LEHMAN, Chief Justice.

After litigation over the construction of appellee Haught's home, the homebuilder, appellant G.C.L, Inc., and Haught entered into a settlement agreement by which G.C.L, Inc. agreed to make certain repairs. When G.C.I., Inc. failed to make the repairs, Haught filed suit, alleging breach of the settlement agreement. After a bench trial, the district court found that G.C.L., Inc. had breached the settlement agreement by failing to make the repairs in a reasonable time and awarded Haught damages. We affirm.

ISSUES

G.C.L., Inc. presents three issues for our review:

I. Because no time was fixed for performance within the agreement, was Haught required, as a matter of law, to make a *908 demand upon GCI before a default or breach could occur?
II. Was the amount of damages awarded by the court, in excess of and contrary to the specific amount expressed by the parties' intent within the agreement?
III. Did Haught exeuse any non-performance by GCI by refusing to allow it to perform, when offered?

Appellee, Janet Haught, rephrases the issues:

1. Is the conclusion of the District Court that the Defendant/Appellant (G.C.I., Inc.) breached its contract with Janet Haught supported, by substantial evidence such that it is not clearly erroneous?
2. Is the conclusion of the District Court regarding the damages suffered by Janet Haught supported by substantial evidence such that it is not clearly erroneous?

FACTS

In early 1995, Janet Haught (Haught) and her husband Dwight hired appellant G.C.1., Inc. to build their "dream home" north of Cheyenne. The home was completed in mid-June of 1995. When the Haughts moved into their new home in late June and early July, they discovered a number of problems. Most obvious of the problems was a chimney that swayed in the wind. A "spongy" floor, i.e., one that bowed when walked on, was also a problem.

G.C.L., Inc. sued Haught in April of 1996 to recover monies due for the construction of the home. Haught counterclaimed, alleging that the workmanship was unsatisfactory. Court-ordered mediation was held in April of 1997, and a settlement agreement was filed in June of 1997. Under the terms of the settlement agreement, Haught agreed to pay $9800 into an escrow account, which she did immediately. When G.C.I., Inc. completed repairs, at its own expense, it would then be entitled to the $9800 held in escrow.

Pursuant to the terms of the settlement agreement, there were two categories of repairs: those the parties agreed on and those contingent on an engineer's report,. As to this second category, the parties agreed to retain an engineer to determine if certain repairs were necessary and also to determine the manner in which certain repairs would be performed. The engineer completed his report on December 10, 1997, and both parties were given a copy of the report.

G.C.L, Inc. never performed any of the repairs, and Haught filed the present action on June 2, 1998, alleging breach of the settlement agreement. Trial was bifurcated into a liability phase and a damages phase. The liability phase was tried to the bench on January 29, 1999, whereafter the district court determined G.C.I., Inc. breached the settlement agreement. The damages phase was held May 25, 1999, where the district court determined that G.C.I., Inc. was liable to Haught for damages of $76,163.36. The district court allowed G.C.1., Inc. to offset the $9800 escrow amount, thus leaving it liable to Haught for $66,863.36. G.C.I., Inc. appealed.

STANDARD OF REVIEW

In this case, we are asked to review both the district court's findings of fact as well as its conclusions of law.

The factual findings of a judge are not entitled to the limited review afforded a jury verdict. Hopper v. All Pet Amimal Clinic, Inc., 861 P.2d 531, 538 (Wyo.1993). While the findings are presumptively correct, the appellate court may examine all of the properly admissible evidence in the record. Id. Due regard is given to the opportunity of the trial judge to assess the credibility of the witnesses, and our review does not entail weighing disputed evidence. Id. Findings of\fact will not be set aside unless the findings are clearly erroneous. Id. A finding is\clearly erroneous when, although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. Id.

Stroup v. Oedekoven, 995 P.2d 125, 128 (Wyo.1999) (quoting Springer v. Blue Cross and Blue Shield of Wyoming, 944 P.2d 1173, 1175-76 (Wyo.1997)). A district court's conclusions of law are reviewed de novo. Hopper v. All Pet Animal Clinic, Inc., 861 P.2d 531, 538 (Wyo.1993).

*909 This dispute arises over a settlement agreement. We have previously stated that a settlement agreement is a contract subject to the same legal principles as those which apply to any contract. Exxon Corp. v. Board of County Comm'rs, Sublette County, 987 P.2d 158, 165 (Wyo.1999); Aztec Gas & Oil Corp. v. Roemer Oil Co., 948 P.2d 902, 903 (Wyo.1997); Matter of Estate of McCormick, 926 P.2d 360, 362 (Wyo.1996); Wyoming Bd. of Certified Public Accountants v. Christensen, 800 P.2d 853, 856 (Wyo.1990).

DISCUSSION

Breach

G.C.L, Inc. argues it did not breach the settlement agreement because Haught never demanded the repairs be performed by a certain time. It argues that, where no time for performance is fixed in a contract, demand is necessary before a party may be held in default. Haught responds that, where there is no time specified for performance, an unreasonable delay constitutes a breach and a formalistic demand is not required.

We first examine the issue of reasonable time. Where, as here, no time for performance is specified in a contract, the law implies performance must be within a reasonable time, and what is a reasonable time depends upon the circumstances of each case. Bennett v. Foust, 996 P.2d 693, 697 (Wyo.2000); Matney v. Webster, 808 P.2d 212, 214 (Wyo.1991); Zitterkopf v. Roussalis, 546 P.2d 436, 439 (Wyo.1976); Black & Yates v. Negros-Philippine Lumber Co., 32 Wyo. 248, 258, 231 P. 398, 401 (Wyo.1924). An unreasonable delay in performance constitutes a breach and justifies the remedy of cancellation. Zitterkopf v. Roussalis, 546 P.2d at 439; Keller v. Hummel, 334 N.W.2d 200, 203 (N.D.1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daryl A. Hensel v. Dapcpa Rpo Llc
2023 WY 84 (Wyoming Supreme Court, 2023)
Casco LLC v. McDonald's Real Estate Co.
666 F. App'x 743 (Tenth Circuit, 2016)
Megan B. Golden, f/k/a/ Megan B. Guion v. Todd A. Guion
2013 WY 45 (Wyoming Supreme Court, 2013)
Baker v. Speaks
2008 WY 20 (Wyoming Supreme Court, 2008)
Chancler v. Meredith
2004 WY 27 (Wyoming Supreme Court, 2004)
Wyoming Bank and Trust v. Haught
2003 WY 111 (Wyoming Supreme Court, 2003)
Orcutt v. Shober Investments, Inc.
2003 WY 60 (Wyoming Supreme Court, 2003)
In Re Adoption of TLC
2002 WY 76 (Wyoming Supreme Court, 2002)
Parsons v. Parsons
2001 WY 62 (Wyoming Supreme Court, 2001)
Scherer Construction, LLC v. Hedquist Construction, Inc.
2001 WY 23 (Wyoming Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
7 P.3d 906, 2000 Wyo. LEXIS 163, 2000 WL 973004, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gci-inc-v-haught-wyo-2000.