In Re FV Steel and Wire Co.

372 B.R. 446, 2007 Bankr. LEXIS 2470, 2007 WL 2116385
CourtUnited States Bankruptcy Court, E.D. Wisconsin
DecidedJuly 19, 2007
Docket19-21177
StatusPublished
Cited by1 cases

This text of 372 B.R. 446 (In Re FV Steel and Wire Co.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re FV Steel and Wire Co., 372 B.R. 446, 2007 Bankr. LEXIS 2470, 2007 WL 2116385 (Wis. 2007).

Opinion

MEMORANDUM DECISION ON ALLOWANCE OF CLAIM

SUSAN V. KELLEY, Bankruptcy Judge.

Background and Facts

In 1989, the United States Environmental Protection Agency (“EPA”) named various parties, including the Glidden Company and DeSoto, Inc., now known as Sherman Wire Company (the “Debtor”), as potentially responsible parties *449 (“PRPs”) liable for the cleanup of the Chemical Recycling, Inc. hazardous waste site located in Wylie, Texas (the “site” or the “CRI Site”). Without admitting liability, the PRPs entered into the Chemical Recycling, Inc. Site Agreement for Participation (the “Agreement”) to jointly manage the cleanup. The Agreement created the CRI Steering Committee (the “CRI Committee”) to organize the initiative and apportion the liability among the parties. The EPA issued an Administrative Consent Order on August 4, 1989, 1 and the PRPs contributed funds to the cleanup. 2 Various drums and tanks were removed in the 1989 to 1990 timeframe, and the site was fenced, but very little else occurred at the site until 2004, when a new EPA On Scene Coordinator was appointed. The EPA issued Action Memoranda which purported to modify the Statement of Work in 2005 and 2006, but no work has been done at the site (except for testing and monitoring) since 1990.

The Debtor filed a chapter 11 petition on February 26, 2004. The claims bar date for nongovernmental entities was July 1, 2004, and the claims bar date for governmental units was August 24, 2004. The CRI Committee and Glidden filed timely proofs of claim related to the site, but, although it had filed claims related to the cleanup of other sites in which the Debtor was involved, the EPA did not file a proof of claim related to the CRI Site. After the claims bar date expired, the Debtor withdrew from the Agreement. The CRI Committee and Glidden 3 then sought leave to file a late proof of claim on behalf of the EPA, claiming that excusable neglect operated to excuse its failure to file this claim prior to the bar date. Although this Court ruled that the doctrine of excusable neglect as dictated by the 7th Circuit Court of Appeals did not permit the late filing of the claim, this decision was reversed on appeal by the District Court. On remand, this Court disallowed the claims filed by Glidden and the CRI Committee based on Bankruptcy Code § 502(e)(1)(B), which bars contingent claims for contribution and reimbursement. 4 However, the court permitted the CRI Committee to file the claim on behalf of the EPA 5 and proceeded with an estimation hearing under 11 U.S.C. § 502(c)(1). The parties have filed post trial briefs.

Arguments and Evidence Adduced at Estimation Hearing

The CRI Committee’s position is that the Debtor is one of the PRPs responsible for addressing the hazardous condition of the site. Citing the Comprehensive Environmental Response, Compensation, and *450 Liability Act (“CERCHA”), 6 the CRI Committee contends that the EPA is authorized and empowered to enforce the Consent Order against the Debtor, and alleges that the Debtor, among the other PRPs, was ordered by the EPA to conduct a removal action to address the conditions at the site, that the cleanup is not complete, anddhat the Debtor is jointly and severally liable for the $1.7-$1.9 million estimated cost to finish the cleanup.

The Debtor contends that the cleanup is virtually complete, and points out that no activity has taken place at the site for many years. The Debtor argues that even in the unlikely event that further cleanup would be required by the EPA, all that should be necessary is monitoring and/or capping the area where the concentration of contaminated soils is found. Moreover, the Debtor contends that the EPA’s claim should be limited to costs spent by the EPA itself, not by those costs that the EPA will visit upon the CRI Committee.

At the estimation hearing, the CRI Committee presented the expert testimony of Jay Winters, an employee of the environmental consulting firm Golder Associates, Inc. 7 who has been involved with the site since November 1989, and wrote a 2006 Site Investigation Report published in January 2007. Winters testified that even though the CRI Site is located in an industrial area and there is no threat to human life, the EPA will require the PRPs to remove about 1640 cubic yards — about 80 truck loads — of contaminated soil. 8 The trucks loaded with contaminated soil would be sent to a chemical waste management facility in Louisiana at a cost of about $1.5 million. While acknowledging that there is no evidence of any expanding plume of contaminated groundwater, he stated the groundwater at the site would require monitoring over 10 years. 9 However, he admitted that the primary waste at the CRI Site is lead and chlorinated solvents in stillbottoms 10 that pose a limited threat to the groundwater.

The CRI Committee acknowledges that “only the EPA has authority to determine that all obligations under the Consent Order have been satisfied.” However, the CRI Committee did not produce a single witness from the EPA to state what further action will be required for the CRI Site or whether EPA will require the soil to be removed or the groundwater monitored. Glidden’s director of environmental claims and remediation testified that to date, the EPA has not required any soils to be removed, although various reports showing the lead contamination as “fairly high,” have been provided to the EPA *451 since 1990. 11 Further, even in his role as an environmental consultant for the CRI Committee, Winters admitted that he never had any direct correspondence with the EPA nor any communications concerning whether the Modified Statement of Work would be approved or soil removal required. Currently, there is no EPA order in existence requiring soil removal, and the CRI Committee was at a loss to explain why the EPA has not taken action in the last 17 years. Even assuming that the cleanup of this site fell through some bureaucratic cracks until the appointment of the new On Scene Coordinator in 2004, there is no explanation as to why, if this site is in imminent need of cleanup, the EPA did not file its own proof of claim in Debtor’s case at that time, or seek an extension of the August 24, 2006 bar date to file a claim, especially when the EPA had filed other claims in this case for other contaminated sites.

The Debtor argued that the 1989 Consent Order was not “open-ended” but rather contained a specific, limited scope of activities that the Debtor and the other PRPs completed more than 17 years ago when the drum and tank removal action at the site was undertaken. 12

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
372 B.R. 446, 2007 Bankr. LEXIS 2470, 2007 WL 2116385, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-fv-steel-and-wire-co-wieb-2007.