958, to foreclose its mechanic’s lien of May 12, 1958, was filed on June 7, 1958.

On the same day, June 7th, the owner filed a surety bond to discharge the mechanic’s lien against its real estate.

The owner answered the complaint and set up as a first defense that by the terms of the contract all factual issues in dispute were to be decided by arbitration; for a second defense, it admitted the basic contract price of $645,620.00 and the additional sum of $5,766.77, denied the item for additional labor and materials in the sum of $20,447.12, admitted payments on the contract price of $582,267.45, and then denied that any amount was due by it to the contractor for reasons stated in the answer and counterclaim, alleged defective work and damages for delay in the total sum of $80,227.49, claiming $75,-847.18 for delay, and $4,380.31 for defective work. The prayer of the answer and counterclaim, among other demands, was for judgment against the contractor in the sum of $10,597.89, the difference between its claimed damages of $80,227.49 and $69,629.60 (the total of $69,117.32 balance under the contract plus $512.28 approved by the engineer/architect).

The contractor replied to this counterclaim denying any liability by reason of the facts alleged in it.

In January, 1959, the owner gave notice of motion for an order submitting to arbitration all issues of fact as to the claims of the parties, each against the other. This motion was heard by Judge Ashton H. Williams on March 13, 1959, and by his Order dated April 15, 1959, Judge Williams denied the motion on the ground that the demand for arbitration was not made within a reasonable time, as required by the contract.

The owner appealed from this Order denying arbitration and the United States Court of Appeals for the Fourth Circuit, basing its decision upon the insufficiency of the record before Judge Williams, dismissed the appeal, but remanded the case *490 to the District Court for further proceedings. Hering Realty Co. v. General Const. Co., Columbia, S. C., 272 F.2d 371.

On remand, the motion was again heard by Judge Williams on two separate occasions, and by his Order dated August 12, 1960, he referred the owner’s claims Nos.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coon v. Renaissance on Charleston Harbor, LLC
Court of Appeals of South Carolina, 2006
Virginia Eastern Co. v. N. C. Monroe Construction Co.
56 Va. Cir. 220 (Salem County Circuit Court, 2001)
Davis v. Kitt Energy Corp.
365 S.E.2d 82 (West Virginia Supreme Court, 1988)
Cady v. Allstate Insurance
747 P.2d 76 (Idaho Court of Appeals, 1987)
Trident Technical College v. Lucas & Stubbs, Ltd.
333 S.E.2d 781 (Supreme Court of South Carolina, 1985)
In Re Arbitration County of Cass & Law Enforcement Labor Services, Inc.
353 N.W.2d 627 (Court of Appeals of Minnesota, 1984)
Five Keys, Inc. v. Pizza Inn, Inc.
653 P.2d 870 (New Mexico Supreme Court, 1982)
Scali, McCabe, Sloves, Inc. v. North River Insurance
532 F. Supp. 203 (S.D. New York, 1981)
Mathauser v. Hellyer
560 P.2d 1325 (Idaho Supreme Court, 1977)
In Re Compudyne Corporation
255 F. Supp. 1004 (E.D. Pennsylvania, 1966)
Fazio v. EMPLOYERS'LIABILITY ASSURANCE CORP. LTD.
197 N.E.2d 598 (Massachusetts Supreme Judicial Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
201 F. Supp. 487, 1962 U.S. Dist. LEXIS 3982, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-construction-co-v-hering-realty-co-southcarolinaed-1962.