East Side Lutheran Church of Sioux Falls v. Next, Inc.

2014 SD 59, 852 N.W.2d 434, 2014 WL 3892968
CourtSouth Dakota Supreme Court
DecidedAugust 6, 2014
Docket26776
StatusPublished
Cited by6 cases

This text of 2014 SD 59 (East Side Lutheran Church of Sioux Falls v. Next, Inc.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Side Lutheran Church of Sioux Falls v. Next, Inc., 2014 SD 59, 852 N.W.2d 434, 2014 WL 3892968 (S.D. 2014).

Opinion

SEVERSON, Justice.

[¶ 1.] East Side Lutheran Church (East Side) appeals from a summary judgment ruling that barred its claim for failing to timely file suit within the applicable six-year statute of limitations. We affirm in part and reverse in part.

Background

[¶ 2.] In April 2002, East Side contracted with NEXT, Inc. (NEXT) for construction of a new addition to East Side’s church and renovation to its existing struc *437 ture. NEXT worked as East Side’s representative for the project and contracted with third-party defendants Brown Architecture & Design Company (Brown) and Fiegen Construction Company (Fiegen). Brown provided design and architectural work on the project and Fiegen served as the general contractor. Fiegen subcontracted with fourth-party defendant M.J. Dalsin Company (Dalsin) to complete the roof construction associated with the project. 1 The project was substantially completed in August 2003.

[¶ 3.] In the months immediately following the project’s completion, East Side experienced a variety of problems throughout the structure. The problems included ice dams, bats in the church, chipping concrete, hail penetration, and drainage issues, but the overriding problem was water infiltration. 2 The water infiltration persisted and resulted in this litigation.

[¶ 4.] East Side and NEXT communicated about, and NEXT attempted to eradicate, the water infiltration from the date of the project’s completion until May 2009. On January 23, 2009, NEXT’S attorney sent a letter to East Side explaining that Fiegen and Dalsin were “unwilling to perform any additional work[,]” and that NEXT had, without admitting liability, “notified its insurance carrier of a potential claim.” Later that spring, on May 28, 2009, NEXT’S attorney informed East Side’s attorney that NEXT “will be undertaking no additional repairs to” the church. The letter further stated that East Side “will need to either undertake its own repairs and proceed with litigation or contact Fiegen and Dalsin regarding any such repairs.”

[¶ 5.] In March 2010, East Side hired Michael Ollerich of American Technical Services. Ollerich’s reports confirmed that the church was experiencing water infiltration. Ollerich’s reports further indicated the project’s design contained structural errors; the work completed contained construction errors; and the structure was experiencing ventilation and insulation problems. East Side filed suit against NEXT in July 2010. 3

[¶ 6.] NEXT, Brown, Fiegen, and Dal-sin (Defendants) moved for summary judgment on the basis that East Side filed its suit outside of the six-year statute of limitations. See SDCL 15-2-13. The Defendants argued that because East Side knew of the water infiltration immediately after construction was completed, the six-year statute of limitations began to run as early as August 2003. As a result, the statute of limitations lapsed in 2009 and East Side’s July 2010 lawsuit was not timely filed.

[¶ 7.] East Side opposed summary judgment and argued that its lawsuit is based in part on the project’s structural design errors and construction errors. Because it did not know of the structural design errors and construction errors until Ollerich’s 2010 reports, it argued its claims *438 did not accrue until 2010, making its suit timely. East Side also argued that equitable estoppel tolled the statute of limitations.

[¶ 8.] The circuit court granted summary judgment to Defendants on the statute of limitations issue because East Side “had actual or constructive notice of a cause of action immediately after the substantial completion [of the project] in August of 2003.” The circuit court also granted summary judgment to Defendants on the issue of equitable estoppel because there was no “genuine issue of material fact regarding whether or not any of the [DJefendants misrepresented or concealed material facts from [East Side] in order to induce [East Side] to change its position in reliance upon either those misrepresentations or that concealment.” East Side now appeals to this Court arguing the circuit court’s rulings on the statute of limitations and equitable estoppel were error. 4

Decision

Statute of limitations

[¶9.] The parties agree that the six-year statute of limitations prescribed by SDCL 15-2-13 controls East Side’s claims. East Side commenced this action in July 2010. Thus, any claims that accrued before July 2004 are barred. As a result, we must resolve if there are any genuine issues of material fact as to whether any or all of East Side’s claims accrued before July 2004.

[¶ 10.] A claim accrues when a plaintiff has actual or constructive notice of a cause of action. Strassburg v. Citizens State Bank, 1998 S.D. 72, ¶ 10, 581 N.W.2d 510, 514. “Actual notice consists in express information of a fact.” SDCL 17-1-2. “Constructive notice is notice imputed by the law to a person not having actual notice.” SDCL 17-1-3. “One having actual notice of circumstances sufficient to put a prudent person on inquiry about ‘a particular' fact, and who omits to make such inquiry with reasonable diligence, is deemed to have constructive notice of the fact itself.’ ” Strassburg, 1998 S.D. 72, ¶ 10, 581 N.W.2d at 514 (quoting SDCL 17-1-4).

[¶ 11.] “Because the point at which a period of limitations begins to run must be decided from the facts of each case, statute of limitations questions are normally left for a jury.” Strassburg, 1998 S.D. 72, ¶ 7, 581 N.W.2d at 513 (citation omitted); see also Wissink v. Van De Stroet, 1999 S.D. 92, ¶ 11, 598 N.W.2d 213, 215 (citations omitted) (“This Court has recognized that, generally, statute of limitations questions are left for the jury.”); Huron Ctr., Inc. v. Henry Carlson Co., 2002 S.D. 103, ¶ 11, 650 N.W.2d 544, 548 (citation omitted) (“[T]he question of when accrual occurred is one of fact generally reserved for trial.”). “Here, we must ascertain whether there is any genuine issue of material fact concerning the date the *439 cause of action accrued; if not, and if the applicable limitations period has expired as a matter of law, then the [Defendants are] entitled to summary judgment.” Strassburg, 1998 S.D. 72, ¶ 7, 581 N.W.2d at 513 (citation omitted).

[¶ 12.] There is no genuine issue of material fact concerning East Side’s actual notice of the water infiltration prior to July 2004.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Johnson
14 N.W.3d 316 (South Dakota Supreme Court, 2024)
Hoven v. Banner Associates, Inc.
993 N.W.2d 562 (South Dakota Supreme Court, 2023)
Work v. Allgier
2018 SD 56 (South Dakota Supreme Court, 2018)
Gades v. Meyer Modernizing Co.
2015 SD 42 (South Dakota Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2014 SD 59, 852 N.W.2d 434, 2014 WL 3892968, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-side-lutheran-church-of-sioux-falls-v-next-inc-sd-2014.