Freeman v. Maple Point, Inc.

574 A.2d 684, 393 Pa. Super. 427, 1990 Pa. Super. LEXIS 928
CourtSupreme Court of Pennsylvania
DecidedMay 9, 1990
Docket2177
StatusPublished
Cited by16 cases

This text of 574 A.2d 684 (Freeman v. Maple Point, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Freeman v. Maple Point, Inc., 574 A.2d 684, 393 Pa. Super. 427, 1990 Pa. Super. LEXIS 928 (Pa. 1990).

Opinion

CAVANAUGH, Judge:

Robert and Marlene Freeman, the appellees herein, purchased a new home from the appellants, Maple Point, Inc. and Toll Brothers, in July, 1984. The house was part of a housing development of single homes and the purchase price was $95,900.00. The house was situated on a lot approximately 80 feet x 130 feet. Because of the grading *429 of the lot and the nature of the soil, which had a high clay content, and the construction of the driveway, water collected in certain areas of the lot after heavy rains. This was brought to the builder’s attention by the Freemans and the builder attempted to correct the situation by regrading the property. The Freemans also made improvements on the house after they purchased it by enclosing the patio at the rear of the house and adding a 12 feet x 13 feet concrete patio. The appellees also put in trees and sod on the property.

After at least four attempts by the builder to regrade the property were not successful in solving the surface water problem, a civil action in assumpsit was commenced against Maple Point, Inc. and Toll Brothers. The demand for damages was more than $7,000.00, but less than $20,000.00 and the matter was referred to arbitration. An award was entered by the arbitrators in favor of the appellees and against the appellants in the amount of $5,874.55. Appellants filed a timely appeal to the Court of Common Pleas. Following a jury trial before Ward, J., a verdict was entered in favor of the appellees and against the appellants in the amount of $45,785.00. The appellants’ motions for new trial and for judgment n.o.v. were denied and judgment was entered on the verdict. An appeal has been taken to this court from the judgment of the court below.

The appellees presented testimony at trial by Jonathan Tabas, a registered engineer and land surveyor, who testified that the driveway was the main contributor to the problems connected with surface water. He also concluded that the installation of a french drain was necessary as well as removal and proper construction of the driveway. His estimate of the cost for. correcting the problem of excess water was $50,738.00. 1 The appellants’ expert witness, Mr. *430 Froshour, estimated that it would cost approximately $10,-000. to $12,000.00 to remedy the situation.

In our opinion, the appellees, the plaintiffs below, did not properly establish damages. The measure of damages for breach of contract in the construction of a house containing defects is set forth in Gadbois v. Leb-Co. Builders, Inc., 312 Pa.Super. 144, 152, 458 A.2d 555, 559 (1983) wherein we stated:

The measure of damages in cases where a homeowner sues for defective construction is the difference between the market value of the house as constructed and the market value that the house would have had if constructed as promised, with the qualification that if it is reasonably practical to cure the defects in construction by repair, and if the cost of repairs does not exceed the difference in market value, then the measure of damages is the cost of repairs.

In the instant case, the appellees presented no evidence whatsoever as to the value of their house as constructed with all of its water problems, and the value it would have had with proper drainage. Only by establishing probable diminution in value because of the improper grading and *431 driveway construction, would it be possible to determine if the damages awarded in the amount of $45,785. were appropriate. The cost of repairs of $45,785. would be excessive if the house had not diminished in value to at least that extent.

In the recent case of Douglass v. Licciardi Construction Co., Inc., 386 Pa.Super. 292, 562 A.2d 913, 915-916 (1989), we stated:

Pennsylvania courts, consistently therewith, have generally allowed damages for incomplete or defective performance of a building contract to be measured by the cost of completing the work or correcting the defects by another contractor. See, e.g.: Ecksel v. Orleans Construction Co., 360 Pa.Super. 119, 519 A.2d 1021 (1987); Steinhauer v. Wilson, 336 Pa.Super. 155, 485 A.2d 477 (1984); Brourman v. Bova, 198 Pa.Super. 279, 182 A.2d 245 (1962). It is only where the cost of completing performance or of remedying the defects is clearly disproportionate to the probable loss in value to the injured party that damages will be measured by the difference between the market price that the property would have had without the defects and the market price of the property with the defects. Although articulating the rule in a slightly different manner, the Court acknowledged and followed the same principle in Gadbois v. Leb-Co. Builders, Inc., 312 Pa.Super. 144, 458 A.2d 555 (1983). Where the cost of remedying the defects in construction is not clearly disproportionate to the probable loss in value to the injured party, the breaching contractor cannot require that the injured party’s damages be measured by the difference between the market price of the property without the defects and the price of the property with the defects. (Emphasis added.) 2

*432 The appellees did not establish what the value of their house would have been had the surface water problem not existed, and its diminished value because of the water problem. The jury entered a verdict based on the cost of correcting the situation as that was the only issue submitted to it. The verdict in the amount of $45,785.00 represented almost 48% of the cost of the house and it is clear in these circumstances that the jury should have had some idea as to the diminution of value in order to avoid a windfall to the appellants. The rule set forth in Douglass v. Licciardi Construction Co., Inc., supra, requires that the cost of repairs be clearly disproportionate to the probable loss in value before damages are limited to the loss in value. Therefore, there must be some evidence produced by the plaintiff of the reduction in value, although it need not be shown with exactitude. There must be a balancing between the probable diminution in value, which is often quite nebulous, and the cost of repairs which may be determined with greater accuracy. However, there must be some reasonable basis for determining reduction in value, before a judgment may be made that the cost of repairs is a *433 proper measure of damages, where the required repairs to a new house represent a high percentage of the cost of the house. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woullard, D v. Sanner Concrete
2020 Pa. Super. 263 (Superior Court of Pennsylvania, 2020)
Carl, T. v. Noonan, G.
Superior Court of Pennsylvania, 2015
Carl v. Noonan
39 Pa. D. & C.5th 520 (Philadelphia County Court of Common Pleas, 2014)
Electroplating Technologies Ltd. v. HH Sumco Inc.
11 Pa. D. & C.5th 160 (Lehigh County Court of Common Pleas, 2009)
DEPT. OF GEN. SERV. v. US Mineral Prod.
898 A.2d 590 (Supreme Court of Pennsylvania, 2006)
Doe v. Raezer
664 A.2d 102 (Superior Court of Pennsylvania, 1995)
KRYSMALSKI BY KRYSMALSKI v. Tarasovich
622 A.2d 298 (Superior Court of Pennsylvania, 1993)
Bonavitacola v. Cluver
619 A.2d 1363 (Superior Court of Pennsylvania, 1993)
Gloviak v. Tucci Construction Co.
608 A.2d 557 (Superior Court of Pennsylvania, 1992)
Amodeo v. Ryan Homes, Inc.
595 A.2d 1232 (Superior Court of Pennsylvania, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
574 A.2d 684, 393 Pa. Super. 427, 1990 Pa. Super. LEXIS 928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/freeman-v-maple-point-inc-pa-1990.