State Highway Department v. Knox-Rivers Construction Co.

160 S.E.2d 641, 117 Ga. App. 453
CourtCourt of Appeals of Georgia
DecidedMarch 11, 1968
Docket43014
StatusPublished
Cited by10 cases

This text of 160 S.E.2d 641 (State Highway Department v. Knox-Rivers Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Highway Department v. Knox-Rivers Construction Co., 160 S.E.2d 641, 117 Ga. App. 453 (Ga. Ct. App. 1968).

Opinion

Whitman, Judge.

Whether the plaintiff’s petition states a cause of action, as against the defendant’s general demurrers, is to be resolved, as both parties point out in their briefs, by *455 ascertaining from the contract upon whom the duty fell to locate a new source of soil for the road building project when the first soil pit failed.

The plaintiff’s position is best illustrated by certain allegations in its petition, to wit:

(6) That the defendant provided petitioner with plans showing the location of a certain soil pit to be used for the acquisition of soil to be mixed with mortar and gravel which would then become part of the base or foundation for said road.

"(7) That petitioner began work under said contract, located its base plant near said soil pit, and attempted to use said pit which had been secured by the defendant; however, said soil pit was subsequently rejected by the engineers of the defendant contending that said pit was unfit for use in said road construction project.

“(7-a) That the defendant has failed to perform its duty under § 6.01, Paragraph B, Subparagraphs 3 and 5 (pages 67 and 68) of its standard specifications Volume I, dated May 1, 1956, which are by stipulation before the court, in that the defendant failed: (1) To eliminate the plaintiff’s first source of soil material by written order and to substitute another source; (2) To identify a new source and to provide petitioner with an estimate of the quantities of clearing, stripping and overhaul required at the new source; (3) To order in writing that the pit plant be moved to another source selected by the engineer of the defendant.

“(8) That notwithstanding the duty upon the defendant to find an alternative soil pit location which would be suitable for use by the petitioner, the petitioner was forced, because of the defendant’s nonfeasance, to obtain sufficient soil from a total of six (6) other soil pits at various locations, all of which involved considerable time and expense to the petitioner, and resulted in a higher unit price for said soil and a longer haul to point of consumption than originally anticipated by the petitioner at the time its bid was submitted and the contract entered into between petitioner and defendant.

(9) That as a result of the failure of the defendant to locate satisfactory soil pits, and because the petitioner was forced to *456 locate same in. order to- expedite the work under said contract, the petitioner suffered a work shutdown and delay during which its men and equipment assigned to its base plant operation could not be productively used and as a result petitioner was penalized for a delay of seventy-four (74) calendar days.”

The provisions of the contract relating to the difficulty éncountered on the project are found in the Highway Department’s Standard Specifications, as amended by a Special Provision, and read as follows:

“§ 6.01 Source of Supply and Quality of Materials: The source for each of the materials specified shall have been approved by the Engineer before delivery is started. Only materials meeting these specifications shall be used. If it is found after trial that sources of supply previously approved do not produce uniform and satisfactory products, or if the product from any source proves unacceptable after approval, the contractor shall furnish materials from other approved sources, except as provided in Article'6.01 b, below. . .

“b. Sources of Materials Outside the Right-of-Way: Earth materials obtained from sources outside the right-of-way may be used for barrow, subgrade treatment, base material, shoulders and for any other use for which they are specified. The provisions of 6.01 b apply to all of these uses.

“It is the intent of this Article that the department, having investigated sources of all earth materials required, is best qualified to determine which sources will be used. The department will not approve any sources of such materials not shown on the plans, before bids have been read publicly.

“This Article does not apply to local sources of materials for Portland Cement Concrete or Bituminous Plant Mix, nor to quarry sites.

“1. Method of Providing Sources: Payment of Royalties: (a) Information on Plans: The sources of local material will be shown on the Plans, and the amounts of royalties and other costs and conditions of acquisition of the material from the owner will also be so shown. The Plans or Special Provisions will also contain an estimate of the quantity of material required from each source and will show where the material is to be placed in *457 the finished work. They will also contain an estimate of the quantities of Clearing and Grubbing, Stripping Excavation, Overhaul and Special Overhaul for each source separately. . .

(b) Options: The Department will obtain all necessary options from the owners.

(c) Payment of Royalties: The Contractor shall pay to the owners of the pits used, all royalties and other costs, promptly, and shall meet all other conditions agreed upon with the owners, if there are any, pertaining to the acquisition of the pits actually used, and shall, before final payment is made, submit to the Engineer satisfactory evidence that he has done so. The Department will not make any separate payment to the Contractor for these, costs of acquisition, and the Contractor is instructed to include them in the unit prices bid for the Pay Items to which they apply.

“2. Haul Roads: No separate payments will be made to the Contractor for construction or maintenance of any roads for hauling. The cost of haul roads shall be included in the prices bid for other Pay Items pertaining to this part of the Work.

“3. Substitution of Sources of Materials: The Engineer has the authority to eliminate any source of material shown on the Plans or in the Special Provisions and, by written order, to substitute other sources as may be to the advantage of the Department. Such substitutions may be made at any time before the Contractor’s plant has been delivered at the source to be eliminated. The written order will identify the new source and will contain an estimate of the quantities of clearing, stripping and overhaul required, and all of these quantities will be corrected for the new source. The new estimate will replace the old estimate, and the unit price applying' to the work will not be changed because of such substitution.

“If, after the Contract is awarded, the Contractor wishes to substitute other sources, and if the materials in these sources are equal to or better than those specified, and if the cost to the Department does not exceed that specified in the Contract, they will be accepted. The Engineer is the only judge as to the quality of materials to be substituted.

“4. Responsibility for Amount and Quality of Materials: The *458

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ramilaben Patel v. Georgia Lottery Corporation
Court of Appeals of Georgia, 2019
Patel v. Ga. Lottery Corp.
830 S.E.2d 393 (Court of Appeals of Georgia, 2019)
National Distributing Co. v. Department of Transportation
283 S.E.2d 470 (Supreme Court of Georgia, 1981)
Gainesville Glass Co. v. Don Hammond, Inc.
278 S.E.2d 182 (Court of Appeals of Georgia, 1981)
National Distributing Co. v. Department of Transportation
278 S.E.2d 648 (Court of Appeals of Georgia, 1981)
Jahncke Service, Inc. v. Department of Transportation
213 S.E.2d 150 (Court of Appeals of Georgia, 1975)
Stone Mountain Memorial Ass'n v. Stone Mountain Scenic Railroad
205 S.E.2d 293 (Supreme Court of Georgia, 1974)
St. Mtn. Mem. Assn. v. St. Mtn. Scenic R.
205 S.E.2d 293 (Supreme Court of Georgia, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
160 S.E.2d 641, 117 Ga. App. 453, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-highway-department-v-knox-rivers-construction-co-gactapp-1968.