GE Oil & Gas Pressure Control, L.P. v. Carrizo Oil & Gas, Inc.

Court of Appeals of Texas·Decided May 18, 2023·No. 01-21-00285-CV·Published

Opinion

Opinion issued May 18, 2023

In The

Court of Appeals

For The

First District of Texas

awarding appellee Carrizo Oil & Gas, Inc. (“Carrizo”) more than $2.5 million in damages on its negligence claim arising from a well blowout.

GE leased and installed equipment for Carrizo (Marcellus) LLC (“Carrizo Marcellus”), a wholly-owned subsidiary of appellee Carrizo, to drill and complete a natural gas well. During the final fracking stage, a blowout occurred, resulting in the release of water, sand, and drilling fluids, and necessitating remediation. Carrizo sued GE and others, alleging negligence, breach of contract, product liability, and breach of warranty. GE counterclaimed, alleging that Carrizo was negligent, and that GE was entitled to indemnification from Carrizo.

In the summer of 2016, the trial court (Judge Mayfield) held a jury trial on liability, and the jury found that both GE and Carrizo were negligent.1 The jury found against Carrizo on the other claims. The trial court denied Carrizo’s motion to disregard the jury’s finding that it was negligent. In 2018, the trial court (Judge Hall) conducted the bench trial on GE’s indemnity claim. Two years later, the trial court signed findings of fact and conclusions of law. In 2021, the trial court granted Carrizo’s renewed motion to disregard the jury’s finding that it was negligent and denied GE’s request for additional findings of fact and conclusions of law. The court then rendered final judgment denying GE’s indemnity claim and awarding Carrizo damages exceeding $2.5 million.

1 The parties agreed to try the indemnification to the bench after the jury trial on liability, if necessary.

On appeal, GE raises three issues challenging: (1) Carrizo’s standing to sue for damages sustained by its wholly-owned subsidiary Carrizo Marcellus; (2) the trial court’s grant of Carrizo’s motion to disregard the jury’s verdict; and (3) the trial court’s determination that GE was not entitled to indemnity.

We affirm.

Background

Carrizo is an oil and gas exploration and production company. Its wholly-

owned subsidiary, Carrizo Marcellus, owns and operates wells in the Marcellus Shale “play” in Pennsylvania, including the Yarasavage 1H well that experienced the blowout from which this litigation arose.2 GE is an oilfield service provider that leases and installs equipment used in drilling and production, including the “frac valve assembly,” which is the main valve assembly at the top of a well and which is used during the process of fracturing a well to prepare it for production.3

2 A “shale gas play” is a “set of discovered, undiscovered or possible natural gas accumulations that exhibit similar geological characteristics.” See https://www.energy.gov/sites/prod/files/2013/04/f0/shale_gas_glossary.pdf (last visited May 2, 2023). The Yarasavage 1H well takes its name, Yarasavage, from the name of the owner of the surface estate. Its designation, 1H, refers to the fact that it is the first (1) of several horizontal (H) wells. The Marcellus Shale (and other similar formations) “hold hundreds of trillions of cubic feet of natural gas”

that was considered prohibitively expensive to access until innovations in drilling and extraction technology brought it within reach. See https://tinyurl.com/y7ah37rr (last visited May 2, 2023).

3 The frac valve assembly is also called the frac tree assembly.

GE installed the frac valve assembly that was used at Yarasavage 1H. All the equipment, except a gasket in the flange beneath the main valve, was leased; the gasket was sold to Carrizo because it is designed to be used once and replaced after use. After passing a static pressure test upon installation, the frac valve assembly was put into service. After twenty successful fracking stages, the frac valve assembly failed during the twenty-first and final fracking stage. Fracking fluids, water, and sand were expelled from the flange installed beneath the master valve, as shown in this photo admitted at trial:

Carrizo regained control of the well, conducted remediation in accordance with relevant laws and regulations, reported the incident to governmental agencies, and made claims with its insurer, Gemini Insurance Company. Gemini later filed suit on behalf of its insureds, Carrizo and Carrizo Marcellus, and in the name of Carrizo. Although Gemini is the real party in interest, we refer to Carrizo as it is the named plaintiff and appellee.

In its live pleading, Carrizo asserted that the frac valve assembly was improperly installed and that the ring gasket used in the flange beneath the master valve was defective and not within American Petroleum Institute (API) or manufacturer specifications. Carrizo alleged claims against GE for negligence, breach of contract, products liability, and breach of implied and express warranty.

GE generally denied the allegations and asserted counterclaims, including allegations that Carrizo was negligent and was contractually obligated to indemnify GE for its negligence. GE also sought attorney’s fees for asserting the indemnity claim.

Carrizo filed an amended pleading adding Carrizo Marcellus as a plaintiff, but the trial court sustained GE’s special exceptions and ordered Carrizo Marcellus to file a petition in intervention if it wished to be joined as a plaintiff. Carrizo Marcellus did not file a petition in intervention. GE moved for summary judgment, arguing that because the Yarasavage 1H well was owned and operated by Carrizo

Marcellus, Carrizo lacked standing to claim damages from the blowout.4 GE asserted that Carrizo “ha[d] not been personally aggrieved and therefore lack[ed] standing to sue GE for those damages.”

Carrizo responded that both it and Carrizo Marcellus suffered damages and that “all costs and expenses were passed on to and ultimately borne by” Carrizo, as the parent company. Carrizo also argued that Carrizo Marcellus had assigned all its rights to Carrizo and that all damages had been paid by and subrogated to its insurer, Gemini Insurance Company, who was the real party in interest. The trial court denied GE’s motion for summary judgment.

Before trial, GE and Carrizo agreed to bifurcate the trial into a jury trial on liability and a later bench trial, if necessary, on GE’s counterclaims for indemnification. The jury trial took place over seven days in the summer of 2016. Manufacturing defect, negligence, and breach of contract theories were submitted to the jury. The jury found that a manufacturing defect was not a producing cause of the blowout, and that GE did not fail to comply with its agreement to install the frac valve assembly on the Yarasavage 1H well. The jury found that the negligence of both GE and Carrizo was a proximate cause of the blowout.

4 GE also made other arguments in this motion for summary judgment. GE filed another motion for summary judgment three weeks after it filed the first summaryjudgment motion. It was largely identical to the first motion. GE filed an amended summary judgment another month later, and the standing arguments were the same.

After trial, Carrizo asked the trial court to disregard the jury’s answers to questions 2b and 3. Question 2b asked whether the negligence, if any, of Carrizo proximately caused the blowout on the Yarasavage 1H well. As to Carrizo, “negligence” was defined as

[the] failure to use ordinary care, that is, failing to do that which an oil and gas operator of ordinary prudence would have done under the same or similar circumstances or doing that which an oil and gas operator of ordinary prudence would not have done under the same or similar circumstances.

(Emphasis added.) The jury answered question 2b, “YES.” Question 3 asked the jury to find the percentage of responsibility attributable to GE and Carrizo. The jury found that GE was 35% responsible and Carrizo was 65% responsible.

Free access — add to your briefcase to read the full text and ask questions with AI

GE Oil & Gas Pressure Control, L.P. v. Carrizo Oil & Gas, Inc., (Tex. Ct. App. 2023).

GE Oil & Gas Pressure Control, L.P. v. Carrizo Oil & Gas, Inc. (GE Oil & Gas Pressure Control, L.P. v. Carrizo Oil & Gas, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Storage & Processors, Inc. v. Reyes
134 S.W.3d 190 (Texas Supreme Court, 2004)
First Valley Bank of Los Fresnos v. Martin
144 S.W.3d 466 (Texas Supreme Court, 2004)
FFE Transportation Services, Inc. v. Fulgham
154 S.W.3d 84 (Texas Supreme Court, 2004)
Austin Nursing Center, Inc. v. Lovato
171 S.W.3d 845 (Texas Supreme Court, 2005)
IRA Resources, Inc. v. Griego
221 S.W.3d 592 (Texas Supreme Court, 2007)
Baylor University v. Sonnichsen
221 S.W.3d 632 (Texas Supreme Court, 2007)
Gaines v. Kelly
235 S.W.3d 179 (Texas Supreme Court, 2007)
Mid-Continent Insurance Co. v. Liberty Mutual Insurance Co.
236 S.W.3d 765 (Texas Supreme Court, 2007)
David J. Sacks, P.C. v. Haden
266 S.W.3d 447 (Texas Supreme Court, 2008)
Nabors Drilling, U.S.A., Inc. v. Escoto
288 S.W.3d 401 (Texas Supreme Court, 2009)
National City Mortgage Co. v. Adams
310 S.W.3d 139 (Court of Appeals of Texas, 2010)
Gulf Insurance Co. v. Burns Motors, Inc.
22 S.W.3d 417 (Texas Supreme Court, 2000)
Coastal Transport Co. v. Crown Central Petroleum Corp.
20 S.W.3d 119 (Court of Appeals of Texas, 2000)
Ganske v. Spence
129 S.W.3d 701 (Court of Appeals of Texas, 2004)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
MG Building Materials, Ltd. v. Moses Lopez Custom Homes, Inc.
179 S.W.3d 51 (Court of Appeals of Texas, 2005)