G & H Development, LLC v. Benton-Parish Metropolitan Planning Commission

641 F. App'x 354
Court of Appeals for the Fifth Circuit·Decided March 2, 2016·No. No. 15-30556·Published·Cited by 5 cases

Opinion

PER CURIAM: *

The district court rejected G & H’s procedural and substantive due process claims with respect to its application to develop a tract of land. We affirm.

I

G & H Development, L.L.C. (G & H) owns a 55-acre parcel of land in Bossier Parish, Louisiana that it sought to develop into a subdivision of 154 lots containing single-family dwellings. G & H applied to the Benton Parish Metropolitan Planning Commission (the MPC) to have the property rezoned from Residence-Agriculture (R-A) zoning to One-Family Residence (R-l) zoning; it also filed with the MPC a subdivision plat for approval. After a hearing, the MPC voted to deny the rezoning application and declared the subdivision application therefore to be moot. G & H appealed the denial to the Bossier Parish Police Jury, which upheld the MPC’s denial and mootness determination after a hearing. The mootness determination was premised on the belief that the property’s existing zoning status was not compatible with the proposed subdivision plat. ' G & H [356] did not seek judicial review of the decision in state court.

G & H subsequently developed a new subdivision plat — which was similar to the first but proposed eleven fewer lots — and submitted the new plat to the MPC without an accompanying application for rezoning. Nancy Penwell, the MPC’s Zoning Administrator, decided not to submit this application to the MPC because it was not accompanied by an application for rezoning, which would have been required according to her understanding of the Bossier Parish Code of Ordinances (the Bossier Parish Code or the Code). Counsel for the MPC accordingly returned the application to G & H with an explanation that the application required an accompanying application for rezoning. G & H appealed this decision to the Benton-Parish Board of Adjustment. The Board of Adjustment held a hearing at which it did not permit G & H to call Penwell to testify under oath. The Board of Adjustment denied the appeal. G & H subsequently appealed to the Police Jury, which refused to consider the merits of the appeal on the ground that it lacked jurisdiction to do so. The Police Jury advised G & H that the proper place for its appeal was in state district court.

G & H did not seek review in state court but instead filed a lawsuit in federal court against various named defendants, including the Board of Adjustment, the Police Jury, and Bossier Parish, seeking declaratory judgments establishing that its rights to due process and equal protection under the United States and Louisiana constitutions had been violated; that any zoning regulations pertaining to the property at issue are null and void because the MPC has never certified a general zoning plan; and that G & H is entitled to a certificate of approval from the MPC for its second subdivision application. It also sought an injunction requiring the MPC to issue such certificate, and it sought damages for “its expenses for surveying, engineering, platting, legal and other professional fees, etc. and other costs and expenses paid and incurred in its efforts to develop the Property.”

In multiple rulings, the district court rejected all of G & H’s procedural due process, substantive due process, and equal protection claims. On appeal, G & H only contests the dismissal of its procedural due process claim against the Board of Adjustment and the grant of summary judgment with respect to its substantive due process claim against the MPC and the Police Jury.

II

We review a district court’s dismissal under Rule 12(b)(6) de novo, “accepting all well-pleaded facts as true and viewing those facts in the light most favorable to the plaintiff[ ].”1 We “review a grant of summary judgment de novo, viewing all evidence in the light most favorable to the nonmoving party and drawing all reasonable inferences in that party’s favor.”2 Summary judgment is proper “if the mov-ant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”3

III

G & H argues that it was denied procedural due process at the hearing for [357] its second subdivision application because it was not afforded the opportunity to be heard “in a meaningful manner.”4 It states that the Board of Adjustment did not allow G & H to submit testimony under oath or to cross-examine Penwell, and that the Board of Adjustment was represented by the same lawyer who was representing the MPC, which was a party to the hearing. The Board responds that the hearing complied with the relevant provisions of the Bossier Parish Code, which require “[pjublic notice” of a hearing of appeal and “due notice” to the appellant. Those provisions further provide that the chairman “may administer oaths and compel attendance of witnesses” and that the Board “shall not be bound by legal rules of evidence.” The Board notes that G & H has not alleged that it lacked notice of the hearing or that it was denied the right to participate.

Free access — add to your briefcase to read the full text and ask questions with AI

G & H Development, LLC v. Benton-Parish Metropolitan Planning Commission, 641 F. App'x 354 (5th Cir. 2016).

641 F. App'x 354 (G & H Development, LLC v. Benton-Parish Metropolitan Planning Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related