Frommeyer v. L. & R. CONSTRUCTION CO.

139 F. Supp. 579, 1956 U.S. Dist. LEXIS 3657
CourtDistrict Court, D. New Jersey
DecidedMarch 27, 1956
DocketCiv. A. 851-55
StatusPublished
Cited by32 cases

This text of 139 F. Supp. 579 (Frommeyer v. L. & R. CONSTRUCTION CO.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frommeyer v. L. & R. CONSTRUCTION CO., 139 F. Supp. 579, 1956 U.S. Dist. LEXIS 3657 (D.N.J. 1956).

Opinion

FORMAN, Chief Judge.

The complaint in this case alleges, among other things, that:

On January 28, 1953 the defendant Wortmann & Sons, Inc. entered into a contract as prime contractor with the United States for the construction of Air Force Bachelor Officers Quarters at the McGuire Air Force Base at Wrights-town, New Jersey. Wortmann gave both the payment and performance bonds required by the Miller Act 1 with itself as *581 principal, the United States as obligee and the defendant Seaboard Surety Company as surety.

Subsequently, Wortmann entered into a subcontract with the defendant L. & R. Construction Company whereby L. & R. bound itself to do all concrete work for the project. Wortmann exacted the following bond from L. & R.:

“Know all Men by these Presents, That we L & R Construction Co., Inc. of Camden, New Jersey called the Principal, and American Surety Company of New York, called the Surety, are held and firmly bound unto Wortmann & Sons of New York City called the Owner, in the sum of One hundred ninety nine thousand dollars-----------Dollars ($199,000.00), for the payment whereof said Principal and Surety bind themselves firmly by these presents.
“Whereas, the Principal has, by written Agreement, dated March 11, 1953, entered into a contract with the Owner for Furnishing of concrete work and installation of reinforcing steel in connection with construction of Air Force quarters McGuire Air Force Base, Wrightstown, New Jersey.”

a copy of which is by reference made a part hereof;

“Now, Therefore, the condition of this obligation is such, that if the Principal shall faithfully perform the contract on his part, free and clear of all liens arising out of claims for labor and materials entering into the construction, and indemnify and save harmless the Owner from all loss, cost or damage which he may suffer by reason of the failure so to do, then this obligation shall be void; otherwise to remain in full force and effect.”

L. & R. then subcontracted with a partnership, Frommeyer and Company, plaintiff herein, in an agreement in which the plaintiff promised to furnish labor and supply materials on the project. It is alleged that L. & R. has defaulted in payment under its contract with the plaintiff, which has brought this suit joining as defendants Wortmann and Seaboard Surety in an exercise of the right of action given by the Miller Act; L. & R. Construction Company in an action founded on the contract between L. & R. and the plaintiff; and the American Surety Company in an action on the bond the terms of which are set forth above.

American has moved to dismiss the complaint as to it on the ground that, regardless of the liability of L. & R., it cannot be sued on the bond by anyone other than Wortmann. The specific argument is that the promise in the bond to pay money is solely a promise made to Wortmann and that American makes no promise that can be construed as giving a right of action on the bond to one not a party to it. The bond, it is said, exists for the single benefit of Wort *582 mann, and not for the benefit of suppliers of L. & R. 2

We may begin with the Restatement of Security. Section 165 provides:

“Where a surety for a contractor on a construction contract agrees in terms with the owner that the contractor will pay for labor and materials, or guarantees to the owner the promise of the contractor to pay for labor and materials, those furnishing labor or materials have a right against the surety as third party beneficiaries of the surety’s contract, unless the surety’s contract in terms disclaims liability to such persons.”

It is obvious that American’s bond is not covered by this section. American has not agreed with Wortmann that L. & R. will pay for labor and materials, nor has it guaranteed a promise of L. & R. to pay those furnishing labor and materials, since neither the bond nor any of the agreements it incorporated by reference contains such a promise attributable to L. & R. Thus, the agreements presently involved in this case meet none of the conditions section 165 imposes as necessary prerequisites to the right of laborers and materialmen to sue the contractor’s surety on the latter’s bond.

Section 166 of the Restatement defines the conditions under which the right of a supplier to sue a contractor’s surety does not exist. It provides:

“Where a surety guarantees the performance of a contract by a contractor who does not promise the owner to pay those furnishing labor or materials but agrees to complete the work free of liens or to furnish labor and materials, laborers and materialmen have no rights against the surety.”

Equally as obvious as the inapplicability of section 165 is the applicability of section 166. American has not promised Wortmann to pay laborers and materialmen but did agree to complete the contract free and clear of all liens. If the Restatement is to govern, this promise by American gives the plaintiffs no right of action against it.

Professor Corbin has stated the principles controlling interpretation of contractors’ surety bonds as follows:

“In the case of a surety bond given to an owner to assure performance of a building contract, the legal duties of the surety ought not to be expanded beyond the terms of the surety's promise. He is paid for his undertaking; but he is not paid for more than his undertaking. The extent of this undertaking is to be determined not only by the surety’s words of express promise, but also by the ‘condition’ of the bond. Words of ‘condition’ are not words of ‘promise’ in form; but in the case of a penal bond they must be construed to be words of promise inasmuch as the only express words of promise are those in which payment of the penal sum is promised. The alternative seems to be between enforcing the penalty and construing the words of condition as a promise and enforcing that. The courts have adopted the latter alternative, penalties no longer being collectible. A bond conditioned to be void on fulfillment by the principal contractor *583 of all of his duties is operative as a promise either that all those duties will be performed or that the promisee will be indemnified within the limit of the penalty in case of nonperformance. The cases denying a remedy to third persons on a private surety bond nearly always interpret it as exclusively the latter promise and rest the decision on that ground.” 4 Corbin on Contracts § 800, pp. 173-174.
“ * * * the third party has an enforceable right if the surety promises in the bond, either in express words or by reasonable implication, to pay money to him. If there is such a promissory expression as this, there need be no discussion of ‘intention to benefit’. We need not speculate for whose benefit the contract was made, or wonder whether the promisee was buying the promise for his own selfish interest or for philanthropic purposes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. Tesco Corp.
816 F. Supp. 2d 410 (S.D. Texas, 2011)
Various Markets, Inc. v. Chase Manhattan Bank, N.A.
908 F. Supp. 459 (E.D. Michigan, 1995)
HOUSING AUTH. OF THE CITY OF JERSEY CITY v. Jackson
749 F. Supp. 622 (D. New Jersey, 1990)
McCormick v. Mays
124 F.R.D. 164 (S.D. Ohio, 1988)
Jennette Fruit & Produce Co. v. Seafare Corp.
331 S.E.2d 305 (Court of Appeals of North Carolina, 1985)
Clements v. Austin
673 S.W.2d 867 (Court of Appeals of Tennessee, 1983)
Land v. Highway Const. Co., Ltd.
645 P.2d 295 (Hawaii Supreme Court, 1982)
A & P Sheet Metal Co., Inc. v. Edward Hansen, Inc.
357 A.2d 37 (New Jersey Superior Court App Division, 1976)
Ramos de Bellique v. Trans Oceanic Insurance
103 P.R. Dec. 298 (Supreme Court of Puerto Rico, 1976)
Slotkin v. Brookdale Hospital Center
377 F. Supp. 275 (S.D. New York, 1974)
Walters v. Hiab Hydraulics, Inc.
356 F. Supp. 1000 (M.D. Pennsylvania, 1973)
Barker v. Louisiana & Arkansas Railway Co.
57 F.R.D. 489 (W.D. Louisiana, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
139 F. Supp. 579, 1956 U.S. Dist. LEXIS 3657, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frommeyer-v-l-r-construction-co-njd-1956.