Gausselin v. Commonwealth Edison Co.

631 N.E.2d 1246, 260 Ill. App. 3d 1068, 197 Ill. Dec. 787, 1994 Ill. App. LEXIS 342
CourtAppellate Court of Illinois
DecidedMarch 18, 1994
Docket1-92-2939
StatusPublished
Cited by33 cases

This text of 631 N.E.2d 1246 (Gausselin v. Commonwealth Edison Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gausselin v. Commonwealth Edison Co., 631 N.E.2d 1246, 260 Ill. App. 3d 1068, 197 Ill. Dec. 787, 1994 Ill. App. LEXIS 342 (Ill. Ct. App. 1994).

Opinion

JUSTICE McNAMARA

delivered the opinion of the court:

Plaintiff, James Gausselin, brought this action to recover for injuries he sustained while working at a nuclear power facility owned and operated by defendant, Commonwealth Edison. In count I of his complaint, plaintiff alleged violations of the Illinois Structural Work Act (Ill. Rev. Stat. 1991, ch. 48, par. 60 et seq.). In count II, he alleged common law negligence. A jury returned a verdict in favor of defendant on both counts and the trial court entered judgment on the verdict. On appeal, plaintiff contends that the trial court erred in (1) refusing to give the jury separate verdict forms for each count of his complaint; (2) allowing an undisclosed expert witness to testify for defendant; (3) allowing documents into evidence which defendant failed to produce prior to trial; and (4) admitting into evidence a photograph without sufficient foundation.

The relevant facts are as follows. On December 14, 1984, plaintiff was injured while working on a scaffold at defendant’s La Salle Nuclear Power Plant ("La Salle”). At the time of the injury, plaintiff was employed as a pipefitter by Morrison Construction Company and was working, along with several other Morrison employees, at the La Salle plant. On the date in question, plaintiff and an apprentice pipefitter, Ed Patz, Jr., were assigned to unbolt a flange on the end of a pipe attached to a vapor body in the "rad waste” building at La Salle. Different types of radioactive waste are processed in vapor bodies in that building. Before going to the rad waste building, Gausselin and Patz obtained a radiation work permit and the necessary authorization to enter the rad waste building. They then received protective clothing from defendant’s "rad chem” department. Gausselin asked one of the technicians whether the flange he was opening was pressurized because he wanted to know if there was potentially radioactive water in the line, but the technician said he did not know. According to plaintiff, it was customary for defendant to drain any pipes needing repair before Morrison employees began to work on them; Morrison employees had no authority to do so on their own.

The pipe and flange plaintiff and Patz were instructed to repair were approximately 10 feet from the floor. The flange was 18 or 24 inches in diameter and weighed about 80 pounds. Plaintiff and Patz had to climb a scaffold to reach them. The scaffold was already assembled, and plaintiff made no attempt to move it. Several tools were on top of the scaffold. Plaintiff did not touch or move these tools because he thought they might be contaminated. Plaintiff agreed that, as far as the location of the flange was concerned, there was nothing wrong with the placement of the scaffold.

Plaintiff and Patz climbed on top of the scaffold and began removing the 14 to 20 bolts securing the flange to the pipe. The deck of the scaffold was approximately two to three feet below the top of the flange, and it was necessary for plaintiff to squat down while he repaired the flange. The flange extended into the scaffold approximately six inches. Plaintiff loosened the bolts in a "crisscross” motion because he "wanted the [flange] to come off nice and easy.” Plaintiff stated that as they loosened the bolts, "some water came out” and "all of a sudden, the flange popped off.” Plaintiff, still in a squat position, quickly twisted around and landed on top of the tools when a spray of water came out "a good two feet in the air.” Plaintiff and Patz quickly got up and "rushed the plate, put our weight on the plate” and "started tightening up the bolts.” Plaintiff said that he felt pain in his right knee when he landed on the tools.

Plaintiff stated that a couple of gallons of water came out of the pipe before they reattached the flange. His boots got wet, but plaintiff did not receive any contamination from this incident. Plaintiff did not know if the water flowed down a drain in the room, but agreed with another witness that sometimes workers would tape over drains.

Once on the ground, plaintiff told Joe Feisel, the Morrison employee stationed outside the rad waste building, to call his foreman, Tom Faubel, and the head foreman, Bob Jahnke, and report that the pipe contained pressurized water. Later that day, plaintiff reported the incident to both Faubel and Jahnke. At the end of his shift, plaintiff drove himself home from work. His knee was swollen and painful when he arrived home.

Plaintiff did not see a doctor over the weekend following the incident because he wanted to see the company doctor on Monday. The doctor was not in on Monday and plaintiff did only light work that day. On Tuesday, he again reported to work and saw the company doctor at a nearby hospital. He told the doctor’s nurse about a fall he took a few weeks before December 14, in which he hit his knees on the floor. He said he experienced no pain or other problems from that fall. Plaintiff did not tell the doctor that he was injured as a result of water spraying out of the pipe.

Plaintiff continued to work the rest of the week, taking pain pills prescribed by the doctor and performing only light work. Plaintiff then called his family physician, Doctor Lambur, but could not get an appointment until January 16, 1985. Doctor Lambur performed tests on the knee on January 21. Plaintiff subsequently underwent surgery to his knee and eventually returned to work in April.

Doctor Lambur testified on plaintiff’s behalf and stated that plaintiff told him that he was injured at work while trying to avoid "a splash of water.” Doctor Lambur performed surgery on plaintiff’s knee on January 30, 1985. He testified that plaintiff’s explanation of how the injury occurred was consistent with the problems he saw in the knee during surgery.

Jahnke also testified for plaintiff. Plaintiff told him on December 14 that he and Patz were unbolting a flange when he was sprayed with contaminated water and twisted his knee on the scaffold. Jahnke noticed that plaintiff was limping. After the incident, Jahnke went into the room where plaintiff had been working and noticed a gallon or two of water on the floor. Jahnke opined that the water came from the flange. After viewing the room, Jahnke reported the incident to Tim O’Connor, one of defendant’s field engineers.

Jahnke stated that Morrison "takes [defendant’s] word” that the pipes to be repaired have been drained. Morrison has no authority to drain the lines. He explained that a pink sheet is customarily attached to the work package Morrison gets from defendant for a repair job, which indicates whether the piping system is running that day and whether there is any pressure in the pipes. According to Jahnke, the work package admitted at trial was incomplete because the pink sheet was missing. Jahnke stated that the work could not be completed without this sheet.

Jahnke was aware that La Salle had a comprehensive draining system leading to holding tanks. He stated that these water holding tanks "used to fill, and then, overfill onto the floor, and then, out the door.” According to Jahnke, none of the water from the pipe plaintiff was repairing could have flowed into the holding tanks because the drain in the rad waste room had been taped by Morrison employees "so no water would go down it.”

Faubel testified next for plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bautista v. Tellez
2025 IL App (1st) 240687-U (Appellate Court of Illinois, 2025)
Frederick v. Gaca
2020 IL App (3d) 200154 (Appellate Court of Illinois, 2020)
Ravizza v. PACCAR, Inc.
2020 IL App (1st) 181109-U (Appellate Court of Illinois, 2020)
Grauer v. Clare Oaks
2019 IL App (1st) 180835 (Appellate Court of Illinois, 2019)
Sharbono v. Hilborn
2014 IL App (3d) 120597 (Appellate Court of Illinois, 2014)
Reyes v. Menard, Inc.
2012 IL App (1st) 112555 (Appellate Court of Illinois, 2012)
In Re Estate of Mercier
961 N.E.2d 958 (Appellate Court of Illinois, 2011)
Balough v. Northeast Illinois Regional Commuter Railroad
950 N.E.2d 680 (Appellate Court of Illinois, 2011)
Linhart v. Bridgeview Creek Development, Inc.
909 N.E.2d 865 (Appellate Court of Illinois, 2009)
Cyclonaire Corp. v. ISG Riverdale, Inc.
882 N.E.2d 684 (Appellate Court of Illinois, 2007)
Cyclonaire v. ISG Riverdale
Appellate Court of Illinois, 2007
First National Bank v. Glen Oaks Hospital & Medical Center
829 N.E.2d 378 (Appellate Court of Illinois, 2005)
York v. El-Ganzouri
817 N.E.2d 1179 (Appellate Court of Illinois, 2004)
In re Jaber W.
Appellate Court of Illinois, 2003
People v. Felicia W.
799 N.E.2d 835 (Appellate Court of Illinois, 2003)
Gold v. Ziff Communications Co.
748 N.E.2d 198 (Appellate Court of Illinois, 2001)
Fritzsche v. Union Pacific Railroad Co.
Appellate Court of Illinois, 1999
Morrison v. Reckamp
Appellate Court of Illinois, 1998

Cite This Page — Counsel Stack

Bluebook (online)
631 N.E.2d 1246, 260 Ill. App. 3d 1068, 197 Ill. Dec. 787, 1994 Ill. App. LEXIS 342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gausselin-v-commonwealth-edison-co-illappct-1994.