Friends of the Boundary Mountains v. U.S. Army Corps of Engineers

24 F. Supp. 3d 105, 2014 U.S. Dist. LEXIS 74449, 2014 WL 2453111
CourtDistrict Court, D. Maine
DecidedJune 2, 2014
DocketNo. 1:12-cv-00357-GZS
StatusPublished
Cited by2 cases

This text of 24 F. Supp. 3d 105 (Friends of the Boundary Mountains v. U.S. Army Corps of Engineers) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Friends of the Boundary Mountains v. U.S. Army Corps of Engineers, 24 F. Supp. 3d 105, 2014 U.S. Dist. LEXIS 74449, 2014 WL 2453111 (D. Me. 2014).

Opinion

ORDER AFFIRMING THE RECOMMENDED DECISION OF THE MAGISTRATE JUDGE

GEORGE Z. SINGAL, District Judge.

The United States Magistrate Judge filed with the Court on April 23, 2014, his Recommended Decision (ECF No. 46). Plaintiff filed its Objection to the Recommended Decision on Cross-Motions for Summary Judgment (ECF No. 47) on May 12, 2014. Defendant-Intervenor filed its Response to Plaintiffs Objection to the Recommended Decision (ECF No. 48) on May 19, 2014. Defendants filed their Opposition to Plaintiffs Objection to the Recommended Decision (ECF No. 49) on May 29, 2014.

I have reviewed and considered the Magistrate Judge’s Recommended Decision, together with the entire record; I have made a de novo determination of all matters adjudicated by the Magistrate Judge’s Recommended Decision; and I concur with the recommendations of the United States Magistrate Judge for the reasons set forth in his Recommended Decision, and determine that no further proceeding is necessary.

1. It is therefore ORDERED that the Recommended Decision of the Mag- ■ istrate Judge is hereby AFFIRMED.

2. It is ORDERED that Defendant’s Cross-Motion for Summary Judgment (ECF Nos. 32/33) is hereby GRANTED.

3. It is ORDERED that Intervenor-Defendant’s Cross-Motion for Summary Judgment (ECF No. 36) is hereby GRANTED.

4. It is ORDERED that Plaintiffs Motion for Summary Judgment (ECF No. 31) is DENIED.

RECOMMENDED DECISION ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

JOHN C. NIVISON, United States Magistrate Judge.

In this action, Plaintiff Friends of the Boundary Mountains seeks to “enjoin the grant of a permit” (Complaint ¶ 1) that Defendants the Army Corps of Engineers, Army Corps Lt. General Thomas P. Bos-[108]*108tick, and Army Corps Senior Project Manager Jay Clement, issued to Intervenor-Defendant TransCanada pursuant to Defendants’ authority under section 404 of the Clean Water Act, 33 U.S.C. § 1344, which governs “permits for dredged or fill material.” The matter is before the Court on Plaintiff’s Motion for Summary Judgment (ECF No. 31), Defendants’ Opposition and Cross-Motion (ECF No. 32), and Intervenor-Defendant’s Cross-Motion and Opposition to Plaintiffs Motion (ECF No. 36).

Following a review of the administrative record, and after consideration of the parties’ arguments, as explained below, the recommendation is that the Court uphold the administrative decision, deny Plaintiffs Motion for Summary Judgment, grant Defendants’ Cross-Motion for Judgment, and grant Intervenor-Defendant’s Cross-Motion for Summary Judgment.

BACKGROUND 1

On February 10, 2010, Intervenor-De-fendant filed an application with the Army Corps of Engineers seeking authorization to disturb wetlands and vernal pools in the Kibby Stream watershed (upper reaches of the Dead River watershed) in connection with the construction of the Kibby Expansion Wind Power Project, located in Kibby and Chain of Ponds Townships, Maine. (R. 1:78, 3:1-3, 3:358-66.) As originally proposed, the Project contemplated the installation of fifteen 3 megawatt wind turbine generators and “associated elements” adjacent to and to the west of the existing, 132 megawatt Kibby Project. (R. 3:358.) The Project also included construction of new ridgeline roads and a new substation. Although the Project would use existing access roads, the plans included the construction of new access roads on Sisk Mountain. (R. 3:360.)

On March 8, 2010, Defendant Clement notified Intervenor-Defendant by letter that the application form was complete, but that the Army Corps of Engineers needed additional information in order to review the application. (R. 2:1.) In addition to requesting further information, Defendant Clement requested that Interve-nor-Defendant notify the Corps of any proceedings that might be held before the Maine Land Use . Planning Commission, formerly known as the Maine Land Use Regulatory Commission, “so that we can attend if possible.” (R. 2:3.) Defendant Clement noted that attendance by the Corps at any such proceedings “may allow us to avoid a similar Corps meeting/hearing later in the process.” (R. 2:3.)

Intervenor-Defendant submitted a revised Grid Scale Wind Energy Development Application to the Land Use Planning Commission in December 2009. (R. 7:10.) The application’s introduction outlined the Project’s scope. (R. 7:31-33.) The application discussed, among other things, avian and bat monitoring conducted by Intervenor-Defendant following consultation with the Maine Department of Inland Fisheries and Wildlife (MDIFW) and the U.S. Fish and Wildlife Service (FWS). Intervenor-Defendant also relied on a collection of studies and surveys in support of its application, including rare raptor nesting surveys, spring and fall daytime surveys of migrating raptors, spring and fall nighttime radar surveys of bird migration, and summertime breeding bird surveys conducted on Sisk Mountain. (R. 7:79-146.) In the application, Intervenor-De-fendant also represented that it would con[109]*109duct post-construction monitoring based on ongoing discussions with MDIFW and FWS.' (R. 7:79-146.)

On May 11, 2011, when the proposed project was still a 15-turbine project, FWS wrote to Intervenor-Defendant concerning Intervenor-Defendant’s report titled Eagle Use in the Proposed Kibby Expansion Wind Power Project Area: Impact Assessment and Decision on Take Permit. (R. 5:14 (Eagle Use report); R. 5:56 (FWS letter).) In the letter, FWS provided In-tervenor-Defendant with some information, and expressed its concerns about the Project. More specifically, FWS noted that while the mountains of western Maine are “of particular importance to golden eagles” based on historic nesting habitat and location within a primary migration corridor, its “best information suggests golden eagles were recently extirpated in Maine,” largely due to the lasting impacts of environmental contaminants like DDT and DDE. (R. 5:56.) FWS also identified known golden eagle eyries within two to ten miles of the Project site and discussed historic knowledge of a radio-tagged, female golden eagle named “Virgil Cain,” which was observed in the vicinity of the project in 2009 and 2010 and was known to be back in Maine in the spring of 2011, though her movements showed “no sign of territoriality.” (R. 5:58.)

FWS also stated that although the degree of deterrence that wind projects place on golden eagle nesting habits is unknown, such projects may “introduce a significant source of mortality to golden eagles and their young.” (R. 5:58.) FWS advised that it recently authored a new (April 2011) Draft Eagle Conservation Plan Guidance, which “provides detailed information on methods for data collection, risk assessment, examples of appropriate avoidance and minimization measures and Advanced Conservation Practices ... for wind projects.” The Guidance “encourage[d] all wind applicants in western Maine to avoid take of golden eagles by using the tiered approach in the guidance: siting wind projects in appropriate locations to minimize risk, gathering adequate information to quantitatively model risk to golden eagles, and developing contingencies for avoiding, minimizing, and mitigating take of bald and golden eagles.” (R. 5:63.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
24 F. Supp. 3d 105, 2014 U.S. Dist. LEXIS 74449, 2014 WL 2453111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/friends-of-the-boundary-mountains-v-us-army-corps-of-engineers-med-2014.