Gainesville Mechanical, Inc. v. Air Data, Inc.

CourtCourt of Appeals of Georgia
DecidedJune 19, 2019
DocketA19A0518
StatusPublished

This text of Gainesville Mechanical, Inc. v. Air Data, Inc. (Gainesville Mechanical, Inc. v. Air Data, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gainesville Mechanical, Inc. v. Air Data, Inc., (Ga. Ct. App. 2019).

Opinion

FIRST DIVISION BARNES, P. J., MERCIER and BROWN, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. http://www.gaappeals.us/rules

June 19, 2019

In the Court of Appeals of Georgia A19A0518. GAINESVILLE MECHANICAL, INC. v. AIR DATA, INC.

BROWN, Judge.

Gainesville Mechanical, Inc. appeals from an order of the superior court

confirming an arbitration award in favor of Air Data, Inc. Gainesville Mechanical

contends that the superior court erred by failing to conclude that the arbitrator’s

written award demonstrates a manifest disregard of the law. For the reasons explained

below, we disagree and affirm.

Absent one of the statutory grounds listed in OCGA § 9-9-13 (b), a superior

court must confirm an arbitration award; on appeal, this Court “will not reverse an

order confirming an award unless the appellant demonstrates that a statutory ground

exists.” Airtab v. Limbach Co., 295 Ga. App. 720, 721 (673 SE2d 69) (2009). The only statutory ground relevant to this case is whether the rights of Gainesville

Mechanical “were prejudiced by . . . [t]he arbitrator’s manifest disregard of the law.”

OCGA § 9-9-13 (b) (5). “[A]s provided in the statute, a showing of prejudice is

required” and “the burden of proof is on the one seeking to set aside an award.”

Bennett v. Builders II, 237 Ga. App. 756, 757 (3) (516 SE2d 808) (1999). In this case,

the arbitrator’s award reflects that it received evidence over the course of six days of

hearings, but the record before us does not include a transcript of the arbitration

proceedings. Accordingly, Gainesville Mechanical attempts to show prejudice from

the arbitrator’s alleged manifest disregard of the law solely from the face of the

arbitrator’s 14-page “Final Award.”

In its order, the arbitrator summarized the evidence briefly and determined that

Gainesville Mechanical paid Air Data only $32,000, less than half the $72,770 it was

entitled to under its contract.1 It also determined that due to the directive of a general

contractor on the construction project, Gainesville Mechanical instructed Air Data to

1 As best we can determine from the limited record before us, Gainesville Mechanical installed a mechanical system for McCarthy Building Company, Inc., the general contractor for the construction of the Georgia State University Humanities and Law Building. Gainesville Mechanical then entered into a subcontract with Air Data under which Air Data would test, adjust, and balance the HVAC system for the building.

2 work 7 days a week for 10 hours a day for an extended period of time. Additionally,

the arbitrator concluded that Gainesville Mechanical required Air Data to conduct

testing on mechanical systems before the building was enclosed and even before

Gainesville Mechanical’s work and that of other trades was complete in the very areas

where Air Data was asked to test. Gainesville Mechanical ultimately fired Air Data

and hired another contractor to perform the work at a cost of over $149,985, at a time

when the building was opened and occupied and the work could be performed by a

single employee.

After outlining these facts, the arbitrator concluded that

[w]hile only rarely governing a construction dispute, the Arbitrator determines that the facts of this case call for the application of the legal doctrine of cardinal change. . . . While the term cardinal change is primarily utilized in Federal Government construction cases, Georgia and other states often adopt other terminology such as quantum meruit, abandonment of contract, and fundamental breach. A Nevada decision explained: The cardinal change doctrine serves to provide a breach remedy for contractors who are directed to perform work which is not within the general scope of the contract and which is not redressable under the contract. Thus a cardinal change occurs when the work is so drastically altered that the contractor effectively performs duties that are materially different from those which the contractor originally bargained.

3 (Punctuation omitted; emphasis omitted.) Later in his order, the arbitrator stated:

Based upon the Arbitrator’s findings as to the above pertinent occurrences on the project, the final step is to assign damages resulting from these occurrences. Air Data claims entitlement to: 1. Compensatory damages of $258,704. 2. Interest of $144,000 through December 17, 2017. 3. $151,384 for attorneys’ fees, and 4. $16,500 for AAA expenses. Air Data contends it has asserted, not a total cost claim for damages arising in connection with its . . . work . . . , but rather a modified total cost claim by reducing its total costs incurred by 5%. . . . The Arbitrator is well aware that total costs claims, even modified total costs claims allegedly such as that here, are disfavored by the courts unless four conditions are found present: 1. The nature of the particular losses makes it impossible or highly impractical to determine them with a reasonable degree of accuracy; 2. The plaintiff’s bid or estimate was realistic; 3. Its actual costs were reasonable; and 4. It was not responsible for the added expenses. Delta Metals, Inc. v. RM Wells, 497 FSupp 541, 545 (S. D. Ga. 1980). Air Data’s “modified” total cost approach meets the first and second criteria, but not the third criteria, and certainly not the fourth. Despite Air Data’s failure to clearly meet all four criteria, especially the fourth criterion “that Air Data was not responsible for the added

4 expenses,” the Arbitrator is of the view that it is entitled to relief and that the first criterion is clearly met - “The nature of the particular losses makes it impossible or highly impractical to determine with a reasonable degree of accuracy.” Accordingly the arbitrator may not award Air Data all its claimed losses, but certainly a substantial portion of them. Thus, the Arbitrator determines that Air Data is entitled to compensatory damages of $185,000.

(Emphasis supplied.)

On appeal, Gainesville Mechanical asserts that this paragraph shows that the

arbitrator manifestly disregarded the law governing the “modified total cost”

approach to damages. “[M]anifest disregard of the law requires (1) that the governing

law alleged to have been disregarded is well defined, explicit and clearly applicable

and (2) proof that the arbitrator was aware of the law but decided to ignore it.”

Johnson Real Estate Investments v. Aqua Indus., 282 Ga. App. 638, 640 (1) (639

SE2d 589) (2006). “[T]his showing is an extremely difficult one to make, especially

in light of the fact that an arbitrator is not required to make findings of fact or state

his or her rationale in reaching decisions.” ABCO Builders v. Progressive Plumbing,

282 Ga. 308, 309 (647 SE2d 574) (2007). When examining this statutory ground, we

must keep in mind that “an arbitrator that incorrectly interprets the law has not

manifestly disregarded it, but has simply made a legal mistake.” (Citations,

5 punctuation and footnote omitted.) Fulton County v. Lord, 323 Ga. App. 384, 388

(746 SE2d 188) (2013).

In this case, the contract between the parties provided that it would be

governed by Georgia law, listed Georgia addresses for both parties, and related to

work to be performed in Georgia. Additionally, Georgia is the forum state.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montes v. Shearson Lehman Brothers
128 F.3d 1456 (Eleventh Circuit, 1997)
Metropolitan Atlanta Rapid Transit Authority v. Green International, Inc.
509 S.E.2d 674 (Court of Appeals of Georgia, 1998)
Johnson Real Estate Investments, LLC v. Aqua Industrials, Inc.
639 S.E.2d 589 (Court of Appeals of Georgia, 2006)
Airtab, Inc. v. Limbach Co., LLC
673 S.E.2d 69 (Court of Appeals of Georgia, 2009)
Greene v. Hundley
468 S.E.2d 350 (Supreme Court of Georgia, 1996)
Bennett v. Builders II, Inc.
516 S.E.2d 808 (Court of Appeals of Georgia, 1999)
ABCO Builders, Inc. v. Progressive Plumbing, Inc.
647 S.E.2d 574 (Supreme Court of Georgia, 2007)
Jenna Newstrom v. Auto-Owners Insurance Company
807 S.E.2d 501 (Court of Appeals of Georgia, 2017)
Fulton County v. Lord
746 S.E.2d 188 (Court of Appeals of Georgia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Gainesville Mechanical, Inc. v. Air Data, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/gainesville-mechanical-inc-v-air-data-inc-gactapp-2019.