Gay v. Lathrop

6 N.Y. St. Rep. 603
CourtNew York Supreme Court
DecidedJanuary 15, 1887
StatusPublished

This text of 6 N.Y. St. Rep. 603 (Gay v. Lathrop) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gay v. Lathrop, 6 N.Y. St. Rep. 603 (N.Y. Super. Ct. 1887).

Opinion

Per Curiam.

Order affirmed, with costs, upon opinion of Martin, J., at special term.

The following is the opinion of Martin, J., in which the facts sufficiently appear:

Martin, J.

This was a motion for a new trial made by the defendant on case and exceptions. So far as the questions involved are concerned, the action was to recover the contract price for the excavation of a quantity of solid rock. The services in question were performed under a written contract between the parties for the construction of a portion of a railroad. By the terms of the contract the plain was to receive ninety cents per cubic yard for the excavation of solid rock. That the plaintiff excavated 15,429 yards is not disputed. That he has been paid for only 12,580 yards is admitted. It was for the difference, 2,849 yards, that the plaintiff sought to recover.

On the trial it was claimed by the defendant that the solid rock in dispute was excavated from a point back of [604]*604the line laid out by the chief engineer of the railway company, and contrary to his instructions. That the excavation of such rock was not only unnecessary and of no benefit to the company, but was an injury to the work. The plaintiff, however, insisted that he excavated only to, or substantially to, such line, and that he substantially complied with the instructions of the engineer. This question was submitted to the jury, who found for the plaintiff.

The contract between the parties contained the following provisions: “ Now, therefore, in consideration of the premises, this agreement further witnesseth, that the said party of the first part hereby agrees with the said E. G-. Gay, party of the second part, that they will pay, or cause to be paid, in lawful money, to the party of the second part, * * * for all materials furnished and delivered, and for all work done under this contract, the prices named in the annexed proposal, signed by the party of the second part, and forming a part of this contract, to be made in the following manner; that is to say: On or about the 10th of each and every month, during the progress of the work, an estimate will be made of all materials delivered and of work done during the preceding calendar month, with its amounts, at the prices named in the annexed proposal, with any extra work done, estimated as hereinbefore provided for, ninety per cent, of which monthly estimate shall be paid to the party of the second part within ten days thereafter. * * * When the work under this contract is completed to the satisfaction of the party of the first part, and the acceptance of the chief engineer of the said railway, there shall be a final estimate made of all materials delivered, and .all the work done agreeably to the terms of this agreement, to be made up from the estimates of said chief engineer as to quantities on the sections included in this contract, to which are to be fixed the prices named in the annexed proposal, to ascertain the amount due on the final estimate, less the sum paid on the monthly estimates, when the balance appearing to be due to said party of the second part shall be paid to said E. G. Gay, * * * And it is further agreed that the decision of the chief engineer of the said railway shall be final and conclusive in any difference or disputes which may arise between the parties to this agreement, relative to, or touching the same, and each and every of said parties do hereby waive any right of action, suit, or suits, or other remedy in law, or otherwise, by virtue of said covenants, so that the decision of, shall, in the nature of the award, be final and conclusive on the rights and claims of the said parties.”

Here were two separate and independent provisions; one providing the manner of payment as the work progressed, [605]*605and also the manner of determining the sum the plaintiff was to_ receive on the completion of his work; the other, providing that the decision of the chief engineer as to any difference between the parties should be final.

That the last provision is void must be admitted, as it is well settled in this state that a general covenant to submit any differences that may arise in the performance of a contract, or under an executory agreement, is a nullity. Haggard v. Morgan, 5 N. Y., 422; Hurst v. Litchfield, 39 id., 377; Hart v. Lauman, 29 Barb., 410; D. & H. Canal Co. v. Pa. Coal Co., 50 N. Y., 250.

But, as these provisions are separate and independent, the invalidity of the latter does not affect the validity or force to be given to the former. Where a contract contains some provisions which are void, but embraces other independent agreements which are valid, the latter may be enforced. Jarvis v. Peck, 10. Paige, 119; Leavitt v. Blatchford, 5 Barb., 10; Leavitt v. Palmer, 3 N. Y., 19; Curtis v. Leavitt, 15 id., 123; Senderson v. Goodrich, 46 Barb., 617; Arnot v. P. & E. Coal Co., 2 Hun 591-S. C. 68 N. Y., 558.

This leads us to consider the rights of the parties under the provision of the contract first above set forth. So far as the question involved is concerned, it provides that when the work shall be completed and accepted, a final estimate shall be made of all the materials delivered and work performed agreeably to the terms of the contract, to he made up from the estimates of the chief engineer as to quantities, to which the prices named in the plaintiff’s proposals were to be fixed, to ascertain the amount due upon the completion of the work. Thus the parties expressly agreed to adopt the estimate of the chief engineer as the basis for determining the amount of the final payment to the plaintiff. Such is the effect of the contract, and such was doubtless the intent of the parties. The situation and relation of the parties, the circumstances and the nature of the transaction all tend to show that such was the intent. The defendant was a contractor with the railroad company for the construction of several miles of its railway. The plaintiff made a sub-contract with the defendant to perform only a small portion of such work. The defendant could only recover from the company for such quantities of labor and material as were included in the final estimate of its chief engineer. Hence it was, that in making this contract, the defendant required the plaintiff to adopt the same basis for the determination of the quantities of his work and material that the defendant by his contract with the railroad company was required to adopt.

That such a contract when fairly entered into is valid .and binding upon the parties to it is well established. In [606]*606McMahon v. N. Y. and E. R. R. Co. (20 N. Y., 467), where the amount of the work was to be determined by the engineer of the defendant, it was held that such a provision was free from any legal objection, and obligatory upon the parties. In Wangler v. Swift (90 N. Y., 38), where the defendant agreed to pay such sum as should appear due for work and materials under a certificate from the engineer in charge of said work, it was held that the agreement was valid. See also Smith v. Briggs, 3 Den., 73; Smith v. Brady, 17 N. Y., 173, 176; Wyckoff v. Meyers, 44 id., 145; Hoffman v. Gallaher, 6 Daly, 42; D. and H. Canal Co. v. Pa. Coal Co., supra; Gibbs v. Continental Ins. Co., 13 Hun, 611, 614;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leavitt v. . Palmer
3 N.Y. 19 (New York Court of Appeals, 1849)
Wangler v. . Swift
90 N.Y. 38 (New York Court of Appeals, 1882)
McMahon v. . the New York and Erie Railroad Company
20 N.Y. 463 (New York Court of Appeals, 1859)
President of Delaware & Hudson Canal Co. v. Pennsylvania Coal Co.
50 N.Y. 250 (New York Court of Appeals, 1872)
Dustan v. . McAndrew
44 N.Y. 72 (New York Court of Appeals, 1870)
Haggart v. . Morgan
5 N.Y. 422 (New York Court of Appeals, 1851)
Arnot v. . Pittston and Elmira Coal Co.
68 N.Y. 558 (New York Court of Appeals, 1877)
Smith v. . Brady
17 N.Y. 173 (New York Court of Appeals, 1858)
Hart v. Lauman
29 Barb. 410 (New York Supreme Court, 1859)
Smith v. Briggs
3 Denio 73 (New York Supreme Court, 1846)
Hoffman v. Gallaher
6 Daly 42 (New York Court of Common Pleas, 1875)
Collins v. Vanderbilt
8 Bosw. 313 (The Superior Court of New York City, 1861)

Cite This Page — Counsel Stack

Bluebook (online)
6 N.Y. St. Rep. 603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gay-v-lathrop-nysupct-1887.