Gaston Cty. Bd. of Educ. v. Shelco

CourtCourt of Appeals of North Carolina
DecidedAugust 16, 2022
Docket21-618
StatusPublished

This text of Gaston Cty. Bd. of Educ. v. Shelco (Gaston Cty. Bd. of Educ. v. Shelco) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gaston Cty. Bd. of Educ. v. Shelco, (N.C. Ct. App. 2022).

Opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

2022-NCCOA-550

No. COA21-618

Filed 16 August 2022

Gaston County, No. 20-CVS-3924

GASTON COUNTY BOARD OF EDUCATION, Plaintiff,

v.

SHELCO, LLC, S&ME, INC., BOOMERANG DESIGN, P.A. (F/K/A MBAJ ARCHITECTURE, INC.), AND CAMPCO ENGINEERING, INC., Defendants / Crossclaim and Third-Party Plaintiff,

HOOPAUGH GRADING COMPANY, LLC; HART WALL AND PAVER SYSTEMS, INC.; WORLDWIDE ENGINEERING, INC.; AND LINCOLN HARRIS, LLC, Third- Party Defendants.

Appeal by Plaintiff and appeal by two of the Defendants, both from an order

entered 13 May 2021 by Judge Athena F. Brooks in Gaston County Superior Court.

Heard in the Court of Appeals 24 May 2022.

Tharrington Smith, L.L.P., by Patricia Ryan Robinson, Rod Malone and Colin A. Shive for the Plaintiff-Appellant.

Hedrick Gardner Kincheloe & Garofalo LLP, by Gerald A. Stein, II, Tyler A. Stull and M. Duane Jones for Defendant-Appellant (Shelco).

Parker Poe Adams & Bernstein LLP, by Collier R. Marsh and Daniel K. Knight, for Defendant-Appellant (Boomerang).

Ragsdale Liggett PLLC, by Sandra Mitterling Schilder and Amie C. Sivon, for Defendant-Appellee (S&ME). GASTON CTY. BD. OF EDUC. V. SHELCO, LLC

Opinion of the Court

Rosenwood, Rose & Litwak, PLLC by Nancy S. Litwak and Carl J. Burchette for Defendant-Appellee (Campco).

DILLON, Judge.

¶1 The four Defendants each moved to dismiss Plaintiff’s claims based on the

applicable statute of repose. The trial court granted the motions to dismiss filed by

two of the Defendants. Plaintiff appeals from those portions of the order.

¶2 The trial court, however, denied the motions to dismiss filed by the other two

Defendants. These two Defendants appeal from those portions of the order.

¶3 In its order, the trial court also allowed in part and denied in part Plaintiff’s

motion to amend its complaint to allege the existence of an agreement to toll the

statute of repose for 18 months.

I. Background

¶4 Plaintiff, a county board of education, filed this action against four companies

who worked on the development of a public high school. This appeal concerns

primarily the motions to dismiss filed by Defendants pursuant to Rule 12(b)(6) of our

Rules of Civil Procedure. Accordingly, for our review, we must accept the allegations

pleaded in Plaintiff’s complaint as true. See Arnesen v. Rivers Edge, 368 N.C. 440,

441, 781 S.E.2d 1, 3 (2015). Our review is therefore confined to the allegations in the

complaint, which include the following: GASTON CTY. BD. OF EDUC. V. SHELCO, LLC

¶5 Sometime prior to 2009, Plaintiff announced plans to develop a new public high

school (“the Project”). To that end, Plaintiff entered separate contracts with three of

the Defendants: Shelco, LLC, (“Contractor”); S&ME, Inc. (“Engineer”); and

Boomerang Designs, P.A., (“Architect”). Architect entered a contract with the fourth

Defendant, Campco Engineering, Inc., (“Subcontractor”).

¶6 The Project included, in part, the construction of reinforced soil slopes and

retaining walls (collectively the “Retaining Walls”) around the proposed high school’s

athletic complex. Around 2011, construction of the Retaining Walls was completed.

In 2012, Plaintiff became aware that portions of the Retaining Walls had cracked.

¶7 On 15 May 2013, Plaintiff, Contractor, and Architect “signed a certificate of

substantial completion” for the entire Project. By signing the certificate, Contractor

and Architect represented that the Project (including the Retaining Walls) was

essentially completed. Engineer and Subcontractor did not sign the certificate.

¶8 In the fall of 2018, Plaintiff, along with Contractor, Engineer, Architect and

Subcontractor (along with some third-party defendants) executed a tolling agreement

(the “Tolling Agreement”) at Plaintiff’s request with a stated effective date of 1 March

2019 until 15 September 2020.

¶9 Then in November 2020, Plaintiff filed suit against all four Defendants,

alleging that the Retaining Walls were defective. Defendants answered and moved

to dismiss pursuant to Rule 12(b)(6), based in part on the six-year statute of repose. GASTON CTY. BD. OF EDUC. V. SHELCO, LLC

Plaintiff then moved to amend its complaint to allege that all parties had entered the

Tolling Agreement, effective 1 March 2019 to 15 September 2020.

¶ 10 After a hearing on all motions, the trial court entered its order (1) allowing

Subcontractor’s and Engineer’s respective Rule 12(b)(6) motions to dismiss based on

the statute of repose (and dismissing Plaintiff’s motion to amend as to its claims

against Subcontractor and Engineer, as moot); and (2) denying Contractor’s and

Architect’s respective Rule 12(b)(6) motions to dismiss based on the statute of repose

(allowing Plaintiff’s motion to amend its complaint as to its claims against Contractor

and Architect). The trial court reasoned that the May 2013 certificate executed by

Plaintiff, Contractor, and Architect, paired with the Tolling Agreement, placed

Plaintiff’s claims against Contractor and Architect within the 6-year statute of

repose. However, since Engineer and Subcontractor did not sign the 2013 certificate,

the Tolling Agreement would not place Plaintiff’s claims against them within the

statute of repose.

¶ 11 Plaintiff appealed the Rule 12(b)(6) dismissals and denial of its motion to

amend its complaint regarding its claims against Engineer and Subcontractor.

Contractor and Architect appealed the denial of Rule 12(b)(6) motions on Plaintiff’s

claims against them.

II. Appellate Jurisdiction

¶ 12 This appeal is from an interlocutory order, as that order did not entirely GASTON CTY. BD. OF EDUC. V. SHELCO, LLC

dispose of the case. Stanford v. Paris, 364 N.C. 306, 311, 698 S.E.2d 37, 40 (2010).

Appeals from interlocutory orders are only allowed in limited circumstances. Id. at

311, 698 S.E.2d at 40. Rule 54(b) of our Rules of Civil Procedure allows an immediate

appeal from an interlocutory order from any part of an order which constitutes a “final

judgment as to one or more but fewer that all the claims or parties[,]” so long as the

trial court in its judgment determines “there is no just reason for delay” in taking the

appeal. N.C. Gen. Stat. § 1A-1, Rule 54(b).

¶ 13 Here, the trial court’s order constitutes a final judgment with respect to

Subcontractor and Engineer, as the order dismisses all claims against these

Defendants with prejudice. Additionally, the trial court certified its order dismissing

these claims for immediate review under Rule 54(b), determining “there was no just

reason for delay.” Accordingly, we have jurisdiction to consider Plaintiff’s appeal of

the portion of the trial court’s order allowing Subcontractor’s and Engineer’s

respective motions to dismiss and mooting its motion to amend with respect to these

Defendants.

¶ 14 However, there has been no final judgment with respect to Plaintiff’s claims

against Contractor and Architect. Rule 54(b), therefore, does not provide an avenue

for immediate review of the portion of the trial court’s order denying these

Defendants’ respective motions to dismiss. Further, we have held that an adverse

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boudreau v. Baughman
368 S.E.2d 849 (Supreme Court of North Carolina, 1988)
Hargett v. Holland
447 S.E.2d 784 (Supreme Court of North Carolina, 1994)
Hayes v. City of Wilmington
91 S.E.2d 673 (Supreme Court of North Carolina, 1956)
RICHLAND RUN HOMEOWNERS ASSOCIATION, INC. v. CHC Durham Corp.
473 S.E.2d 649 (Court of Appeals of North Carolina, 1996)
Stanford v. Paris
698 S.E.2d 37 (Supreme Court of North Carolina, 2010)
Lee v. Baxter
556 S.E.2d 36 (Court of Appeals of North Carolina, 2001)
Arnesen v. Rivers Edge Golf Club and Plantation, Inc.
781 S.E.2d 1 (Supreme Court of North Carolina, 2015)
Head v. Gould Killian Cpa Grp., P.A.
812 S.E.2d 831 (Supreme Court of North Carolina, 2018)
Richland Run Homeowners Ass'n v. CHC Durham Corp.
484 S.E.2d 527 (Supreme Court of North Carolina, 1997)
Lawrence ex rel. Situated v. Gen. Panel Corp.
822 S.E.2d 800 (Supreme Court of South Carolina, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Gaston Cty. Bd. of Educ. v. Shelco, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gaston-cty-bd-of-educ-v-shelco-ncctapp-2022.