Freedom Springs Water v. Great Spring CV-98-676-JD 08/06/99 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Freedom Springs Water Co., Inc.
v. Civil No. 98-676-JD
Great Spring Waters of America, Inc.
O R D E R
Freedom Springs Water Company seeks a stay of arbitration of
its contract disputes with Great Spring Waters of America. In
support of a stay. Freedom Springs argues that the arbitration
clause in the parties' agreement does not cover the breach of
contract issues presently before the arbitrator. Great Spring
objects, contending that the arbitration clause in the parties'
agreement reguires arbitration of all of the issues currently in
arbitration, including the breach of contract claims.
During a conference call on the status of the case, the
parties agreed to address the scope of the arbitration clause in
a motion for partial summary judgment and an objection. Great
Spring has filed a motion for summary judgment asking the court
to deny Freedom Springs's motion for a stay of arbitration, based
on the meaning of the arbitration clause. Freedom Springs filed
an objection. As the parties agree that the guestion of the
arbitrability of the breach of contract issues may be resolved as
a matter of law, the court will address both the plaintiff's motion to stay arbitration (document no. 2) and the defendant's
motion for summary judgment (document no. 30) together.1
Background2
The plaintiff. Freedom Springs Water Company, operates
natural water springs in Freedom, New Hampshire. The defendant.
Great Spring Water of America, which is a division of Perrier
Company, is in the business of buying and distributing bottled
water. The parties entered a contract, dated January 6, 1996,
under which Freedom Springs agreed to supply water and Great
Spring agreed to purchase water, based on certain conditions, for
a ten year period. The agreement provided that Great Spring
would construct facilities for pumping and piping water from
Freedom Springs and be repaid for the development costs through
rebates on the water purchased from Freedom Springs. The
agreement also reguired that Freedom Springs's water meet
specified guality standards.
The facilities at Freedom Springs began producing water for
1The parties' reguests for oral argument are denied as additional argument is not likely to be of assistance to the court and the parties failed to submit a written statement justifying their reguests. See LR 7.1(d).
2The background facts are provided as a factual summary of the parties' relationship and not as factual findings.
2 Great Spring in June of 1996. A temporary interruption occurred
in August of 1996 when the water from Freedom Springs's facility
tested for bacteria in excess of the agreed guality standards.
In March of 1997, the property where Freedom Springs operates was
accidentally flooded, and the springs contaminated. The parties
then disputed whether the guality of Freedom Springs's water met
their agreed standards. Freedom Springs alleges that Great
Spring stopped making payments in October of 1997.
Freedom Springs, represented by one of its principals,
William Foord, filed a demand for arbitration on May 2, 1998,
asking that issues about payments, indemnification, exclusivity,
water guality and testing, and notice be arbitrated as provided
in the parties' agreement. Great Spring notified Freedom Springs
on May 7, 1998, that the agreement was terminated. Great Spring
filed its answer in the arbitration proceeding with counterclaims
seeking repayment of money spent in developing Freedom Springs's
facilities and damages for breach of the parties' agreement. The
arbitrator held a series of telephone conferences in August and
September of 1998 and ordered the parties to provide certain
discovery and to submit statements of the issues they intended to
arbitrate.
On October 13, 1998, after his attorney reviewed the
materials submitted in the arbitration proceeding, William Foord
3 submitted a restatement and amendment of the issues Freedom
Springs wanted to arbitrate in response to Great Spring's
counterclaims. Freedom Springs's amendments asserted breach of
contract claims against Great Spring and sought additional
damages. The arbitrator's order dated October 27, 1998,
indicates that Freedom Springs withdrew its October 13 pleading
and, instead, asserted claims in an October 26 pleading, that
does not seem to be included in the record. On November 3, the
arbitrator dismissed several of Freedom Springs's claims in
response to a motion by Great Spring.
In early November, Foord moved for a continuance in the
arbitration proceeding, explaining that his attorney was no
longer able to represent Freedom Springs and asking for time to
find new counsel. On November 30, 1998, Freedom Springs's new
counsel moved for a ninety day continuance of the arbitration
hearing scheduled for December 9, 10, and 11, 1998. Freedom
Springs filed the action in this court on December 7, 1998,
alleging a breach of contract claim against Great Spring and
seeking temporary and permanent stays of the arbitration
proceeding. The parties then stipulated to a temporary stay
pending the decision on Freedom Springs's motion for a
preliminary injunction.
4 Discussion
The parties do not dispute that they agreed to arbitrate
some issues, although they differ as to whether their arbitration
agreement applies to all of the issues being considered in their
current arbitration proceeding. The Federal Arbitration Act
("FAA") applies to this case. See 9 U.S.C.A. § 2. Unless the
parties clearly agreed to arbitrate the issue of arbitrability of
their dispute, the court decides whether the parties' dispute is
subject to their arbitration agreement. See First Options of
Chicago, Inc. v. Kaplan, 514 U.S. 938, 944-46 (1995). The
parties did not clearly agree to arbitrate the meaning of the
arbitration clause in this case, nor has either party argued that
the agreement provided for arbitration of the meaning of the
clause.
Courts may stay arbitration that is not authorized by the
parties' agreement. See 9 U.S.C.A. § 4; see also PCS 2 000 L .P .
v. Romulus Telecomm. Inc., 148 F.3d 32, 25 (1st Cir. 1998);
Gruntal & Co. v. Steinberg, 854 F. Supp. 324, 331 (D.N.J. 1994).
The FAA indicates that "arbitrability is to be determined on an
issue-by-issue basis, without regard to the way that the issues
are grouped into claims." Summer Rain v. Donning Co., 964 F.2d
1455, 1461 (4th Cir. 1992).
5 A. The Parties' Arbitration Agreement
Freedom Springs challenges the arbitrability of the breach
of contract issues that have been submitted for arbitration. The
arbitration clause in the parties' agreement provides:
Free access — add to your briefcase to read the full text and ask questions with AI
Freedom Springs Water v. Great Spring CV-98-676-JD 08/06/99 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Freedom Springs Water Co., Inc.
v. Civil No. 98-676-JD
Great Spring Waters of America, Inc.
O R D E R
Freedom Springs Water Company seeks a stay of arbitration of
its contract disputes with Great Spring Waters of America. In
support of a stay. Freedom Springs argues that the arbitration
clause in the parties' agreement does not cover the breach of
contract issues presently before the arbitrator. Great Spring
objects, contending that the arbitration clause in the parties'
agreement reguires arbitration of all of the issues currently in
arbitration, including the breach of contract claims.
During a conference call on the status of the case, the
parties agreed to address the scope of the arbitration clause in
a motion for partial summary judgment and an objection. Great
Spring has filed a motion for summary judgment asking the court
to deny Freedom Springs's motion for a stay of arbitration, based
on the meaning of the arbitration clause. Freedom Springs filed
an objection. As the parties agree that the guestion of the
arbitrability of the breach of contract issues may be resolved as
a matter of law, the court will address both the plaintiff's motion to stay arbitration (document no. 2) and the defendant's
motion for summary judgment (document no. 30) together.1
Background2
The plaintiff. Freedom Springs Water Company, operates
natural water springs in Freedom, New Hampshire. The defendant.
Great Spring Water of America, which is a division of Perrier
Company, is in the business of buying and distributing bottled
water. The parties entered a contract, dated January 6, 1996,
under which Freedom Springs agreed to supply water and Great
Spring agreed to purchase water, based on certain conditions, for
a ten year period. The agreement provided that Great Spring
would construct facilities for pumping and piping water from
Freedom Springs and be repaid for the development costs through
rebates on the water purchased from Freedom Springs. The
agreement also reguired that Freedom Springs's water meet
specified guality standards.
The facilities at Freedom Springs began producing water for
1The parties' reguests for oral argument are denied as additional argument is not likely to be of assistance to the court and the parties failed to submit a written statement justifying their reguests. See LR 7.1(d).
2The background facts are provided as a factual summary of the parties' relationship and not as factual findings.
2 Great Spring in June of 1996. A temporary interruption occurred
in August of 1996 when the water from Freedom Springs's facility
tested for bacteria in excess of the agreed guality standards.
In March of 1997, the property where Freedom Springs operates was
accidentally flooded, and the springs contaminated. The parties
then disputed whether the guality of Freedom Springs's water met
their agreed standards. Freedom Springs alleges that Great
Spring stopped making payments in October of 1997.
Freedom Springs, represented by one of its principals,
William Foord, filed a demand for arbitration on May 2, 1998,
asking that issues about payments, indemnification, exclusivity,
water guality and testing, and notice be arbitrated as provided
in the parties' agreement. Great Spring notified Freedom Springs
on May 7, 1998, that the agreement was terminated. Great Spring
filed its answer in the arbitration proceeding with counterclaims
seeking repayment of money spent in developing Freedom Springs's
facilities and damages for breach of the parties' agreement. The
arbitrator held a series of telephone conferences in August and
September of 1998 and ordered the parties to provide certain
discovery and to submit statements of the issues they intended to
arbitrate.
On October 13, 1998, after his attorney reviewed the
materials submitted in the arbitration proceeding, William Foord
3 submitted a restatement and amendment of the issues Freedom
Springs wanted to arbitrate in response to Great Spring's
counterclaims. Freedom Springs's amendments asserted breach of
contract claims against Great Spring and sought additional
damages. The arbitrator's order dated October 27, 1998,
indicates that Freedom Springs withdrew its October 13 pleading
and, instead, asserted claims in an October 26 pleading, that
does not seem to be included in the record. On November 3, the
arbitrator dismissed several of Freedom Springs's claims in
response to a motion by Great Spring.
In early November, Foord moved for a continuance in the
arbitration proceeding, explaining that his attorney was no
longer able to represent Freedom Springs and asking for time to
find new counsel. On November 30, 1998, Freedom Springs's new
counsel moved for a ninety day continuance of the arbitration
hearing scheduled for December 9, 10, and 11, 1998. Freedom
Springs filed the action in this court on December 7, 1998,
alleging a breach of contract claim against Great Spring and
seeking temporary and permanent stays of the arbitration
proceeding. The parties then stipulated to a temporary stay
pending the decision on Freedom Springs's motion for a
preliminary injunction.
4 Discussion
The parties do not dispute that they agreed to arbitrate
some issues, although they differ as to whether their arbitration
agreement applies to all of the issues being considered in their
current arbitration proceeding. The Federal Arbitration Act
("FAA") applies to this case. See 9 U.S.C.A. § 2. Unless the
parties clearly agreed to arbitrate the issue of arbitrability of
their dispute, the court decides whether the parties' dispute is
subject to their arbitration agreement. See First Options of
Chicago, Inc. v. Kaplan, 514 U.S. 938, 944-46 (1995). The
parties did not clearly agree to arbitrate the meaning of the
arbitration clause in this case, nor has either party argued that
the agreement provided for arbitration of the meaning of the
clause.
Courts may stay arbitration that is not authorized by the
parties' agreement. See 9 U.S.C.A. § 4; see also PCS 2 000 L .P .
v. Romulus Telecomm. Inc., 148 F.3d 32, 25 (1st Cir. 1998);
Gruntal & Co. v. Steinberg, 854 F. Supp. 324, 331 (D.N.J. 1994).
The FAA indicates that "arbitrability is to be determined on an
issue-by-issue basis, without regard to the way that the issues
are grouped into claims." Summer Rain v. Donning Co., 964 F.2d
1455, 1461 (4th Cir. 1992).
5 A. The Parties' Arbitration Agreement
Freedom Springs challenges the arbitrability of the breach
of contract issues that have been submitted for arbitration. The
arbitration clause in the parties' agreement provides:
In order to resolve any dispute under this agreement guickly and efficiently, at the minimum cost and expense, the parties agree that in the event a dispute arises under the terms of this Agreement, in connection with fact or interpretation and meaning thereof, those limited issues shall be submitted to arbitration under the Rules of the American Arbitration Association, established by the American Arbitration Association in the City of Boston.
Water Supply Agreement at 5 13.4. Freedom Springs argues that
the clause limits arbitration to disputes arising while the
agreement was in effect and does not apply to claims of breach of
the entire agreement that have arisen since Great Spring
terminated the agreement. Great Spring asserts the strong policy
of the FAA to resolve doubt in favor of arbitrability and argues
that the terms of the arbitration clause permit arbitration of
the parties' breach of contract claims.
The FAA demonstrates a strong federal policy in favor of
arbitration. Moses H. Cone Memorial Hosp. v. Mercury Constr.
Corp., 460 U.S. 1, 24 (1983). Arbitration is available, however,
only by agreement, and, therefore, no party can be compelled to
arbitrate disputes or issues that are not part of the parties'
agreement. See 9 U.S.C.A. § 2; Volt Info. Sciences, Inc. v.
6 Board of Trustees of Leland Stanford, Jr. Univ., 489 U.S. 468,
479 (1989). McCarthy v. Azure, 22 F.3d 351, 354 (1st Cir. 1994).
"That is because a party who has not agreed to arbitrate will
normally have a right to a court's decision about the merits of
its dispute (say, as here, its obligation under a contract)."
First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 942
(1995). Whether a particular dispute is subject to arbitration
depends on the parties' intent as demonstrated by their
agreement. See PaineWebber Inc. v. Elahi, 87 F.3d 589, 593 (1st
Cir. 1996).
State law provides the basic principles of contract
interpretation, although state arbitration law is not applicable
to FAA cases. See PaineWebber, 87 F.3d at 593. The interpre
tation of the arbitration clause is controlled by Maine law.
Maine follows the common principles of contract interpretation
that language is construed according to its plain and common
meaning taken in the context of the entire contract. See Apqar
v. Commercial Union Ins. Co., 683 A.2d 497, 498 (Me. 1996);
Brackett v. Middlesex Ins. Co., 486 A.2d 1188, 1190 (Me. 1985).
A contract provision is ambiguous only if it is "reasonably
susceptible to two or more interpretations, or its meaning is
unclear." Waltman & Co. v. Leavitt, 722 A.2d 862, 864 (Me.
1999). In addition to state law interpretive rules, analysis of
7 an arbitration clause "is informed by FAA jurisprudence." Id.
Great Spring argues that the arbitration clause's
introductory phrase, "In order to resolve any dispute under this
agreement," plainly expresses a broad and comprehensive scope of
the agreement. Freedom Springs, however, correctly points out
that the arbitration clause expressly applies to "limited
issues." The clause explains that the "limited issues" for
arbitration are disputes under the agreement about facts or the
meaning of the agreement. Great Spring says that the issues in
arbitration fall within that definition, while Freedom Springs
says they do not.
Taken in the context of the whole arbitration clause, "any
dispute" is limited to "any dispute under this agreement . . . in
connection with fact or interpretation and meaning of [the
agreement]." Language limiting arbitration to disputes arising
under the agreement has been interpreted as a narrow provision
compared to a broad provision to arbitrate all disputes. See
McCarthy, 22 F.3d 351, 358 (1st Cir. 1994); see also New York
News Inc. v. Newspaper Guild of New York, 927 F.2d 82, 83-84 (2d
Cir. 1991). The presumption in favor of arbitrability has less
force in cases where the parties have limited their agreement to
arbitrate specific disputes or issues. See McDonnell Douglas
Finance v. Pa. Power & Light Co., 858 F.2d 825, 832 (2d Cir. 1988). Nevertheless, disputes "under this agreement" could
include breach of contract issues if the issues were not further
limited.
Freedom Springs argues that the phrases "under this
agreement" and "under the terms of this Agreement" limit
arbitrable issues to those arising during performance and before
breach and termination of the agreement. Unless an arbitration
clause expressly limits its application to the life of the
agreement, however, the clause continues to apply to arbitrable
disputes that arise under the terms of a terminated agreement
even if the events occur after termination. See, e.g., Nolde
Bros., Inc. v. Local No. 358, Bakery & Confectionery Workers
Union, 430 U.S. 243, 255 (1977); Rilev Mfg. Co. v. Anchor Glass
Container Corp., 157 F.3d 775, 781 (10th Cir. 1998); Cincinnati
Typographical Union No. 3 v. Gannett Satellite Infor. Network ,
Inc., 17 F.3d 906, 910 (6th Cir. 1994); Sweet Dreams Unltd. v.
Dial-A-Mattress Internat'l, 1 F.3d 639, 643 (7th Cir. 1993).
Therefore, "under this agreement" does not limit arbitration to
issues that arose during performance of the agreement.
The arbitration clause limits arbitration to "any dispute
under this agreement . . . in connection with fact or
interpretation and meaning of [the agreement]." Therefore, based
on the expressed intent in the clause, the parties agreed to arbitrate issues about facts or the meaning of the agreement that
arise from disputes under the agreement. The guestion that must
be resolved is whether the issues raised in the parties'
arbitration proceeding are within the scope of their arbitration
agreement. Although Great Spring argues that all of the issues
in arbitration are arbitrable, the list Great Spring provides
merely cites factual disputes pertinent to the agreement, without
reference to the parties' underlying claims, and avoids the
issues of obligation, liability, remedies, and damages in the
breach of contract claims. Neither party has provided a list or
summary of all of the claims and issues that are currently
pending in the arbitration proceeding.
The record is unclear as to the status of Freedom Springs's
claims for arbitration. Freedom Springs initially filed nine
issues in its demand for arbitration eight of which state
disputes under particular provisions of the parties' agreement
and the ninth states a claim of promissory estoppel. The claims
for relief seek payment of money allegedly owed under the
agreement and compliance with other terms of the agreement.
Freedom Springs filed a restatement or amendment of its issues,
dated October 13, 1998, adding claims for breach of contract and
seeking damages. The arbitrator's order of October 27, 1998,
indicates that Freedom Springs filed a subseguent submission,
10 which is not included in the record, that withdrew the claims
added on October 13, but sought to substitute certain other
language that was indicated in brackets. The arbitrator ruled,
"Such bracketed sections only may be added as amendments to
Claimant's previous statement of claims." Order of October 27,
1998. On November 3, 1998, in response to Great Spring's motion
for summary disposition, the arbitrator dismissed Freedom
Springs's claims in paragraphs 2, 4, 8, and 9, apparently
referring to the original filing of issues.
In the meantime. Great Spring filed its answer with three
counterclaims. The first claim seeks recoupment of costs as
provided in section 3.1 of the agreement. The second is a breach
of contract claim seeking damages. The third claim states that
Freedom Springs failed to comply with section 4.1 of the
agreement reguiring it to obtain and maintain permits that
resulted in insecurity and costs to Great Spring. In sum, it
appears that some of the issues before the arbitrator raise only
factual disputes, which are arbitrable, while the breach of
contract claims and counterclaims, raise issues of liability and
damages that are not arbitrable.
Since the parties agreed to arbitrate factual issues
pertinent to disputes under the agreement and issues about the
meaning of the agreement, the arbitration proceeding is limited
11 to those issues. The parties did not agree to arbitrate legal
liability or the imposition of remedies or damages. Once the
fact and meaning issues are arbitrated, either party may resort
to the judicial process to resolve any claims for breach of
contract, damages, or enforcement of the contract terms. Of
course, once the pertinent facts and the meaning of disputed
parts of the agreement are determined, liability and the likely
remedies should be readily apparent so that further proceedings
may not be necessary.
B . Waiver
Great Spring contends, in opposition to Freedom Springs's
motion for a stay of arbitration, that Freedom Springs waived any
objection to the arbitrability of the issues raised in the
arbitration proceeding by initiating arbitration and filing
breach of contract claims in the proceeding. In general, a party
has been deemed to have waived an objection to arbitration if the
party participates extensively in the proceedings and raises an
objection only after an unfavorable result. See, e.g., ConnTech
Dev't Co. v. University of Connecticut Educ. Prop., Inc., 102
F.3d 677, 685 (2d Cir. 1996); Raytheon Co. v. Automated Business
Svs. Inc., 882 F.2d 6, 8 (1st Cir. 1989); Mantle v. Upper Deck
C o ., 956 F. Supp. 719, 735 (N.D. Tex. 1997) . The First Circuit
12 also has required a showing of prejudice by the opposing party as
a predicate to finding a waiver. See Menorah Ins. Co., Ltd. v.
INX Reinsurance Corp., 72 F.3d 218, 221 (1st Cir. 1995).
Since the parties do not dispute that they agreed to
arbitrate at least some issues, the mere initiation of
arbitration does not waive an objection to arbitration that
Freedom Springs's contends is not authorized by their agreement.
C f . Nqhiem v. NEC Electronic, Inc., 25 F.3d 1437, 1440 (9th Cir.
1994) (finding waiver after party initiated and substantially
completed arbitration before asserting lack of arbitrator's
authority). Freedom Springs initially raised claims in the
arbitration proceeding that it now contends are not arbitrable
and did not immediately object to Great Spring's counterclaims.
Before the hearings in the arbitration proceeding began, however.
Freedom Springs sought to withdraw some of its own claims and
moved for a continuance to settle the issue of arbitrability. On
the current record. Great Spring has not shown either that
Freedom Springs acquiesced in arbitration of the challenged
issues until it received an unfavorable result, or that it has
been prejudiced by Freedom Springs's conduct in the arbitration
proceeding.
Because the parties anticipated a need for discovery on the
waiver issue, it may be premature to resolve the waiver issue
13 based on the current record. For that reason, the issue of
waiver may be raised again, if necessary, in opposition to any
further court proceedings after the arbitration proceeding has
concluded.
C. Disposition
Since in the opinion of the court the scope of the
arbitration clause is clear, no further litigation is necessary
to resolve its meaning. Freedom Springs's motion to stay
arbitration is granted as to arbitration of any issues other than
the facts pertinent to disputes under the agreement or the
meaning of the agreement. Thus, arbitration is stayed as to the
disposition of the parties' legal obligations or liability and
imposition of damages or other remedies. The motion to stay is
denied as to arbitration of all factual issues pertinent to
disputes under the agreement and the meaning of the agreement.
Conclusion
For the foregoing reasons, the defendant's motion for
summary judgment (document no. 30) is granted in part and denied
in part as to the meaning of the arbitration clause. The
plaintiff's motion for a stay of arbitration (document no. 2) is
14 granted in part as is explained in this order. As no further
issues remain to be decided in this case, the clerk of court is
directed to enter judgment imposing a stay of arbitration as
defined in this order and to close the case.
SO ORDERED.
Joseph A. DiClerico, Jr, District Judge
August 6, 1999
cc: Donald L. Wyatt Jr., Esguire Kelly A. McEnaney, Esguire