Frey v. Environmental Protection Agency

403 F.3d 828, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20076, 60 ERC (BNA) 1097, 2005 U.S. App. LEXIS 5432
CourtCourt of Appeals for the Seventh Circuit
DecidedApril 6, 2005
Docket03-3877
StatusPublished
Cited by3 cases

This text of 403 F.3d 828 (Frey v. Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frey v. Environmental Protection Agency, 403 F.3d 828, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20076, 60 ERC (BNA) 1097, 2005 U.S. App. LEXIS 5432 (7th Cir. 2005).

Opinion

403 F.3d 828

Sarah E. FREY, Kevin Enright, and Protect Our Woods, Inc., Plaintiffs-Appellants,
v.
ENVIRONMENTAL PROTECTION AGENCY, Stephen L. Johnson, Acting Administrator, and Viacom, Inc., Defendants-Appellees.

No. 03-3877.

United States Court of Appeals, Seventh Circuit.

Argued May 25, 2004.

Decided April 6, 2005.

Rudolph W. Savich, Mick G. Harrison (argued), Bloomington, IN, for Plaintiffs-Appellants.

Anna T. Katselas (argued), Department of Justice Environment & Natural Resources Division, Washington, DC, David B. Hird, Weil Gotshal & Manges, Washington, DC, for Defendants-Appellees.

Before EASTERBROOK, WOOD, and WILLIAMS, Circuit Judges.

WOOD, Circuit Judge.

In this successive appeal, we confront another chapter in the long history of certain Superfund sites located near Bloomington, Indiana. The sites are contaminated with polychlorinated biphenyls (PCBs), dioxin, and other toxic chemicals. Sarah Frey, Kevin Enright, and the organization Protect Our Woods (to whom we refer collectively as "Frey") are before us once again, trying to invoke the citizen suit provision of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). That law, in general, permits a plaintiff to challenge cleanup efforts at Superfund sites once the Environmental Protection Agency (EPA) and other responsible parties proclaim their work to be completed. 42 U.S.C. § 9613(h)(4); Frey v. EPA, 270 F.3d 1129, 1133 (7th Cir.2001) (Frey I). Frey argues that her suit meets the statutory criteria, because EPA has completed the excavation of PCBs and has not yet selected further remedies. The district court saw matters differently; it found that Frey's action was (still) premature because EPA has made it clear that it is studying further cleanup options for the three sites challenged in this lawsuit: Lemon Lane Landfill, Neal's Landfill, and Bennett's Dump. We conclude, however, that because EPA has failed to provide any objective referent by which to measure its progress, Frey is finally entitled to her day in court. We reverse.

* On January 4, 1983, the United States initiated a civil action under CERCLA, 42 U.S.C. §§ 9601 et seq., against Viacom (formerly the Westinghouse Electric Corporation and then the CBS Corporation, until it merged into Viacom) to clean up two PCB contaminated dump sites in Bloomington, Indiana. After the City of Bloomington sued Viacom in connection with two other contaminated sites, the cases were consolidated and an additional two sites were added, bringing the total to six. In 1985, the parties entered into a consent decree that directed Viacom to excavate fully (meaning literally down to bedrock) and incinerate the PCBs at the six sites. This plan proved to be controversial, because it required Viacom to construct an incinerator. In 1988, Frey filed suit to challenge the proposed incineration remedy; we dismissed that action for lack of subject matter jurisdiction. Schalk v. Reilly, 900 F.2d 1091, 1096-97 (7th Cir.1990).

Although Frey's lawsuit was unsuccessful, the Indiana State Legislature acted in 1991 to block construction of the incinerator. This forced the parties to the consent decree into further negotiations to find alternative remedies for the contaminated sites. In the course of these discussions, EPA and Viacom came to an impasse. Viacom believed that it should be required only to excavate highly contaminated soil (known as "hot spots"), while EPA took the position that hot spots excavation would be appropriate only if water treatment and sediment removal were included as part of the alternative remedy. In 1997, the district court issued an order stating that the sites had to be remediated by 1999.

To assist the parties in breaking the deadlock in time for the 1999 deadline, the court appointed a special master "to see that the aims of the consent decree are carried out expeditiously and to resolve possible disputes between the parties." The special master's report recommended that the remediation deadline be moved back one year to 2000. It noted that the parties had reached agreement on some alternative methods of PCB excavation and that they had also agreed to complete the source control (excavation) work by the end of 2000. While the excavation work was underway, Viacom agreed to investigate water treatment and sediment remediation solutions at the three sites. According to the schedule proposed by the special master, the parties were to "engage in further settlement negotiations regarding water treatment and sediment removal aspects of remediation at Neal's Landfill and Lemon Lane Landfill, including negotiations for permanent water treatment solutions for these sites, approximately one year following the completion of source control activities at each site." The district court adopted the special master's report and recommendations on February 1, 1999, noting in its order that the schedule required that excavation work at Neal's Landfill and Bennett's Dump be completed by the end of 1999 and that the work at Lemon Landfill be completed by the end of 2000. It instructed the parties to engage in further settlement negotiations regarding the water treatment and sediment removal phases of the remediation.

After the incinerator option was abandoned, EPA took steps to select a new source control remedy for excavation of PCBs at the three sites. The National Oil and Hazardous Substances Pollution Contingency Plan (NCP), 40 C.F.R. Pt. 300, establishes the criteria and procedures to be followed in comparing remedial alternatives and choosing a response. This regulatory process requires EPA to develop a list of effective remedial alternatives and to assess their feasibility. Id. at § 300.430(d) & (e) (describing the Remedial Investigation/Feasibility Study phase). After each alternative is evaluated against nine established criteria, EPA selects a preferred remedy and presents it to the public in a proposed plan for review and comment. Following a period of public comment, including the possibility of a public meeting, EPA selects a final remedy and memorializes it in a public document called a Record of Decision (ROD). Id. at § 300.430(f)(3)(F).

On March 29, 1999, EPA issued an amendment of the ROD for the "source control operable unit" for Neal's Landfill. This document explained that the original remedy for Neal's Landfill called for the excavation of 320,000 cubic yards of PCB contaminated landfill material and treatment through construction of an approved waste-fired incinerator. The modified remedy called for the excavation and removal of material with a high level contamination (the hot spots) to be followed by the construction of a landfill cap. Prior to adopting the hot spots excavation remedy, EPA considered alternatives, including the total excavation of the landfill. It concluded that the hot spots remedy was superior to total excavation in light of the nine regulatory criteria. As required by the regulations, EPA took public comment and held a hearing in Bloomington on the proposed remedies. This ROD Amendment dealt only with the source control component.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frey v. Environmental Protection Agency
751 F.3d 461 (Seventh Circuit, 2014)
T & B LTD. INC. v. City of Chicago
369 F. Supp. 2d 989 (N.D. Illinois, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
403 F.3d 828, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20076, 60 ERC (BNA) 1097, 2005 U.S. App. LEXIS 5432, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frey-v-environmental-protection-agency-ca7-2005.