Freedom Springs Water v. Great Spring

District Court, D. New Hampshire·Decided August 6, 1999·No. CV-98-676-JD·Published

Opinion

Freedom Springs Water v. Great Spring CV-98-676-JD 08/06/99 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Freedom Springs Water Co., Inc.

v. Civil No. 98-676-JD Great Spring Waters of America, Inc.

O R D E R

Freedom Springs Water Company seeks a stay of arbitration of its contract disputes with Great Spring Waters of America. In support of a stay. Freedom Springs argues that the arbitration clause in the parties' agreement does not cover the breach of contract issues presently before the arbitrator. Great Spring objects, contending that the arbitration clause in the parties' agreement reguires arbitration of all of the issues currently in arbitration, including the breach of contract claims.

During a conference call on the status of the case, the parties agreed to address the scope of the arbitration clause in a motion for partial summary judgment and an objection. Great Spring has filed a motion for summary judgment asking the court to deny Freedom Springs's motion for a stay of arbitration, based on the meaning of the arbitration clause. Freedom Springs filed an objection. As the parties agree that the guestion of the arbitrability of the breach of contract issues may be resolved as a matter of law, the court will address both the plaintiff's

motion to stay arbitration (document no. 2) and the defendant's motion for summary judgment (document no. 30) together.1

Background2

The plaintiff. Freedom Springs Water Company, operates natural water springs in Freedom, New Hampshire. The defendant. Great Spring Water of America, which is a division of Perrier Company, is in the business of buying and distributing bottled water. The parties entered a contract, dated January 6, 1996, under which Freedom Springs agreed to supply water and Great Spring agreed to purchase water, based on certain conditions, for a ten year period. The agreement provided that Great Spring would construct facilities for pumping and piping water from Freedom Springs and be repaid for the development costs through rebates on the water purchased from Freedom Springs. The agreement also reguired that Freedom Springs's water meet specified guality standards.

The facilities at Freedom Springs began producing water for

1The parties' reguests for oral argument are denied as additional argument is not likely to be of assistance to the court and the parties failed to submit a written statement justifying their reguests. See LR 7.1(d).

2The background facts are provided as a factual summary of the parties' relationship and not as factual findings.

Great Spring in June of 1996. A temporary interruption occurred in August of 1996 when the water from Freedom Springs's facility tested for bacteria in excess of the agreed guality standards. In March of 1997, the property where Freedom Springs operates was accidentally flooded, and the springs contaminated. The parties then disputed whether the guality of Freedom Springs's water met their agreed standards. Freedom Springs alleges that Great Spring stopped making payments in October of 1997.

Freedom Springs, represented by one of its principals, William Foord, filed a demand for arbitration on May 2, 1998, asking that issues about payments, indemnification, exclusivity, water guality and testing, and notice be arbitrated as provided in the parties' agreement. Great Spring notified Freedom Springs on May 7, 1998, that the agreement was terminated. Great Spring filed its answer in the arbitration proceeding with counterclaims seeking repayment of money spent in developing Freedom Springs's facilities and damages for breach of the parties' agreement. The arbitrator held a series of telephone conferences in August and September of 1998 and ordered the parties to provide certain discovery and to submit statements of the issues they intended to arbitrate.

On October 13, 1998, after his attorney reviewed the materials submitted in the arbitration proceeding, William Foord

submitted a restatement and amendment of the issues Freedom Springs wanted to arbitrate in response to Great Spring's counterclaims. Freedom Springs's amendments asserted breach of contract claims against Great Spring and sought additional damages. The arbitrator's order dated October 27, 1998, indicates that Freedom Springs withdrew its October 13 pleading and, instead, asserted claims in an October 26 pleading, that does not seem to be included in the record. On November 3, the arbitrator dismissed several of Freedom Springs's claims in response to a motion by Great Spring.

In early November, Foord moved for a continuance in the arbitration proceeding, explaining that his attorney was no longer able to represent Freedom Springs and asking for time to find new counsel. On November 30, 1998, Freedom Springs's new counsel moved for a ninety day continuance of the arbitration hearing scheduled for December 9, 10, and 11, 1998. Freedom Springs filed the action in this court on December 7, 1998, alleging a breach of contract claim against Great Spring and seeking temporary and permanent stays of the arbitration proceeding. The parties then stipulated to a temporary stay pending the decision on Freedom Springs's motion for a preliminary injunction.

Discussion

The parties do not dispute that they agreed to arbitrate some issues, although they differ as to whether their arbitration agreement applies to all of the issues being considered in their current arbitration proceeding. The Federal Arbitration Act ("FAA") applies to this case. See 9 U.S.C.A. § 2. Unless the parties clearly agreed to arbitrate the issue of arbitrability of their dispute, the court decides whether the parties' dispute is subject to their arbitration agreement. See First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 944-46 (1995). The parties did not clearly agree to arbitrate the meaning of the arbitration clause in this case, nor has either party argued that the agreement provided for arbitration of the meaning of the clause.

Courts may stay arbitration that is not authorized by the parties' agreement. See 9 U.S.C.A. § 4; see also PCS 2 000 L .P . v. Romulus Telecomm. Inc., 148 F.3d 32, 25 (1st Cir. 1998); Gruntal & Co. v. Steinberg, 854 F. Supp. 324, 331 (D.N.J. 1994). The FAA indicates that "arbitrability is to be determined on an issue-by-issue basis, without regard to the way that the issues are grouped into claims." Summer Rain v. Donning Co., 964 F.2d 1455, 1461 (4th Cir. 1992).

A. The Parties' Arbitration Agreement Freedom Springs challenges the arbitrability of the breach of contract issues that have been submitted for arbitration. The arbitration clause in the parties' agreement provides:

In order to resolve any dispute under this agreement guickly and efficiently, at the minimum cost and expense, the parties agree that in the event a dispute arises under the terms of this Agreement, in connection with fact or interpretation and meaning thereof, those limited issues shall be submitted to arbitration under the Rules of the American Arbitration Association, established by the American Arbitration Association in the City of Boston.

Water Supply Agreement at 5 13.4. Freedom Springs argues that the clause limits arbitration to disputes arising while the agreement was in effect and does not apply to claims of breach of the entire agreement that have arisen since Great Spring terminated the agreement. Great Spring asserts the strong policy of the FAA to resolve doubt in favor of arbitrability and argues that the terms of the arbitration clause permit arbitration of the parties' breach of contract claims.

The FAA demonstrates a strong federal policy in favor of arbitration. Moses H. Cone Memorial Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24 (1983). Arbitration is available, however, only by agreement, and, therefore, no party can be compelled to arbitrate disputes or issues that are not part of the parties' agreement. See 9 U.S.C.A. § 2; Volt Info. Sciences, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Freedom Springs Water v. Great Spring, (D.N.H. 1999).

Freedom Springs Water v. Great Spring (Freedom Springs Water v. Great Spring) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
McCarthy v. Azure
22 F.3d 351 (First Circuit, 1994)
Menorah Insurance v. INX Reinsurance Corp.
72 F.3d 218 (First Circuit, 1995)
PCS 2000 LP v. Romulus Telecommunications, Inc.
148 F.3d 32 (First Circuit, 1998)
Mantle v. Upper Deck Co.
956 F. Supp. 719 (N.D. Texas, 1997)
Apgar v. Commercial Union Insurance
683 A.2d 497 (Supreme Judicial Court of Maine, 1996)
Gruntal & Co., Inc. v. Steinberg
854 F. Supp. 324 (D. New Jersey, 1994)
Brackett v. Middlesex Insurance
486 A.2d 1188 (Supreme Judicial Court of Maine, 1985)
Waltman & Co. v. Leavitt
1999 ME 4 (Supreme Judicial Court of Maine, 1999)