Gallagher Switchboard Corp. v. Heckler Electric Co.

34 Misc. 2d 256, 229 N.Y.S.2d 623, 1962 N.Y. Misc. LEXIS 3314
CourtNew York Supreme Court
DecidedMay 14, 1962
StatusPublished
Cited by10 cases

This text of 34 Misc. 2d 256 (Gallagher Switchboard Corp. v. Heckler Electric Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gallagher Switchboard Corp. v. Heckler Electric Co., 34 Misc. 2d 256, 229 N.Y.S.2d 623, 1962 N.Y. Misc. LEXIS 3314 (N.Y. Super. Ct. 1962).

Opinion

Walter R. Hart, J.

Plaintiff moves as follows: (a) for summary judgment under rules 113 and 114 of the Rules of Civil Practice, on the amended complaint’s first cause of action [258]*258against defendant Heckler Electric Company, Inc. (hereinafter referred to as “Heckler” or simply “defendant”); (b) for judgment pursuant to subdivision 7 of rule 110 of the Rules of Civil Practice, dismissing the counterclaim set up in defendant’s answer in that the claim constituting said counterclaim has been released, or, in the alternative, for summary judgment dismissing said counterclaim pursuant to rules 113 and 114 of the Rules of Civil Practice; (c) for an order striking the second separate and affirmative defense from defendant’s answer as being insufficient in law (Rules Civ. Prac., rule 109, subd. 6) and (d) for an order striking the words “ under duress ” from paragraph 6 of defendant’s answer (Rules Civ. Prac., rule 103).

Defendant Heckler cross-moves to dismiss the first and third causes of action of the amended complaint as being legally insufficient (Rules Civ. Prac., rule 92; rule 108, subd. 4).

The facts, so far as needful to a comprehension of the issues here involved are briefly as follows:

Defendant Heckler placed with the plaintiff a purchase order for the furnishing and delivery to it by plaintiff of certain specified electrical equipment. Said equipment was required by defendant in connection with the performance of a contract entered into by defendant with the City of New York, acting through the Department of Public Works, calling for the modification of electrical facilities located in the Municipal Building in the Borough of Brooklyn. Defendant’s purchase order was dated March 10, 1960 and was accepted by plaintiff on March 17, 1960. Thereafter, and in the course of the performance of said agreement, certain disputes arose between plaintiff and defendant with regard to the deliveries and payments called for by the agreement. Thereupon the parties signed an agreement dated September 25, 1961 which, among other things, established an “arbitrary value” for certain circuit breaker take-off devices remaining to be delivered under the purchase order agreement of March, 1960, and which provided, further, for delivery of said items to defendant on a O. O. D. basis. It is claimed by plaintiff that the defendant’s retention of the afore-mentioned items, upon their subsequent delivery to defendant, without making payment on delivery as required under the agreement of September 25,1961, constituted an unlawful withholding and detention of said chattels.

The amended complaint consists of three causes of action as follows: The first cause of action charges defendant Heckler with wrongfully and unlawfully taking possession and detaining from plaintiff certain chattels owned by plaintiff, to wit, 22 circuit breaker take-off steel boxes and contents hereinabove [259]*259referred to. The second cause of action, which is brought against all three defendants named in the action, seeks recovery on a mechanic’s lien filed with the defendant City of New York and bonded by defendant Seaboard Surety Company, covering a balance of $33,301.81 allegedly due from defendant Heckler to plaintiff under the purchase order agreement of March, 1960 as modified by the purported written agreement entered into between plaintiff and defendant Heckler dated September • 25, 1961. The third cause of action is one to recover the agreed “fair and reasonable value” of $52,931 for “extra” work, labor, services and materials allegedly furnished by plaintiff to defendant at defendant’s “ special instance and request.”

The answer interposed by defendants Heckler and Seaboard Surety contains denials and two affirmative defenses and, in addition, a counterclaim on behalf of defendant Heckler. The first separate defense alleges payment. The second separate defense, which is here sought to be stricken from the answer as being insufficient, alleges that the plaintiff is not entitled to recover in the action since the purchase-order agreement of March, 1960 was breached by the plaintiff in that said party ‘ ‘ failed to deliver the materials as agreed, failed to deliver materials within prescribed times, supplied and furnished defective materials and materials which were incomplete and unfinished, failed, omitted and refused to deliver drawings required by the terms of the agreement and shop drawings within the time or times prescribed therein ”. The defense further alleges that the document purporting to be a contract dated September 25, 1961 is null and void and without any legal effect in that it was entered into by defendant under plaintiff’s threat to withhold all further labor and materials required to be furnished to the defendant under the agreement of March, 1960 and to 11 cause the defendant, Heckler, additional hardship in the completion and performance of its obligations under the terms and conditions of its said contract with the City, and to cause said defendant substantial economic loss ” unless the defendant entered into an agreement with the plaintiff modifying the written agreement of March, 1960; and, that the defendant thereupon signed the agreement of March 25, 1961 ‘ ‘ in order to meet its obligations with the City and to avoid further delay and economic loss ”.

The counterclaim on behalf of defendant Heckler, set forth in the answer, asserts that said defendant was damaged by reason of delays and disruptions caused by plaintiff’s breach of the agreement of March, 1960 and by the refusal of said plaintiff to deliver the materials and drawings which it was obligated to [260]*260furnish under the aforesaid agreement unless the defendant signed the purported agreement dated September 25,1961.

The reply to the aforesaid counterclaim, in addition to generally denying the allegations of the counterclaim, asserts an affirmative defense of accord and satisfaction based on the above-mentioned agreement of September, 1961.

Turning attention first, in the interests of logical sequence, to a consideration of defendant’s cross motion for dismissal of the first and third causes of action of the amended complaint for insufficiency, the court reaches the view that the challenge directed against said causes of action on this motion is not sustainable. There is no merit to the claim that the failure to allege performance by the plaintiff of conditions precedent of the contract on its part to be performed renders the first cause of action insufficient. The cause of action clearly is in replevin and, therefore, the foregoing requirement, which relates to actions in contract, is not applicable. The merits of the cause of action, or any form of objection such as was sought to be raised in defendant’s reply affidavit, based on grounds other than legal insufficiency, may not be considered on this motion. Similarly, the third cause of action, as has hereinabove been pointed out, is in quantum meruit for “extra” work, labor, services and materials allegedly furnished to defendant, and appears not to be founded on any express contract or, specifically, on either of the agreements expressly pleaded in the amended complaint; hence, there is no requirement that plaintiff allege performance of conditions precedent. (See 3 CarmodyWait, New Tork Practice, pp. 607-608; cf. Royle v. McLaughlin, 195 App. Div. 413.)

The defendant’s cross motion is, therefore, in all respects denied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Austin Instrument, Inc. v. Loral Corp.
35 A.D.2d 387 (Appellate Division of the Supreme Court of New York, 1970)
A. Alport & Son, Inc. v. Hotel Evans, Inc.
65 Misc. 2d 374 (New York Supreme Court, 1970)
Tomkins Lakes Estates Ass'n v. Speisman
51 Misc. 2d 488 (New York Supreme Court, 1966)
Mutual ReDevelopment Houses, Inc. v. Hanft
42 Misc. 2d 1044 (Civil Court of the City of New York, 1964)
Frank M. Herbert, Inc. v. M & P Scrap Iron & Metal Corp.
41 Misc. 2d 1020 (New York Supreme Court, 1964)
Belmet Products, Inc. v. Merit Enterprises, Inc.
37 Misc. 2d 368 (Civil Court of the City of New York, 1963)
Gallagher Switchboard Corp. v. Heckler Electric Co.
36 Misc. 2d 225 (New York Supreme Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
34 Misc. 2d 256, 229 N.Y.S.2d 623, 1962 N.Y. Misc. LEXIS 3314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gallagher-switchboard-corp-v-heckler-electric-co-nysupct-1962.