This text of 293 B.R. 76 (Tidwell v. A & M Check Cashing, Inc. (In re Arrington)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tidwell v. A & M Check Cashing, Inc. (In re Arrington), 293 B.R. 76, 2003 Bankr. LEXIS 342 (Ga. 2003).

Opinion

[78]*78 MEMORANDUM OPINION

ROBERT F. HERSHNER, Jr., Chief Judge.

J. Coleman Tidwell, Chapter 7 Trustee, Trustee, filed objections to the allowance of certain claims on October 24, 2002. A & M Check Cashing, Inc. and Ingleside Florist (collectively “Respondents”) filed responses on November 29, 2002. David L. Arrington, Debtor, filed objections to Respondents’ claims on December 26, 2002, and January 21, 2003. The objections to claims came on for hearing on January 22, 2003, and February 25, 2003. The Court, having considered the record and the arguments of counsel, now publishes this memorandum opinion.

Debtor owned an interest in certain commercial real property (the “realty”).1 There was a pending contract to sell the realty for more than $1 million. Respondents believed that Debtor’s share of the net proceeds would total some $300,000. Respondents and a third creditor, Snead & Associates, were concerned that Debtor would sell the realty, but would not use the proceeds to satisfy his obligations.

Respondents and Snead & Associates filed on April 4, 2002, an^involuntary petition under Chapter 7 of the Bankruptcy Code against Debtor.2 The Court entered an order scheduling an expedited hearing for the appointment of an interim trustee. The hearing was set for April 11, 2002. Debtor filed on April 11, 2002, a number of motions in response to the involuntary petition.3

An amendment to the involuntary petition was filed on April 11, 2002. The amendment adds Larry A. Williams and Pete Welborne as petitioning creditors.

Debtor reached an agreement with Respondents and the other petitioning creditors. The terms of the settlement agreement were announced in open court on April 11, 2002. Debtor consented to the entry of an order for relief under Chapter 7 of the Bankruptcy Code.4 Debtor agreed to withdraw his motions. Respondents and the other petitioning creditors agreed to file their proofs of claim within ten days.5 Mark Roadarmel, Assistant United States Trustee, announced that he would expedite the appointment of a Chapter 7 trustee so that the trustee could review the pending sale of Debtor’s realty.6 The settlement agreement announced in open court did not address the consequences of any party’s failure to perform under the terms of the agreement.

Debtor, on April 11, 2002, withdrew his motions filed in response to the involuntary petition. The Court entered on April 11, 2002, an order for relief under 11 U.S.C.A. § 303. J. Coleman Tidwell was appointed to be the Chapter 7 Trustee.

Respondents and the other petitioning creditors failed to file proofs of claim within ten days (that is, by April 21, 2002). Respondents’ counsel concedes that he simply neglected to file the proofs of claim.

The Clerk of Court sent a notice dated April 19, 2002, advising that creditors must file proofs of claim on or before July 18, [79]*792002, (“the bar date”).7 Respondents,8 Mr. Williams, Mr. Welborne,9 and a number of other creditors filed proofs of claim prior to the bar date. Snead & Associates did not file a proof of claim.

Debtor filed his bankruptcy schedules on April 26, 2002. Debtor listed as disputed his obligations to Respondents. Debtor noted on an attachment to Schedule F that the claims of Respondents and the other petitioning creditors “are barred by failure to comply with the agreement. The claims were not filed within [ten] days.”

The Court entered an order on July 19, 2002, granting Debtor a discharge from all dischargeable obligations. Trustee has liquidated Debtor’s commercial realty. The assets of the bankruptcy estate may be sufficient to pay all claims in full and return a dividend to Debtor.

Trustee and Debtor argue that Respondents’ claims should be disallowed because the claims were not filed within ten days.10 Debtor argues that he relied upon the ten-day commitment in agreeing to dismiss his motions.

In Schwartz v. Florida Board of Regents,11 the Eleventh Circuit Court of Appeals stated, in part, as follows:

The construction of the settlement agreement is a question of law subject to de novo review by this court. A settlement agreement is a contract and, as such, its construction and enforcement are governed by principles of Florida’s general contract law. Words in a contract are to be given their plain and ordinary meaning, and it is not for the court to add or subtract any language from the face of a clearly worded agreement. Nor is the court to add to a settlement terms that were not contemplated by the parties. The court’s role is to determine the intention of the parties from the language of the agreement, the apparent objects to be accomplished, other provisions in the agreement that cast light on the question, and the circumstances prevailing at the time of the agreement.

807 F.2d at 905.

“An agreement to settle a legal dispute is a contract.... The enforceability of settlement agreements is governed by familiar principles of contract law. A settlement contract may not be unilaterally rescinded. Upon breach by one party, the other party may obtain damages or specific performance as appropriate.” Village of Kaktovik v. Watt, 689 F.2d 222, 230 (D.C.Cir.1982).

‘Where the parties, acting in good faith, settle a controversy, the courts will enforce the compromise without regard to what the result might, or would have been, had the parties chosen to litigate rather than settle.” J. Kahn & Co. v. Clark, 178 F.2d 111, 114 (5th Cir.1949).

“[T]he fact that the [settlement] agreement is not in writing does not render it unenforceable.” Hensley v. Alcon [80]*80Laboratories, Inc., 277 F.3d 535, 540 (4th Cir.2002).

Georgia law may provide the remedy for Respondents’ breach of the settlement agreement. Resnick v. Uccello Immobilien GMBH, Inc., 227 F.3d 1347, 1350 n. 4 (11th Cir.2000) (“Because this settlement agreement is between two private parties, federal common law does not apply.”) (state contract law applies even though settlement agreement arose under the American with Disabilities Act); Hayes v. National Service Industries, 196 F.3d 1252 (11th Cir.1999) (applying Georgia law to construction and enforceability of settlement agreement arising under federal employment discrimination claim).

Under both federal law and state law, the usual remedy for breach of a settlement agreement is monetary damages or specific performance. See Penobscot Indian Nation v. Key Bank of Maine, 112 F.3d 538, 558 n. 28 (1st Cir.), cert. denied, 522 U.S. 913, 118 S.Ct. 297, 139 L.Ed.2d 229 (1997); TNT Marketing, Inc. v. Agresti

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ARGUELLES v. NIELSEN
M.D. Georgia, 2023

Cite This Page — Counsel Stack

Bluebook (online)
293 B.R. 76, 2003 Bankr. LEXIS 342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tidwell-v-a-m-check-cashing-inc-in-re-arrington-gamb-2003.