Baker v. Speaks

2008 WY 20, 177 P.3d 803, 2008 Wyo. LEXIS 21, 2008 WL 467020
CourtWyoming Supreme Court
DecidedFebruary 22, 2008
DocketS-07-0170
StatusPublished
Cited by13 cases

This text of 2008 WY 20 (Baker v. Speaks) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker v. Speaks, 2008 WY 20, 177 P.3d 803, 2008 Wyo. LEXIS 21, 2008 WL 467020 (Wyo. 2008).

Opinion

BURKE, Justice.

[¶ 1] Four members of the Speaks family brought suit against the Appellant, Byron Baker, for breach of a construction contract. After a bench trial, the district court granted judgment in favor of Appellees. Mr. Baker challenges that judgment. We affirm.

ISSUES

[¶ 2] Mr. Baker raises the following issue:

Did the Appellees breach the contract and breach the implied covenant of good faith and fair dealing requirement by wrongfully expelling the builder, [Mr. Baker], from the project?

Appellees present the issues as follows:

1. Did the District Court err when it found that Byron Baker had breached his contract with the [Appellees]?
*805 2. Did the District Court err when it found that Byron Baker had presented insufficient evidence to support his counterclaims against the [Appellees]?

FACTS

[¶ 3] In July 1999, David and Elizabeth Speaks opened negotiations to employ Mr. Baker to construct a home. 1 The negotiations concluded on September 14,1999, when Mr. Baker and Appellees entered into a contract. Pursuant to the contract, Mr. Baker agreed to build a 36’ by 36’ log home for the total amount of $133,488.00. The negotiations involved a number of floor plans that the parties exchanged, but Mr. Baker was to be solely responsible for turning the final floor plan drawing into a structurally sound home.

[¶ 4] The contract was memorialized in a three-page document with two features that are particularly relevant to our review. First, the home was to be “[cjompleted in a substantial workmanlike manner.” Second, the contract provided no particular time for completion of the home. The same day that the parties entered into the contract, Appel-lees paid Mr. Baker the first installment of $2,669.76, which was listed in the contract as a “commencement” payment.

[¶ 5] By the spring of 2000, Appellees were growing increasingly concerned about both the pace of construction and its apparent poor quality. Appellees met with Mr. Baker numerous times during the summer of 2000 regarding the delays. There was a final meeting on or about August 1st at which David and Elizabeth Speaks presented Mr. Baker with a written list of incomplete items and asked Mr. Baker to commit to a completion date. The parties agreed to a schedule providing that the interior of the home would be completed by the end of August, and that the exterior would be completed by September 10th. During that meeting, Mr. Baker’s comments raised concerns regarding the status of payment to the subcontractors. Ap-pellees asked Mr. Baker to provide lien waivers from the subcontractors.

[¶ 6] By the first week of September, Mr. Baker had not completed any items on the August 1st list. Neither had he provided the requested lien waivers from the subcontractors. At that time, Appellees had paid Mr. Baker a total of $140,202.61. On September 5th, Appellees, acting through their attorney, sent Mr. Baker a letter instructing him to vacate the job site until he provided the requested lien waivers. Mr. Baker left the job site after receiving the letter on September 7th.

[¶ 7] Now left with an incomplete home, Appellees hired a plumber to evaluate the remaining plumbing work. The plumber recommended hiring a general contractor to perform a general inspection, and Appellees did so. The contractor noticed several problems in the home, including sheetrock that was crushed at the top and under-sized rafters and roof purlins. The contractor recommended that Appellees contact a structural engineer to perform an in-depth analysis of the construction. The structural engineer found that the roof was “substantially under-structured or undersized to safely support the potential snow loads.” Appellees responded to the inspections by hiring others to repair and complete the home at significant additional cost. 2

[¶ 8] Appellees filed suit, alleging breach of contract, breach of the covenant of good faith and fair dealing, breach of implied warranty, and promissory estoppel. Mr. Baker filed a counterclaim for breach of contract. 3 *806 A three-day bench trial was held. On June 7, 2007, the district court entered its Findings of Fact, Conclusions of Law and Judgment. After detailing the course of events leading to the trial, the district court found that “Defendant Byron Baker breached [the] contract by failing to complete the project in a timely manner and failing to perform work in a safe and workmanlike manner and in accordance with industry standards.” As a result of these breaches, the court awarded Appellees $239,359.37 in compensatory damages.

STANDARD OF REVIEW

[¶ 9] When a district court issues specific findings of fact and conclusions of law, we review its findings of fact for clear error and its conclusions of law de novo. E.g., Piroschak v. Whelan, 2005 WY 26, ¶ 7, 106 P.3d 887, 890 (Wyo.2005). We do not set aside findings of fact simply because we would have reached a different result, nor do we re-weigh the evidence on appeal. Instead, we presume that the district court’s findings of fact are correct. We also assume that the evidence of the party prevailing below is true and give that party every inference that can be fairly drawn from the evidence. A finding of fact is clearly erroneous only where, “although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” Id.

DISCUSSION

[¶ 10] Much of Mr. Baker’s brief is focused on his proposition that “the trial court’s findings were one-sided, even though both parties had submitted Findings of Fact and Conclusions of Law.” He claims that his workmanship was acceptable and that the construction time was reasonable. He also claims that Appellees breached the construction contract when they instructed him to leave the job site.

[¶ 11] We first address the district court’s finding that Mr. Baker failed to complete the home in a timely manner. As we have previously stated, “[w]here ... no time for performance is specified in a contract, the law implies performance must be within a reasonable time, and what is a reasonable time depends upon the circumstances of each case.” G.C.I., Inc. v. Haught, 7 P.3d 906, 909 (Wyo.2000). On appeal, Mr. Baker contends that the evidence is insufficient to establish that he failed to perform in a timely manner. We disagree.

[¶ 12] Mr. Baker does not dispute that the parties intended the roof to be completed prior to significant snowfall in the fall of 1999. He also does not dispute that the roof was not completed until March 2000. David Speaks testified that he raised his concerns regarding the lack of progress with Mr. Baker during the August 1, 2000 meeting. Mr. Baker agreed to a specific schedule for the remaining construction. The evidence shows that Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Casco LLC v. McDonald's Real Estate Co.
666 F. App'x 743 (Tenth Circuit, 2016)
Derek Earl Hill v. State
2016 WY 27 (Wyoming Supreme Court, 2016)
Michael Jesse Munoz v. The State of Wyoming
2013 WY 94 (Wyoming Supreme Court, 2013)
Stastny v. State
2011 WY 138 (Wyoming Supreme Court, 2011)
Winter v. Pleasant
2010 WY 4 (Wyoming Supreme Court, 2010)
Bowser v. State
2009 WY 54 (Wyoming Supreme Court, 2009)
Belden v. Thorkildsen
2008 WY 145 (Wyoming Supreme Court, 2008)
Abeyta v. State
2003 WY 136 (Wyoming Supreme Court, 2003)
South Coast Fisheries, Inc. v. Department of Fish & Game
213 Cal. App. 2d 325 (California Court of Appeal, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
2008 WY 20, 177 P.3d 803, 2008 Wyo. LEXIS 21, 2008 WL 467020, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-v-speaks-wyo-2008.