Dravo-Doyle Co. v. Royal Indemnity Co.

92 A.2d 554, 372 Pa. 64
CourtSupreme Court of Pennsylvania
DecidedNovember 25, 1952
DocketAppeal, 167
StatusPublished
Cited by10 cases

This text of 92 A.2d 554 (Dravo-Doyle Co. v. Royal Indemnity Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dravo-Doyle Co. v. Royal Indemnity Co., 92 A.2d 554, 372 Pa. 64 (Pa. 1952).

Opinion

Opinion by

Mr. Justice Chidsey,

The lower court sustained preliminary objections to the plaintiff’s complaint in assumpsit and gave the plaintiff fifteen days in which to amend in order to allege that it had the right to a lien. Upon failure to amend, judgment was entered for the defendant. This appeal is from the entry of that judgment.

*66 The question here involved is one of law and there is no dispute regarding the facts. Plaintiff, DravoDoyle Company, is an unpaid materialman. Defendant is a surety for a subcontractor which is now bankrupt.

Bechtel International Corporation, the general contractor, entered into a subcontract with Industrial Contracting Company. Defendant’s bond generally insures the performance of such contract. Plaintiff furnished material and equipment to the subcontractor for which it has not been paid. The determination of the question involved turns on an interpretation of the contract between Bechtel and Industrial.

The pertinent portions of such contract are as follows: “2. ITEMS TO BE FURNISHED BY SUBCONTRACTOR : Subcontractor shall supply and furnish at the location where the work is to be performed all items, including labor, materials, and equipment, necessary for the complete and satisfactory performance of this subcontract, except such items as the Contractor in the Subcontract of which these terms and conditions are a part specifically agrees to supply or furnish to or for the use of Subcontractor. . . 12. LIENS AND CLAIMS: Subcontractor shall indemnify and save harmless Contractor and Owner from all claims, demands, causes of action or suits of whatsoever nature arising out of the services, labor and material furnished by Subcontractor, or its subcontractors, under this Subcontract. Subcontractor shall immediately pay and discharge, or shall provide security sufficient and satisfactory in itself to its laborers, materialmen or other creditors, or those of its subcontractors, for the payment of any obligation, or alleged obligation, it, or any of its subcontractors may have, in aid of the enforcement of which a lien or right of any kind is established, or is attempted to be established, upon or against the work or the real property upon which the *67 work is situated. Contractor may, as a condition precedent to any payment hereunder, require Subcontractor to submit complete waivers and releases of any and all claims of any person, firm or corporation. Such release must be submitted covering all such claims as a condition precedent to final payment. . . 17. INSUBANCE AND BONDS: Subcontractor, at its own expense, shall procure, carry and maintain on all its operations hereunder the bonds and policies of insurance in the amounts specified in the Subcontract. The bonds and policies of insurance shall be in such form and shall be issued by such company or companies as may be satisfactory to Contractor. Subcontractor shall cause to be furnished to Contractor certificates of insurance from the assuring companies which shall include the following clause: ‘Ten (10) days’ advance notice shall be given in writing to Bechtel International Corporation, 141 Battery Street, San Francisco, California, on cancellation, termination, or any alteration of the policy or policies evidenced by this certificate.’ ... 18. (d) Payments otherwise due may be withheld by Contractor on account of defective work not remedied, claims filed, or reasonable evidence indicating probability of filing of claims, failure of Subcontractor to make payments properly to subcontractors or for material or labor, or a reasonable doubt that the subcontract can be completed for the balance then unpaid. If the foregoing causes are removed, the withheld payments shall promptly be made. If the said causes are not removed on written notice, Contractor may rectify the same at Subcontractor’s expense. Should any valid indebtedness arise after final payment is made, the Subcontractor shall reimburse the Contractor for any amount that it may pay in discharging any lien therefor or [sic] any claim affecting title to the work on Owner’s property.”

*68 The bond in its pertinent portion provided: “WHEREAS, the above bounden Principal has entered into a certain written contract with the above named Obligee, dated the 14 day of May, 1949. To: Sandblast and Paint Piling and Structural Steel in transit which contract is hereby referred to and made a part hereof as fully and to the same extent as if copied at length herein. Now, therefore, the condition of the above obligation is such, That if the above bounden Principal shall well and truly keep, do and perform, each and every, all and singular, the matters and things in said contract set forth and specified to be by the said Principal kept, done and performed at the time and in the manner in said contract specified, and shall pay over, make good and reimburse to the above named Obligee, all loss and damage which said Obligee may sustain by reason of failure or default on the part of said Principal, then this obligation shall be void; otherwise, to be and remain in full force and effect.”

With this factual background, we turn to a consideration of the law. The bond, of course, only insured that the Industrial Contracting Company would carry out the terms of the contract. Therefore the decision involves an interpretation of the contract.

Appellant contends that the bond was both a “performance” and a “payment” bond and that therefore as a third-party beneficiary of the contract, it should be entitled to recover. The law is clear that since the decision in Commonwealth v. Great American Indemnity Co., 312 Pa. 183, 167 A. 793, an unpaid material-man may be under certain circumstances a third-party beneficiary of the contract. Equally apparent from the decisions is the proposition that one bond may insure both payment and performance and again in certain circumstances an unpaid materialman may be a third-party beneficiary: Pennsylvania Supply Company v. *69 National Casualty Company, 152 Pa. Superior Ct. 217, 31 A. 2d 453; Cf. Fleck-Atlantic Company v. Indemnity Insurance Company of North America, 326 Pa. 15, 191 A. 51. But none of these general propositions definitely determine the issue here involved, for in the instant case we have a contract unlike those present in the cases above cited.

The question here involved is one of interpreting the contract with a view to determining (a) whether the parties intended to benefit any third parties, and (b) if so, what parties they intended to benefit.

It seems clear to us, as it did to the court below, that the above quoted portions of the contract show an intention to benefit some third parties. However, in summary, the lower court decided that . . the general contractor in the bond and contract was only seeking to protect itself from claims, which might result in a lien upon or against the work or the real property upon which the work was situated. Under these circumstances, there can be no implication drawn that any materialman, who did not have in aid of his claim a right to a lien, received any protection under the bond or became a donee beneficiary. . . .”. With this conclusion we agree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knecht, Inc. v. United Pacific Insurance Company
860 F.2d 74 (Third Circuit, 1988)
Wyoming MacHinery Co. v. United States Fidelity & Guaranty Co.
614 P.2d 716 (Wyoming Supreme Court, 1980)
U.S. Steel Corp. v. Mursor Builders, Inc.
61 Pa. D. & C.2d 454 (Luzerne County Court of Common Pleas, 1972)
Babcock & Wilcox Co. v. Fischbach & Moore, Inc.
280 A.2d 582 (Superior Court of Pennsylvania, 1971)
Atlantic Refining Co. v. Continental Casualty Co.
183 F. Supp. 478 (W.D. Pennsylvania, 1960)
Frommeyer v. L. & R. CONSTRUCTION CO.
139 F. Supp. 579 (D. New Jersey, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
92 A.2d 554, 372 Pa. 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dravo-doyle-co-v-royal-indemnity-co-pa-1952.