Friends of Wild Swan v. United States Environmental Protection Agency

74 F. App'x 718
Court of Appeals for the Ninth Circuit·Decided July 25, 2003·No. No. 00-36001, 00-36004 & 00-36013·Published·Cited by 7 cases

Opinion

MEMORANDUM **

In this action, brought by five environmental groups (collectively “Friends”) under 33 U.S.C. § 1313, the district court found that the Environmental Protection Agency (“EPA”) violated the Administrative Procedure Act (“APA”) and the Clean Water Act (“CWA”) by arbitrarily and capriciously approving Montana’s 1998 list of water quality limited segments (‘WQLSs”) and corresponding total maximum daily loads (“TMDLs”) submitted to EPA pursuant CWA § 303(d). The district court remanded to the EPA with a deadline for establishment of TMDLs for all WQLSs and provided that any failure to meet the deadline would constitute a final agency action. The district court also required that TMDLs be established for all WQLSs identified in Montana’s 1996 submission and prohibited the issuance of new discharge permits until Montana develops its TMDLs. We have jurisdiction pursuant to 28 U.S.C. § 1291 and we affirm in part, reverse in part, and remand.

We review a district court’s grant of summary judgment de novo. See Clicks Billiards Inc. v. Sixshooters, Inc., 251 F.3d 1252, 1257 (9th Cir.2001). We review the district court’s selection of equitable remedies for an abuse of discretion. See Grosz-Salomon v. Paul Revere Life Ins. Co., 237 F.3d 1154, 1163 (9th Cir.2001). A district court abuses its discretion when it commits an error of law, exceeds its authority or fails to consider appropriate factors in fashioning an equitable remedy. See Sony Computer Entertainment, Inc. v. Connectix Corp., 203 F.3d 596, 602 (9th Cir.2000). Because the parties are familiar with the record, we recite the facts and procedural background only to the extent necessary to explain our ruling.

ANALYSIS

I. Final Agency Action

Appellants argue that Friends lack statutory standing because they did not challenge a final agency action. Two conditions render an action final:

First, the action must mark the “consummation” of the agency’s decision-making process-it must not be of a merely tentative or interlocutory nature. And second, the action must be one by which “rights or obligations have been determined,” or from which “legal consequences will flow.”

Bennett v. Spear, 520 U.S. 154, 177, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997) (citations omitted). This requirement is easily met in this case. The EPA’s June 23, 1998, order was accompanied by a statement of reasons explaining the EPA’s analysis and the basis for approval. The order was not tentative or interlocutory. See id. Legal consequences flowed from the EPA’s decision to approve the list. [721] For example, disapproval would require the EPA to identify the WQLSs and the TMDLs. The list and TMDLs must be incorporated into the State’s continuing planning process under 33 U.S.C. § 1313(e), which must also be approved by the EPA. If the EPA does not approve the list and continuing planning process, permits will not issue. See 33 U.S.C. § 1313(e)(2) (“[The] Administrator shall not approve any State permit program [NPDES/MPDES] ... for any State which does not have an approved continuing planning process.”). The approval of the list also sets parameters for future licenses, which must comply with TMDLs.

Appellants argue that the order was not final for Friends’ purposes because it did not address the long-term schedule for TMDL development or Montana’s failure to develop all necessary TMDLs. The district court found EPA’s approval arbitrary and capricious precisely because it failed to consider these issues. This does not mean that Friends’ challenge is based upon a failure to act.1 Such an approach would preclude review of agency approvals that overlook an important factor. We reject Appellants’ statutory standing argument.

II. Remedy

A. The District Court’s Equitable Powers

Appellants argue that, if EPA erred in approving the 1998 list, the appropriate remedy was to remand. The district court, however, did remand. It also employed its equitable powers to shape the parameters of the remand order. The only question is whether these parameters exceeded the court’s powers.

While courts may not “usurp[] an administrative function, FPC v. Idaho Power Co., 344 U.S. 17, 20, 73 S.Ct. 85, 97 L.Ed. 15 (1952) (“Idaho Power”), they retain equitable powers to shape an appropriate remedy. See West. Oil & Gas Ass’n v. EPA, 633 F.2d 803, 813 (9th Cir.1980) (‘Western Oil”). Equitable considerations are appropriate in reviewing agency decisions under the APA and crafting a remedy. See Nat’l Wildlife Fed’n v. Espy, 45 F.3d 1337, 1343 (9th Cir.1995) (“The court’s decision to grant or deny injunctive or declaratory relief under APA is controlled by principles of equity.”); Sierra Pacific Indus. v. Lyng, 866 F.2d 1099, 1111 (9th Cir.1989) (“Our inquiry into the district court’s authority to order equitable relief begins with the well-established principle that ‘while the court must act within the bounds of the statute and without intruding upon the administrative province, it may adjust its relief to the exigencies of the case in accordance with the equitable principles governing judicial action.” ’ (quoting Ford Motor Co. v. NLRB, 305 U.S. 364, 373, 59 S.Ct. 301, 83 L.Ed. 221 (1939))).

Free access — add to your briefcase to read the full text and ask questions with AI

Friends of Wild Swan v. United States Environmental Protection Agency, 74 F. App'x 718 (9th Cir. 2003).

74 F. App'x 718 (Friends of Wild Swan v. United States Environmental Protection Agency) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related