Rounds & Hagler v. Aiken Mfg. Co.

36 S.E. 714, 58 S.C. 299, 1900 S.C. LEXIS 129
CourtSupreme Court of South Carolina
DecidedJuly 27, 1900
StatusPublished
Cited by6 cases

This text of 36 S.E. 714 (Rounds & Hagler v. Aiken Mfg. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rounds & Hagler v. Aiken Mfg. Co., 36 S.E. 714, 58 S.C. 299, 1900 S.C. LEXIS 129 (S.C. 1900).

Opinion

The opinion of the Court was delivered by

Mr. Justice Pope.

This action was commenced on the 1st day of June, 1898. I do not know that any words of mine would more accurately describe how the action was, in the opinion of the plaintiffs, rendered necessary, with the grounds for that opinion, than by adopting those employed by the Circuit Judge, Judge Benet, in his well considered-opinion. Flence I will reproduce the text of that décree:

“The defendant, the Aiken Manufacturing Company, a corporation by and under the laws of this State, having organized to do business as manufacturers of cotton goods, at Bath, in the county and State aforesaid, determining to erect a brick structure, or cotton factory, at said place, and having *302 advertised for competitive bids for the erection of said buildings and appurtenances, the plaintiffs, on March n, 1895, filed with the defendant’s agent a bid in writing, to do the work according to the plans and specifications that had been previously prepared by an architect and which had been examined by the plaintiffs; said bid, together with the pencil memorandum, known in the case as the ‘Barrett memorandum’ (and which will be herein referred to) shows that the plaintiffs undertook'to do the work required on the original mill and appurtenances for the lump sum of $53,198; said bid so modified by the Barrett memorandum, passed into a written agreement, which was made and executed by the parties on March 16, 1895, which paper is the contract in the case. It is noteworthy that there is not a thing set forth in the contract going to show at what price the plaintiffs were to furnish lumber or materials of any kind, except as set forth in the 19th section of said article, that the brick were to be at $4.25 per M., on an estimate that it took 2,000,000 of brick to complete the work. There is nothing in the contract going to show on what basis the plaintiffs estimated that they should be paid for laying brick, either in Portland or Rosendale cement, or lime. It is further agreed that all extra work should be paid for in proportion to the work in the original contract, and section 26 provides that no payment on account by the owners shall be deemed a waiver of the right to object to defective material or imperfect work. The work under the contract progressed, and as it progressed, extra additions were ¿greed to be made to the mill and to the work, all under the same contract, and the builders, or plaintiffs, went on to carry out the same. Payments were made to them from time to time, and it is unquestioned that much more than the original contract price was paid to them. After the work was completed, dispute arose as to the amounts due to the plaintiffs by the defendant, and in order to settle said disputes without litigation, an agreement in writing was entered into by the parties to submit the same to arbitration. The terms of said agreement are impprtant. *303 The preamble recites, that whereas, the contract aforesaid provides: ‘That any dispute or difference concerning the meaning and construction of the plans, drawings, or specifications, as to what is extra work, shall be decided by the architect.’ And whereas, in the specifications it is provided that ‘in case any dispute arises, respecting the true value of the extra work, or of work omitted, at the request of the owner, the same shall be valued by two competent persons, one employed by the owner and the other by the contractor, and those two to have power to name an umpire, whose decision shall be binding upon all parties.’ And whereas, a controversy is pending ‘in relation to the price to be paid by said company to said Rounds & Hagler for certain extra work done and performed by said Rounds & Hagler for said company upon their mill and canal and other structures at Bath, and also for material furnished by said Rounds & Hagler in doing such work, and deductions for work omitted.’ Then the matter in dispute is submitted ,to' the arbitrament and award of arbitrators to determine ‘the price to be paid for such extra and additional work, and material furnished, or of the amount to be deducted for omissions by them in the erection and building of the Aiken Manufacturing Company’s mill, its canal and other structures, at Bath, S. C.’ It is agreed further, that the builders shall nominate one of said arbitrators and the owners another; those two are called in the submission, arbitrators, and they are given ‘power to nominate an -umpire’ — he is called an umpire in the submission. It is further provided: ‘The award of any two shall be final and binding upon the parties.’ And there is no provision in the submission as to zvhen the award is to be made, as to how it is to be published, or what notice, if any, is to be given to the parties that the award is reached. There is a provision to this effect: ‘That the schedule of measurements as made by Rounds & Hagler and A. H. McCarrell, and contained in their respective books, shall be produced and delivered to the board of arbitrators, and as far as said measurements coincide and agree, they shall be accepted as *304 correct; and whenever said measurements do not agree, then the board of arbitrators shall take such course as they may deem proper, to ascertain such measurements, as they need.’ There is no provision in the submission as to the acceptance by the arbitrators of any price that may have been placed upon material or work by the contractors, or by McCarrell. Under this submission, the corporation appointed as their arbitrator, Joseph B. Storey, the plaintiffs appointed as theirs, Charles B. Allen, and those two appointed as the umpire, T. O. Brown; and on the 15th day of September, 1896, the three parties took an oath to carry out the terms of the submission. The evidence in the case shows that these three gentlemen are competent men, and stand well in the city of Augusta, where they live, and, in fact, in the argument of the case, counsel on both sides paid proper tribute to all of them. The two arbitrators, Storey and Allen, met, Mr. McCarrell appeared before them, as representing the company, and Mr. Rounds, the firm of Rounds & Hagler. It is unquestioned that a rule or regulation was agreed on, which was notified both to McCarrell and Rounds, that the arbitrators would meet every afternoon at the office of the Aiken Manufacturing Company, in Augusta, Ga., at 3 o’clock, and sit a reasonable time to consider the matters in question. This place was chosen without objection on the part of Mr. Rounds, and at the suggestion of Mr. Allen, because he said it was more commodious and suitable than his own private place of business. Both McCarrell and Rounds were present at many meetings. The arbitrators made calculations in the presence of both of them, questioned them, examined other witnesses, and went into all documents presented. Rounds made no objection either to the place of meeting, the mode of procedure, or the fact that McCarrell was present, or to the fact

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Construction Co. v. Hering Realty Co.
201 F. Supp. 487 (E.D. South Carolina, 1962)
Miller, Administrator v. A.C.L.R. Co.
138 S.E. 675 (Supreme Court of South Carolina, 1926)
State ex rel. Grubbs v. Schulz
171 N.W. 263 (Supreme Court of Minnesota, 1919)
State ex rel. Burrows v. Truax
166 N.W. 339 (Supreme Court of Minnesota, 1918)
Brooke v. Laurens Milling Co.
58 S.E. 806 (Supreme Court of South Carolina, 1907)
County of Greenville v. County of Spartanburg
40 S.E. 147 (Supreme Court of South Carolina, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
36 S.E. 714, 58 S.C. 299, 1900 S.C. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rounds-hagler-v-aiken-mfg-co-sc-1900.