Cyclonaire v. ISG Riverdale

CourtAppellate Court of Illinois
DecidedDecember 31, 2007
Docket1-07-0421 Rel
StatusPublished

This text of Cyclonaire v. ISG Riverdale (Cyclonaire v. ISG Riverdale) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cyclonaire v. ISG Riverdale, (Ill. Ct. App. 2007).

Opinion

FIRST DIVISION DECEMBER 31, 2007

No. 1-07-0421

CYCLONAIRE CORPORATION, ) Appeal from the ) Circuit Court of Plaintiff-Appellant, ) Cook County. ) v. ) No. 04 CH 21746 ) ISG RIVERDALE, INC., ) Honorable ) Clifford L. Meacham, Defendant-Appellee. ) Judge Presiding.

JUSTICE ROBERT E. GORDON delivered the opinion of the court:

Plaintiff, Cyclonaire Corporation, appeals from a judgment of the circuit court of

Cook County, finding that plaintiff’s subcontractor’s mechanic’s lien was invalid for

failure to strictly comply with the 90-day written notice period mandated by section 24(a)

of the Mechanics Lien Act. 770 ILCS 60/24(a)(West 2006). The trial court found that

plaintiff’s notice of lien was sent outside the 90-day written notice period, and found that

any services performed and replacement parts provided by plaintiff during the 90-day

period preceding the notice of plaintiff’s lien constituted warranty service that could not

extend the time for written notice. On appeal, plaintiff contends that (1) the trial court’s

judgment was against the manifest weight of the evidence, and (2) the trial court erred by

excluding from evidence, plaintiff’s exhibits Nos. 45 and 46, constituting internal No. 1-07-0421

shipping and invoicing documents, which plaintiff claims would have proved that

plaintiff’s last date of performance fell within the applicable 90-day period.

BACKGROUND

Defendant ISG Riverdale, Inc., owns and operates a steel mill in Riverdale,

Illinois. In July of 2003, defendant entered into a contract with general contractor

Fairfield Engineering Co. for a flux delivery system to convey lime, dolo lime, and coal

into a basic oxygen furnace at defendant’s steel mill facility. Fairfield elicited bids from

subcontractors for the delivery of the flux delivery system equipment. Plaintiff’s final

written proposal to Fairfield dated May 14, 2003, noted that installation of the equipment

was to be performed “BY OTHERS” rather than plaintiff.

Fairfield executed a written purchase order with plaintiff for the delivery of five

units of equipment at ISG’s facility. The written contract between plaintiff and Fairfield

consisted of Fairfield purchase order No. 24806-001A and three change orders. The

contract specified that the project would be completed in three phases. Phase I consisted

of conveyors 1 and 2. Phase II consisted of conveyors 3 and 4. Finally, Phase III

consisted of conveyor 5. The equipment contract provided that plaintiff was to deliver all

of its equipment by “approximately” December 15, 2003.

The equipment was delivered on December 16, 2003. At trial, all of the witnesses

testified that plaintiff’s equipment did not function properly. All of the witnesses

substantially agreed that the performance problems were due to the fact that certain parts

of the equipment were too small, which prevented sufficient airflow within the flux

2 No. 1-07-0421

delivery system to allow the equipment to function properly. In response, plaintiff

serviced and provided replacement parts for the equipment. At trial, plaintiff contended

that these services constituted “start-up” services that were part of the parties’ written

contract. Plaintiff contends that the last day of performance was on February 6, 2004.

Defendant contended that these services constituted warranty services, which were not

part of the contract, but rather subsequent to it. Under defendant’s version, the last day

of performance under the contract was on or before December 31, 2003, when plaintiff

delivered its equipment to defendant’s steel mill.

A. Plaintiff’s Notice of Mechanic’s Lien Claim

Plaintiff cause an original subcontractor’s claim for lien in the amount of

$120,465.26 to be filed with the office of the Cook County Recorder of Deeds on June

22, 2004, as document number 0417432102. Written notice of plaintiff’s lien claim was

sent to defendant on May 4, 2004.

B. Plaintiff’s Equipment Warranty

Plaintiff’s equipment contract contained a “system performance guarantee” which

provided: “If it is determined that the cause of the non-performance (or potential non-

performance) was known or should have been known by [plaintiff], due to their

experience, then [plaintiff] will correct the performance issue at no additional cost to

Fairfield Engineering.” The “second-to-none” system performance guarantee was

written by Jim Ketcham, plaintiff’s regional sales manager, and guaranteed that

plaintiff’s equipment would perform as intended and without Fairfield offering or

3 No. 1-07-0421

providing any engineering design assistance or any additional equipment based on

plaintiff’s final design.

C. Trial Witnesses

Several witnesses testified at trial. Jim Boger is defendant’s plant engineer who

oversaw the installation of the flux delivery system. Scott Schmid is plaintiff’s vice

president of engineering. As noted, Jim Ketcham is plaintiff’s regional sales manager.

John Andrews is plaintiff’s service manager and oversaw the project.

Jim Boger, defendant’s plant manager, testified that he maintained a log,

documenting important points and corresponding dates concerning the project. Based

upon this log, Mr. Boger testified that Phase I of the project, consisting of conveyors 1

and 2, was commissioned and on-line on December 22, 2003. He further testified that

Phase II, consisting of conveyors 3 and 4, was commissioned and on-line on January 9,

2004. Finally, he testified that the last conveyor was commissioned and on-line as of

January 15, 2004. By “commissioned,” Mr. Boger meant that the equipment was

“actually put into production.” Mr. Boger testified that pursuant to the written contract,

plaintiff was not to perform any “start-up” services; rather, Fairfield, defendant’s own

personnel, and another subcontractor, LML, performed “start-up” services. Mr. Boger

testified that plaintiff’s service personnel were present during the “start-up” and initial

operations. He stated that plaintiff’s personnel were on site because the equipment was

experiencing a “plugging” problem. Mr. Boger testified that the plugging was primarily

4 No. 1-07-0421

due to the fact that the injection lines were too small, which prevented sufficient airflow

to propel material into the furnace(s).

Scott Schmid, plaintiff’s vice president, testified that he visited the steel mill on

December 29 through December 31 of 2003 to address the plugging problem and

determined it was due to improper sizing of valves and elbows. He modified the system

to increase airflow. Mr. Schmid testified that plaintiff did not bill defendant for these

visits because plaintiff treated the plugging problem as a warranty issue. He testified that

he was aware of three separate categories of warranty issues with respect to plaintiff’s

equipment: (1) plugging, which commenced at the initial start-up of Phase I; (2)

excessive and premature wear and abrasion (regarding pinch valves and flexible

connectors); and (3) problems getting Phase III, the coal injection system, operational

(this equipment did not function as designed until April 2004). With respect to Phase III,

Mr. Schmid testified that LML commissioned conveyor 5.

Jim Ketcham, plaintiff’s regional sales manager, testified that he attended a pre-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gausselin v. Commonwealth Edison Co.
631 N.E.2d 1246 (Appellate Court of Illinois, 1994)
Clean World Engineering, Ltd. v. Midamerica Bank
793 N.E.2d 110 (Appellate Court of Illinois, 2003)
Samour, Inc. v. Board of Election Commissioners
866 N.E.2d 137 (Illinois Supreme Court, 2007)
Lundy v. Boyle Industries, Inc.
361 N.E.2d 321 (Appellate Court of Illinois, 1977)
Miller Bros. Industrial Sheet Metal Corp. v. La Salle National Bank
255 N.E.2d 755 (Appellate Court of Illinois, 1969)
Merchants Environmental Industries, Inc. v. SLT Realty Ltd. Partnership
731 N.E.2d 394 (Appellate Court of Illinois, 2000)
Maple v. Gustafson
603 N.E.2d 508 (Illinois Supreme Court, 1992)
Caruso v. Kafka
638 N.E.2d 663 (Appellate Court of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Cyclonaire v. ISG Riverdale, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cyclonaire-v-isg-riverdale-illappct-2007.