Paul Allison, Inc. v. Minikin Storage of Omaha, Inc.

486 F. Supp. 1, 1979 U.S. Dist. LEXIS 13613
CourtDistrict Court, D. Nebraska
DecidedMarch 21, 1979
DocketCiv. 77-0-204
StatusPublished
Cited by4 cases

This text of 486 F. Supp. 1 (Paul Allison, Inc. v. Minikin Storage of Omaha, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paul Allison, Inc. v. Minikin Storage of Omaha, Inc., 486 F. Supp. 1, 1979 U.S. Dist. LEXIS 13613 (D. Neb. 1979).

Opinion

MEMORANDUM

DENNEY, District Judge.

Paul Allison, Inc. [Allison] and the Mini-kin Storage Corporation [Minikin] entered into a construction contract calling for the erection of warehouse facilities in Nebraska. A dispute arose, and the matter was submitted to arbitration in accordance with the contract. On September 16, 1975, an *2 award of $20,607.30 was entered for the plaintiff, in the State of Nebraska, a location not specifically designated as an arbitration site in the contract. Minikin subsequently refused to pay the award, and Allison filed a petition in an Oklahoma state court to collect damages arising from the defendant’s alleged breach of contract. The petition, which was filed on January 8, 1976, made no reference to the arbitration proceedings.

Thereafter, Minikin, a Nebraska corporation, filed a petition for removal to the federal district court in Oklahoma. Subsequent to removal, the Travelers Indemnity Company, a third-party defendant, raised the arbitration proceeding in its answer. Allison thereupon amended its complaint and stated that it would withdraw its claim for contractual damages if the arbitration award was adjudged binding on the parties.

On June 30, 1977, after argument on the law and facts, a federal district judge in Oklahoma granted the defendant’s motion for a change of venue. Paul Allison, Inc. v. Minikin Storage of Omaha, Inc., 436 F.Supp. 444 (W.D.Okl.1977).

Subsequently, the defendant filed a motion to dismiss for lack of subject matter jurisdiction, contending that since the Oklahoma court had no jurisdiction over the subject matter, it had no power to transfer this case pursuant to 28 U.S.C. § 1404(a) (1976). On June 28, 1978, this Court entered its memorandum and order holding that the federal district court in Oklahoma had subject matter jurisdiction over this case, and, therefore, was empowered to transfer the matter to this Court. Paul Allison, Inc. v. Minikin Storage of Omaha, Inc., 452 F.Supp. 573 (D.Neb.1978).

On August 11, 1978, the United States Magistrate ordered that the issue as to the validity of the arbitration proceedings as presented by plaintiff’s amended complaint be bifurcated for separate trial to this Court. In accordance with that order, this Court, on February 27, 1979, held a nonjury trial on the issue of the validity of the arbitration award.

Discussion

At the outset, the Court is faced with the question of determining which law to apply: state or federal. The defendant argues that since the contract is governed by the laws of the State of Nebraska and since the arbitration proceedings were conducted in accordance with Nebraska law, the arbitration provision is also governed by Nebraska law.

Under Nebraska law, various procedures are set up for conducting an arbitration proceeding and for enforcing an arbitration award. Neb.Rev.Stat. §§ 25-2103 to 2120 (Reissue 1975). As the arbitration proceedings did not comply with these procedures, the defendant contends that the award is invalid and unenforceable.

While the parties have stipulated to the effect that the arbitration proceedings did not comply with the applicable Nebraska statute, the plaintiff contends that since the Federal Arbitration Act [the Act], 9 U.S.C. §§ 2-14 (1970) is the law applicable to the arbitration provisions of the contract, it was unnecessary to meet the procedural requirements of the Nebraska law.

The defendant, in support of its position, stresses the importance of two articles contained in the contract. Article 7.1.1 provides that “[t]he contract shall be governed by the law of the place where the project is located.” The project was located in Omaha, Nebraska. Article 7.10.1, the relevant provision on arbitration, provides:

All claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof, . shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

*3 The Federal Arbitration Act was enacted in 1925. “[Reversing centuries of judicial hostility to arbitration agreements, [the Act] was designed to allow parties to avoid ‘the costliness and delays of litigation’ and to place arbitration agreements ‘upon the same footing as other contracts . . Scherk v. Alberto-Culver Co., 417 U.S. 506, 510-11, 94 S.Ct. 2449, 2452, 41 L.Ed.2d 270 (1974). Accordingly, federal courts generally resolve any doubts in favor of arbitration, Metro Indus. Painting Corp. v. Terminal Construction Co., 287 F.2d 382, 385 (2d Cir. 1961), and are hesitant in upsetting arbitration awards. Totem Marine Tug & Barge, Inc. v. North American Towing, Inc., 429 F.Supp. 452, 453 (E.D.La.1977).

Section 2 of the Act, the key provision in this action, provides that:

A written provision in any maritime transaction or a contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction, or the refusal to perform the whole or any part thereof, of an agreement in writing to submit to arbitration an existing controversy arising out of such a contract, transaction, or refusal, shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.

“Commerce”, as employed in § 2, is defined in § 1 of the Act to mean in part “commerce among the several states.” Thus, the Act is limited in its application to maritime transactions and transactions involving interstate commerce.

It is clear from the record that the contract here is definitely one “evidencing a transaction involving commerce” and thus falls within the scope of the Federal Act. “Once a dispute is covered by the Act, federal law applies to all questions of interpretation, construction, validity, revocability, and enforceability.” Coenen v. R. W. Pressprich & Co., 453 F.2d 1209, 1211 (2d Cir.), cert. denied, 406 U.S. 949, 92 S.Ct. 2045, 32 L.Ed.2d 337 (1972).

Moreover, despite the existence of a “choice of law” clause in the contract, the law is clear that it is federal law which governs questions regarding the validity and enforceability of the arbitration agreement. Commonwealth Edison Co. v. Gulf Oil Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
486 F. Supp. 1, 1979 U.S. Dist. LEXIS 13613, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paul-allison-inc-v-minikin-storage-of-omaha-inc-ned-1979.