Gades v. Meyer Modernizing Co.

2015 SD 42, 865 N.W.2d 155, 2015 S.D. LEXIS 76, 2015 WL 3505523
CourtSouth Dakota Supreme Court
DecidedJune 3, 2015
Docket27209
StatusPublished
Cited by18 cases

This text of 2015 SD 42 (Gades v. Meyer Modernizing Co.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gades v. Meyer Modernizing Co., 2015 SD 42, 865 N.W.2d 155, 2015 S.D. LEXIS 76, 2015 WL 3505523 (S.D. 2015).

Opinion

GILBERTSON, Chief Justice.

[¶ 1.] Blair and Lynn Gades appeal the circuit court’s determination that their cause of action was time barred, as well as the court’s order granting summary judgment in favor of Meyer Modernizing Co., Inc. (Meyer). The Gadeses assert there are genuine disputes of material fact as to the date of accrual of their cause of action. They also assert Meyer concealed the existence of their cause of action. We affirm.

Facts and Procedural History

[¶ 2.] The facts of this case are largely undisputed. 1 In 2000, the Gadeses engaged Enercept, Inc. — a manufacturing company located in Watertown, South Dakota — to design and manufacture the structural insulated panels 2 used to con *157 struct their home in Mitchell, South Dakota. The Gadeses did not hire a general contractor to oversee the actual construction of their home; instead, Blair Gades assumed that role himself. In early 2000, the Gadeses hired Master Builders of Avon — a Minnesota entity — to install the footings, erect the Enercept panels, finish and shingle the roof, install the windows and doors, and apply the house wrap.

[¶3.] On April 3, 2000, the Gadeses hired Meyer to install the siding, soffits, and gutters on the home. The estimate offered by Meyer and accepted by the Gadeses did not mention, or include charges for, the installation of flashing around the windows and doors. 3 By the time Meyer installed the siding, Master Builders had already installed all of the windows, doors, and house wrap. The home was substantially completed, and the Gadeses moved into the home, by late 2000.

[¶ 4.] As early as spring 2001, but no later than 2002, the Gadeses first noticed water infiltration around window and door openings during rain and wind events. 4 This water infiltration resulted in standing water on the window sills and seepage into the door trim and floors. Similar instances of water infiltration have occurred every year since the Gadeses moved into their home, with some years seeing as many as 10 to 12 such incidents. The totality of the Gadeses’ asserted injury in this case stems from these water infiltrations, the natures of which have not changed since first manifesting. Since first becoming aware of the problem, the Gadeses have not performed any corrective work on the home. 5

[¶ 5.] The Gadeses retained counsel in this matter by April 11, 2005. However, they did not bring suit regarding their water infiltration claim until April 20Í0. They amended their complaint in 2013 to include the assertion that Meyer concealed the absence of installed flashing. Meyer moved for summary judgment, which the circuit court granted.

[¶ 6.] The Gadeses raise one issue on appeal: Whether there is a genuine dispute of material fact as to the date of accrual of their cause of action.

Standard of Review

[¶ 7.] “In reviewing a grant or a denial of summary judgment under SDCL 15 — 6—56(c), we must determine whether the moving party demonstrated the absence of any genuine issue of material fact *158 and showed entitlement to judgment on the merits as a matter of law.” Peters v. Great W. Bank, Inc., 2015 S.D. 4, ¶ 5, 859 N.W.2d 618, 621 (quoting Saathoff v. Kuhlman, 2009 S.D. 17, ¶ 11, 763 N.W.2d 800, 804). If the moving party properly supports the motion, the nonmoving party may only avoid summary judgment by “set[ting] forth specific facts showing that there is a genuine issue for trial.” SDCL 15 — 6—56(e). Any material fact asserted by the moving party in support of the motion for summary judgment is deemed admitted by the nonmoving party unless controverted. SDCL 15-6-56(c)(3). We view the evidence “most favorably to the non-moving party and [resolve] reasonable doubts ... against the moving party.” Peters, 2015 S.D. 4, ¶ 5, 859 N.W.2d at 621 (quoting Saathoff, 2009 S.D. 17, ¶ 11, 763 N.W.2d at 804). “If there exists any basis which supports the ruling of the trial court, affirmance of a summary judgment is proper.” Id. (quoting Saathoff, 2009 5.D. 17, ¶ 11, 763 N.W.2d at 804).

Analysis and Decision

[¶ 8.] There does not appear to be a genuine dispute as to the applicable period of limitation in this case. 6 SDCL 15-2-13(1) provides that “[a]n action upon a contract, obligation, or liability, express or implied,” may only be filed “within six years after the cause of action shall have accrued[.]” The Gadeses assert there are genuine issues of material fact as to the beginning of this six-year period. First, the Gadeses assert Meyer knew flashing had not been installed and that “Meyer actively concealed the lack of flashing!.]” The Gadeses allege Meyer maintained this concealment “at least from 2004 or 2005 when it undertook additional work if not from initial installation.” Finally, the Gadeses assert they were not “actually aware of the lack of flashing” until October 2013.

[¶ 9.] As indicated in the previous paragraph, the Gadeses were permitted to file their cause of action within six years of its accrual. SDCL 15-2-13(1). The Gadeses assert they were not “actually aware of the lack of flashing” until October 2013. “A claim accrues when a plaintiff has actual or constructive notice of a cause of action.” E. Side Lutheran Church of Sioux Falls v. NEXT, Inc., 2014 S.D. 59, ¶ 10, 852 N.W.2d 434, 438 (emphasis added). 7 Because “[e]very person who *159 has actual notice of circumstances sufficient to put a prudent man upon inquiry as to a particular fact, and who omits to make such inquiry with reasonable diligence, is deemed to have constructive notice of the fact itself[,]” SDCL 17-1-4, “[a] claim can accrue ‘even when one may not yet know all the underlying facts or the full extent of damages[,]’” E. Side Lutheran Church, 2014 S.D. 59, ¶ 14, 852 N.W.2d at 439-40 (quoting Strassburg v. Citizens State Bank, 1998 S.D. 72, ¶ 13, 581 N.W.2d 510, 515). Thus, “[s]tatutes of limitations begin to run when plaintiffs first become aware of facts prompting a reasonably prudent person to seek information about the problem and its cause.” Id. ¶ 14, 852 N.W.2d at 440 (quoting Strassburg, 1998 S.D. 72, ¶ 13, 581 N.W.2d at 515) (internal quotation marks omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoven v. Banner Associates, Inc.
993 N.W.2d 562 (South Dakota Supreme Court, 2023)
S.D. Petroleum Release Compensation Fund v. Bp
2020 S.D. 47 (South Dakota Supreme Court, 2020)
Healy v. Osborne
2019 S.D. 56 (South Dakota Supreme Court, 2019)
Ridley v. Sioux Empire Pit Bull Rescue
2019 S.D. 48 (South Dakota Supreme Court, 2019)
Ridley v. Sioux Empire Pit Bull Rescue, Inc.
932 N.W.2d 576 (South Dakota Supreme Court, 2019)
Fischer v. City of Sioux Falls
2018 SD 71 (South Dakota Supreme Court, 2018)
S.D. Wheat Growers Ass'n v. Chief Indus., Inc.
337 F. Supp. 3d 891 (U.S. District Court, 2018)
Hanson v. Big Stone Therapies, Inc.
2018 SD 60 (South Dakota Supreme Court, 2018)
Schaefer v. Sioux Spine & Sport, Prof. LLC
2018 SD 5 (South Dakota Supreme Court, 2018)
Beals v. Autotrac, Inc.
2017 SD 80 (South Dakota Supreme Court, 2017)
Lowery Construction & Concrete, LLC v. Owners Insurance Co.
2017 SD 53 (South Dakota Supreme Court, 2017)
Nicolay v. Stukel
2017 SD 45 (South Dakota Supreme Court, 2017)
Schliem v. State Ex Rel. Department of Transportation
2016 SD 90 (South Dakota Supreme Court, 2016)
Karst v. Shur-Co.
2016 SD 35 (South Dakota Supreme Court, 2016)
Pitt-Hart v. Sanford USD Medical Center
2016 SD 33 (South Dakota Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2015 SD 42, 865 N.W.2d 155, 2015 S.D. LEXIS 76, 2015 WL 3505523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gades-v-meyer-modernizing-co-sd-2015.