Gainesville Glass Co. v. Don Hammond, Inc.

278 S.E.2d 182, 157 Ga. App. 640, 1981 Ga. App. LEXIS 1949
CourtCourt of Appeals of Georgia
DecidedFebruary 24, 1981
Docket60950
StatusPublished
Cited by23 cases

This text of 278 S.E.2d 182 (Gainesville Glass Co. v. Don Hammond, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gainesville Glass Co. v. Don Hammond, Inc., 278 S.E.2d 182, 157 Ga. App. 640, 1981 Ga. App. LEXIS 1949 (Ga. Ct. App. 1981).

Opinion

Carley, Judge.

Appellee-Don Hammond, Inc., general contractor for the construction of a recreational center at Lake Lanier Islands, instituted suit against appellant-Gainesville Glass Company, Inc., a purported subcontractor. According to the allegations of appellee’s complaint, the appellant had orally agreed to supply and install the windows in the project for the sum of $2,003. However, when the appellee called upon the appellant to perform the window work the appellant refused to do so for the agreed contract price. When appellant refused to honor its agreement, the appellee secured the services of another glass company which supplied and installed the windows in the center for a cost of $7,253.95. The appellee instituted suit against appellant for $5,250.95, the difference between the ultimate cost to appellee of obtaining and installing windows in the center and appellant’s alleged agreement to do the work for $2,003. The jury returned a verdict for the appellee in the full amount prayed for and judgment was entered thereon. Appellant appeals.

1. Appellant argues that the evidence “failed to show any agreement, contract, or meeting of the minds between the parties that would bind [appellant] at the time performance was de *641 manded.” Appellant’s argument in support of this contention does not raise the issue of the statute of frauds. But see Cason v. Thomas Cheely & Co., 6 Ga. 554 (1849); Campbell & Co. v. Mion Bros., 6 Ga. App. 134 (64 SE 571) (1909). Appellant’s arguments relate solely to the failure of the evidence to show the formal requisites of a contract. After a very careful and thorough review of the evidence, we agree that the evidence fails to support a finding of appellant’s contractual liability to the appellee.

The appellee’s evidence showed that it solicited and received an offer by appellant to do the window work on the center for $2,003. The appellee relying on this “offer” by appellant, submitted its bid on the project and was awarded the contract. The evidence further showed that the owner of the project wanted to have an option, to be exercised by April 1,1978, to elect to delete the windows as an element of the construction contract. While appellant’s evidence disputed the fact, the appellee’s evidence showed that it contacted appellant and requested that such an option be extended to it. However, this was not an “acceptance” of appellant’s original offer to do the work; it was a counteroffer by the appellee to appellant. Winder Mfg. Co. v. Pendleton Co., 27 Ga. App. 476 (108 SE 823) (1921); Estes Lumber Co. v. Palmyra Yellow Pine Co., 29 Ga. App. 15 (113 SE 821) (1922). The undisputed evidence further shows that appellant did not accept this counteroffer by appellee. Rather appellant made its own counteroffer, to the effect that it would agree to extend its offer with the option to cancel by April 1, 1978, in return for appellee’s agreement that, if the option to cancel was not exercised, the final contract price for performance would be $2,003 plus any increase in the cost of materials which might occur before that date. While the evidence does show that the appellee relayed appellant’s counteroffer concerning contract price to the owner of the project and that the appellee and the owner agreed between themselves that appellant’s counteroffer would be accepted, there was absolutely no evidence by either party that the appellee ever communicated to appellant its acceptance of the counteroffer to grant an option in return for an assurance of material price increase protection. “[I]t is the law of contracts that an acceptance of a bilateral contract requires communication.” Hartford Fire Ins. Co. v. Steenhuis, 115 Ga. App. 625, 626 (155 SE2d 690) (1967). Apparently, the appellee relies upon the fact that, as between itself and the owner, the owner accepted the counterproposal and agreed to pay any increase in material cost in return for the right to delete the windows from the project supplies the necessary contractual element of acceptance as between itself and appellant. However, the counteroffer by appellant was extended to the appellee as general contractor not to the owner and, *642 apparently, the appellee’s “acceptance” of the counteroffer was never communicated to appellant. “The offer can be accepted only by the person or persons to whom it is made.” Milner Hotels v. Black, 196 Ga. 686, 691 (27 SE2d 402) (1943). The appellee’s testimony that appellant “knew” it “had the glass work” even though the acceptance of its counteroffer was never communicated to it in “specific words” does not, in our opinion, show there had been a meeting of the minds so as to create a contractual relationship between the appellee and appellant. Bush & Hattaway v. McCarty Co., 127 Ga. 308 (56 SE 430) (1907); Saunders v. Vikers, 116 Ga. App. 733 (158 SE2d 324) (1967). Nor does the fact that the appellee discussed whether the eventual terms of the agreement would be “satisfactory” to appellant before entering into the agreement with the owner supply the missing contractual element of acceptance by appellee of appellant’s counteroffer. The eventual terms of the agreement were the terms of appellant’s counteroffer and, of course, those terms would be “satisfactory” to it. This evidence shows no more than negotiations between appellant and the appellee, not acceptance by the latter of the former’s counteroffer. Frigidice Co. v. Southeastern Fair Assn., 58 Ga. App. 694 (199 SE 760) (1938). Compare Wilson v. Martin, 27 Ga. App. 549 (109 SE 294) (1921). Therefore, the evidence shows, at most, a counteroffer by appellant to extend to the appellee an option to purchase and have windows installed for an agreed price, the “acceptance” of which by the appellee was never communicated to appellant until long after the option date contemplated in the counteroffer itself had passed. This evidence shows no contract between appellant and the appellee. Cf. Timmons v. Bostwick, 141 Ga. 713, 714 (3) (82 SE 29) (1914).

Appellant further argues that, pretermitting the sufficiency of the evidence to show a contract the amount of damages awarded for the breach thereof is not supported by the evidence. The measure of damages here would be the reasonable cost of completing the window work in the center, that is, the difference between the contract price and the reasonable and necessary cost to appellee to have the windows supplied and installed in accordance with the terms of the original contract. Palmer v. Howse, 133 Ga. App. 619 (212 SE2d 2) (1974). The contract here called for appellee as general contractor and, ultimately, appellant as subcontractor, to “[f|urnish and install pavilion clerestory plexiglass panels.. .as indicated on the drawings.” The evidence adduced at trial was that “plexiglass” is a trade name of a specific product made only by one manufacturer but is a term also used frequently to apply to acrylic products made by different companies. There was no conclusive evidence as to how much plexiglass panels increased in price prior to April 1, 1978. We, *643 therefore, assume that the first component of the measure of damages — the original contract price — was $2,003.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alphamed, Inc. v. B. Braun Medical, Inc.
367 F.3d 1280 (Eleventh Circuit, 2004)
Oasis Goodtime Emporium I, Inc. v. Crossroads Consulting Group, LLC.
565 S.E.2d 573 (Court of Appeals of Georgia, 2002)
Smith v. Direct Media Corp.
544 S.E.2d 762 (Court of Appeals of Georgia, 2001)
Kent v. Brown
518 S.E.2d 737 (Court of Appeals of Georgia, 1999)
Oasis Goodtime Emporium I, Inc. v. Cambridge Capital Group, Inc.
507 S.E.2d 823 (Court of Appeals of Georgia, 1998)
Geriner v. Branigar Organization, Inc.
489 S.E.2d 305 (Supreme Court of Georgia, 1997)
Ghrist v. Fricks
465 S.E.2d 501 (Court of Appeals of Georgia, 1995)
MANNING & ASSOCIATES PERSONNEL, INC. v. Trizec Properties, Inc.
442 S.E.2d 783 (Court of Appeals of Georgia, 1994)
Amalgamated Transit Union Local 1324 v. Roberts
434 S.E.2d 450 (Supreme Court of Georgia, 1993)
Webb v. Hancock Plumbing & Heating Co.
391 S.E.2d 697 (Court of Appeals of Georgia, 1990)
Ideal Pool Corp. v. Hipp
370 S.E.2d 32 (Court of Appeals of Georgia, 1988)
Dubberly v. P. F. Moon & Co.
361 S.E.2d 223 (Court of Appeals of Georgia, 1987)
All American Assurance Co. v. Brown
339 S.E.2d 611 (Court of Appeals of Georgia, 1985)
Southeast Grading, Inc. v. City of Atlanta
324 S.E.2d 776 (Court of Appeals of Georgia, 1984)
Cowen v. Snellgrove
312 S.E.2d 623 (Court of Appeals of Georgia, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
278 S.E.2d 182, 157 Ga. App. 640, 1981 Ga. App. LEXIS 1949, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gainesville-glass-co-v-don-hammond-inc-gactapp-1981.