Gencorp, Inc. v. Olin Corporation

477 F.3d 368, 67 Fed. R. Serv. 3d 539, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20042, 64 ERC (BNA) 1001, 2007 U.S. App. LEXIS 3102, 2007 WL 437914
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 12, 2007
Docket05-4439
StatusPublished
Cited by84 cases

This text of 477 F.3d 368 (Gencorp, Inc. v. Olin Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gencorp, Inc. v. Olin Corporation, 477 F.3d 368, 67 Fed. R. Serv. 3d 539, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20042, 64 ERC (BNA) 1001, 2007 U.S. App. LEXIS 3102, 2007 WL 437914 (6th Cir. 2007).

Opinion

OPINION

SUTTON, Circuit Judge.

After a protracted trial and an unsuccessful appeal to this court, GenCorp filed a Rule 60(b)(6) motion asking the district court to set aside a judgment in favor of Olin Corporation on the basis of Cooper Industries v. Aviall Services, Inc., 543 U.S. 157, 125 S.Ct. 577, 160 L.Ed.2d 548 (2005). GenCorp also asked the district court to stay execution of the judgment. The district court denied both motions. We affirm.

I.

In the 1960s, GenCorp and Olin built a chemical-processing plant in Ohio and stored the hazardous waste generated by the plant at two different sites. Although the agreement between the companies originally contemplated placing the plant under GenCorp’s sole control, Olin ultimately retained ownership of the plant. In 1985, the Environmental Protection Agency (EPA) notified Olin that it was a “potentially responsible party” under the Comprehensive Environmental Response, Compensation and Liability Act (CERC-LA) for the clean-up of “Big D,” one of the two disposal sites. After negotiations failed, the EPA issued two unilateral administrative orders under CERCLA § 106, 42 U.S.C. § 9606 — one for each site. The orders established “remedial design and remedial action” plans for the sites and required Olin to comply with them. JA 167. The government also brought a civil action against Olin under CERCLA § 107, 42 U.S.C. § 9607, seeking “reimbursement of the response costs which it ha[d] incurred in conducting a response action” at Big D. JA 281. In addition, the complaint asked for a declaratory judgment that Olin would “be liable for all future costs incurred by the United States ... in conjunction with the response activities at the Big D Campground Site.” JA 286.

This action began in 1993 when GenCorp requested a declaratory judgment disclaiming any CERCLA liability for the clean-up costs of the sites. Olin counterclaimed, seeking contribution for its response costs under CERCLA § 1 13(f), 42 U.S.C. § 9613(f), and arguing that Gen-Corp should be jointly and severally liable for the response costs under CERCLA § 107(a), id. § 9607(a). In 1995, GenCorp agreed to dismiss its declaratory judgment action, after which the parties litigated Olin’s counterclaims. GenCorp also amended its response to Olin’s counterclaim, adding the claim that Olin had breached its contract to insure the plant.

The district court eventually dismissed Olin’s claim for joint and several liability under § 107, reasoning that as a potentially responsible party Olin’s recourse lay in the contribution provision of CERCLA § 113(f). See Centerior Serv. Co. v. Acme Scrap Iron & Metal Corp., 153 F.3d 344, 356 (6th Cir.1998). The district court then held a bench trial and ruled for Olin on its *371 contribution claim on May 9, 2002. The district court concluded that GenCorp was responsible for 30% of the clean-up costs of Big D and 40% of the costs for the other site, leading to a judgment against Gen-Corp (and in favor of Olin) for $19 million in contribution costs and $9.7 million in prejudgment interest.

GenCorp asked the court to reconsider its decision based on “the plain language of § 113(f)(1),” arguing that a potentially responsible party like Olin could seek contribution only “during or following any civil action” under CERCLA § 106 or § 107. JA 257; 42 U.S.C. § 9613(f)(1). Claiming that Olin had not been subject to such a civil action, GenCorp argued that “[t]he express language of the statute bars Olin’s contribution claim.” JA 257. GenCorp acknowledged that the Sixth Circuit had not confronted the issue before and that district courts had taken conflicting positions on it. GenCorp also noted that the Sixth Circuit case most on point — Centeri- or — “did not undertake to define the scope and limits of the contribution action itself,” JA 259, and that the Fifth Circuit had recently issued a decision favoring Gen-Corp’s interpretation of section 113(f)(1), see Aviall Servs., Inc. v. Cooper Indus., 263 F.3d 134, 137 (5th Cir.2001). The district court rejected GenCorp’s motion. It noted that the Fifth Circuit had since vacated and reversed the panel decision, see Aviall Sews., Inc. v. Cooper Indus., Inc., 312 F.3d 677 (5th Cir.2002) (en banc), and reasoned that the final sentence of section 113(f)(1) assured that potentially responsible parties could proceed with contribution claims even in the absence of a civil action. See 42 U.S.C. § 9613(f)(1).

After rejecting GenCorp’s motion for reconsideration, the district court entered a final judgment for Olin on its contribution claim under Civil Rule 54(b). The district court stayed consideration of GenCorp’s breach-of-contract claim pending the resolution of a dispute between Olin and its insurers in the District Court for the Southern District of New York.

On appeal, GenCorp did not raise the issue presented in its motion for reconsideration. Our court rejected the issues that GenCorp did present on appeal and ultimately affirmed the judgment with one reservation. GenCorp, Inc. v. Olin Corp., 390 F.3d 433 (6th Cir.2004). We held that the statutory language of CERCLA § 113(g)(2) required a district court to enter a declaratory judgment as to future costs if a claimant succeeds in a contribution suit, but that such a judgment necessarily was limited by Article Ill’s “case or controversy” requirement. Id. at 451. “[Ujnable to find sufficient evidence of future response costs,” we remanded the case to the district court “for initial consideration of whether a ‘case or controversy’ exists, and if so, for the entry of a declaratory judgment.” Id.

After the Sixth Circuit issued its decision on November 22, 2004, GenCorp petitioned for rehearing en banc. At that point, it pressed the “civil action” argument for the first time in the court of appeals, noting that the Supreme Court had granted certiorari to the Fifth Circuit on the question. See Cooper Indus., Inc. v. Aviall Servs., Inc., 540 U.S. 1099, 124 S.Ct. 981, 157 L.Ed.2d 811 (2004). On December 13, 2004, the Supreme Court announced its decision in Cooper Industries, 543 U.S. 157, 125 S.Ct. 577, 160 L.Ed.2d 548, holding that § 113(f)(1) authorized contribution actions only when the claimant had been subject to a “civil action” under sections 106 or 107. Our court thereafter denied GenCorp’s petition for rehearing en banc, and the Supreme Court thereafter denied GenCorp’s petition for a writ of certiorari, GenCorp, Inc. v. Olin *372 Corp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
477 F.3d 368, 67 Fed. R. Serv. 3d 539, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20042, 64 ERC (BNA) 1001, 2007 U.S. App. LEXIS 3102, 2007 WL 437914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gencorp-inc-v-olin-corporation-ca6-2007.