Gebbers v. OKANOGAN CTY. PUBLIC UTIL. DIST.

183 P.3d 324
CourtCourt of Appeals of Washington
DecidedMay 1, 2008
Docket25995-1-III
StatusPublished
Cited by4 cases

This text of 183 P.3d 324 (Gebbers v. OKANOGAN CTY. PUBLIC UTIL. DIST.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gebbers v. OKANOGAN CTY. PUBLIC UTIL. DIST., 183 P.3d 324 (Wash. Ct. App. 2008).

Opinion

183 P.3d 324 (2008)

Daniel GEBBERS, People for Alternatives, Conservation & Education; and Methow Valley Citizens' Council, Appellants,
v.
OKANOGAN COUNTY PUBLIC UTILITY DISTRICT NO. 1, and the Commissioners thereof; Donald W. Johnson, Ernest J. Bolz, and David W. Womack, Respondents.

No. 25995-1-III.

Court of Appeals of Washington, Division 3.

May 1, 2008.

*325 Peter Robert Goldman, Attorney at Law, Seattle, WA, for Appellant.

Steven Gary Jones, Michael Gregory Lufkin, Dustin Trowbridge Till, Marten Law Group PLLC, Seattle, WA, Michael D. Howe, Attorney at Law, Omak, WA, for Respondent.

BROWN, J.

¶ 1 Property owner Daniel Gebbers; People for Alternatives, Conservation & Education; and Methow Valley Citizens' Council (collectively Citizens) appeal from a final order of the Okanogan County Superior Court upholding the adequacy of the Final Environmental Impact Statement (FEIS) of the Okanogan County Public Utility District No. 1(PUD). The PUD Board, by split vote, adopted alternative 2 for a new electrical transmission line and substation between Pateros and Twisp, while repairing and maintaining the existing Okanogan to Twisp transmission line, known as the Loup Loup line, for a secondary or redundant power source. We reject the Citizens' contention *326 that the FEIS is legally deficient for failing to consider work on the existing line (Alternative 4) as a connected action under a cumulative impacts analysis. We also reject Citizens' contentions that the FEIS underestimates Alternative 2 environmental impacts and economic costs while exaggerating those for Alternative 4. We conclude the FEIS was adequate under the rule of reason and the PUD did not act arbitrarily and capriciously. Accordingly, we affirm.

FACTS

¶ 2 The PUD electrical system has two main components, transmission and distribution. Existing transmission lines carry high voltage electricity to substations located in the Methow Valley. Distribution lines carry lower voltage to consumers. The transmission line was built in 1948 to serve the Methow Valley by bringing power west from the substation at Okanogan to substations at Malott, the Loup Loup summit area, and Twisp. The existing system has for years experienced reliability, capacity, and line loss problems. Increased service failures are predicted. The existing single radial transmission line has no back-up during power losses.

¶ 3 Capacity refers to the megawatts of power that a transmission line can carry. The existing line's capacity is 45 megawatts (MW). When the line approaches capacity, voltage drops may be so severe that damage results to the PUD's and customer-owned equipment. Capacity problems are expected to increase as the service population grows. Transmission line loss is the loss of power that could have been delivered to customers. The existing line presently experiences excessive and costly line losses. Replacing line conductors with larger wires is one method of reducing line losses. The electrical distribution system is now chronically overloaded, causing outages. Distribution line losses are partly caused by the distance between the substation and the consumer.

¶ 4 As a result, in 1996, the PUD proposed a new transmission line and substation between Pateros and Twisp. Progress slowed when the Superior Court ordered the preparation of an EIS. The PUD as lead agency under the State environmental Policy Act (SEPA), and the U.S. Forest Service as federal lead agency, worked together to prepare a draft EIS. The agencies sought input from citizens, environmental groups, and government agencies. After a lengthy process, the agencies prepared, and the PUD Board adopted, a Purpose and Need Statement to address the reliability, capacity, and line loss problems in both the transmission and distribution components of the PUD's system. Fifteen alternatives were identified and compared against the PUD's stated objectives. At a 2004 public meeting, the Board eliminated alternatives that did not appear to meet project needs. The Board approved six alternatives for consideration, plus a SEPA mandated no-action alternative.

¶ 5 In January 2005, an extensive Draft EIS (DEIS) was released describing each alternative to allow impact assessments. The DEIS included technical appendices addressing air quality, soils and erosion, vegetation, fish and wildlife, and visual aesthetics. The PUD conducted two public hearings and held several public meetings. The PUD responded to over 400 public comment letters and modified the Final Environmental Impact Statement (FEIS) to better explain issues or respond to public concerns.

¶ 6 In February 2006, the PUD manager, as the SEPA lead agency responsible official, selected Alternative 2 as the preferred alternative. The PUD released the FEIS on March 7, 2006. After extensive discussion of potential impacts on resources, the FEIS concluded none of the alternatives would have significant environmental impacts. At a regular public meeting on March 28, 2006, the PUD Board selected Alternative 2 over Alternative 4 by a 2 to 1 vote and directed work to begin. This appeal challenges that selection.

¶ 7 Alternative 2 proposes about 28 miles of new transmission line from Pateros to Twisp with installation of an 85-MW capacity conductor. A new substation will be constructed in the Gold Creek area, dividing the load on the lower valley distribution system in half. About 21.6 miles of new track road must be constructed and 252 structures installed. *327 About five miles of the new line would be overbuilt on the existing lower valley distribution system. The distribution system would not require total rebuilding. The new line would become the main transmission line into the Methow Valley. The FEIS estimates a cost of about $10.7 million for Alternative 2. The estimated system capacity totals 130 MW—85 MW for the new line plus 45 MW for the existing line.

¶ 8 Under Alternative 2, the existing Loup Loup transmission line would be repaired and maintained for service as a secondary or backup line and a redundant power source. The existing line is redefined as a secondary or "weak" line in an "Improved Radial Transmission Grid" with looped substation and transmission lines where one side of the loop has normal peak load capacity. The existing line will have lesser performance criteria than a single radial line.

¶ 9 In an improved radial grid, a secondary line must have sufficient capacity to carry 80 percent of the normal cold load on the primary line. The existing 45 MW line can meet this standard until the load increases to 56 MW (56 × 80% = 44.8 MW). According to the PUD's technical consultants, Foster Wheeler Environmental Corporation, the Methow Valley load in the year 2020 is estimated at 39.7 MW. Switches would be installed near Pateros, Gold Creek and Twisp to allow power to be switched from the new line to the existing line as needed.

¶ 10 The FEIS determines that Alternative 2 meets all of the technical objectives established for the Methow Transmission Project. Those objectives are: (1) reducing transmission line voltage drops; (2) ensuring transmission capacity to accommodate anticipated load growth; (3) reducing transmission line-related outages; (4) reducing existing transmission line losses; (5) reducing voltage drops on the distribution circuits; (6) ensuring distribution capacity to accommodate growth; (7) increasing transfer capability between distribution circuits; and (8) reducing line losses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Public Utility District No. 1 v. State
342 P.3d 308 (Washington Supreme Court, 2015)
Pub. Util. Dist. No. 1 v. State
Washington Supreme Court, 2015
Public Utility District No. 1 v. State
174 Wash. App. 793 (Court of Appeals of Washington, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
183 P.3d 324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gebbers-v-okanogan-cty-public-util-dist-washctapp-2008.