Frank Lill & Son, Inc. v. Secretary of Labor

362 F.3d 840, 360 U.S. App. D.C. 398, 20 OSHC (BNA) 1673, 2004 U.S. App. LEXIS 6494, 2004 WL 725367
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 6, 2004
Docket03-1096
StatusPublished
Cited by12 cases

This text of 362 F.3d 840 (Frank Lill & Son, Inc. v. Secretary of Labor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frank Lill & Son, Inc. v. Secretary of Labor, 362 F.3d 840, 360 U.S. App. D.C. 398, 20 OSHC (BNA) 1673, 2004 U.S. App. LEXIS 6494, 2004 WL 725367 (D.C. Cir. 2004).

Opinion

Opinion for the court filed by Circuit Judge KAREN LeCRAFT HENDERSON.

KAREN LeCRAFT HENDERSON, Circuit Judge:

The Secretary of Labor (Labor), through the Occupational Safety and Health Administration (OSHA), cited Frank Lili & Son, Inc. (Lili) for willful violation of 29 C.F.R. § 1926.501(b)(1) which requires an employer to provide fall protection where employees work on a surface with an unprotected edge more than 6 feet above the level below. The Administrative Law Judge (ALJ) affirmed the citation as serious (rather than willful) and his decision became the final order of the Occupational Safety and Health Review Commission (OSHRC, Commission). Lili petitioned for review of the final order. For the reasons set forth below, we deny the petition for review.

I.

Lili is in the business of constructing power plants and process piping installations. In April 2001 Lili began construction of two eighty-foot heat recovery steam generators (HRSGs) in Newington, New Hampshire under a subcontract with general contractor Fluor Constructors (Fluor). On January 24, 2002 at about 9:30 a.m. OSHA Compliance Officer Stephen Rook visited the construction site to conduct a safety inspection. When he arrived, Rook went to Fluor’s job trailer and spoke with Fluor safety director Jim Reese, who accompanied Rook on an inspection of the site.

During his inspection, Rook observed two Lili employees at HRSG No. 2 “working at a platform approximately 100 feet up in the air without fall protection.” Tr. 16. He walked to HRSG No. 2 and began to climb its stairway toward the workers. While ascending, he encountered Lili site foreman Bob Brown. According to Rook, he informed Brown he was “on site for a complaint” and had “observed employees working without fall protection.” Tr. 18. Rook then continued up the stairs and saw two employees, Real Savoy and Kevin Gross, “working at the edge of the platform without fall protection.” Tr. 19. He photographed Savoy. Savoy’s only visible protection consisted of a horizontal wire rope, about 18 inches high, at the edge of the platform and “a ratline or horizontal lifeline” above his shoulder. Tr. 28. Rook spoke with Savoy and Gross who informed him that working without fall protection “was a pattern throughout the worksite or throughout the HRSGs on days prior, that employees weren’t always tied off’ and that “there isn’t a convenient place to tie off.” Tr. 25. They also told Rook that members of Lili management “had been working in the area when employees weren’t tied off.” Id.

A short time later, Rook met with Lili foreman Ron Tanguay, explained who he was and why he was at the site and stated he had seen employees working without fall protection. When asked, Tanguay confirmed that working without fall protection was “a recurring pattern,” Tr. 29, and told him of an incident 7-10 days earlier when Lili employee Rick Chamberlain “had slipped and fallen while walking *843 along the platform on the HRSG,” Tr. 30. After this conversation, Rook began to climb down the stairs to interview Chamberlain. While descending the stairs, Rook observed and photographed another Lili employee, Steve Drew, working without fall protection about 75 feet above the ground. Rook proceeded down the stairs and located Chamberlain. When asked about his fall, Chamberlain explained he had fallen toward the edge of the platform from about eight feet in and had landed about three feet from the edge. He also told Rook he had not been tied off. After this conversation, Rook inspected HRSG No. 1 and, although the workers there were tied off, Lili foreman Dwight Grant informed him “it was a frequent occurrence for employees not to be tied off while working on the HRSG.” Tr. 40.

The following day Rook returned to the Newington site and spoke with three members of Lili managemenNsite manager Bill Cole, site foreman Brown and site safety representative Neil Briscoe-and told them of his “findings the day earlier, inadequate fall protection which had occurred on the HRSGs.” Tr. 45. He then accompanied them to the top of HRSG No. 1 and “explained to them they had three options that they use according to the minimum OSHA standards, a fall protection system, a safety net system or a guardrail system.” Tr. 46. Rook visited the site a third time on January 28, 2002 and spoke with Bris-coe and Cole. Finally, on February 22, 2002 Rook met with management from all of the site contractors, including Lili, and discussed his inspection and the deficiencies he had observed.

On March 8, 2002 OSHA issued a citation to Lili for willful violation of 29 C.F.R. § 1926.501(b)(1), which provides: “Each employee on a walking/working surface (horizontal and vertical surface) with an unprotected side or edge which is 6 feet (1.8 m) or more above a lower level shall be protected from falling by the use of guardrail systems, safety net systems, or personal fall arrest systems.” Specifically, the citation alleged that Lili employees “were not adequately protected from falls of approximately 85 feet while working on HRSG #2.” JA 327. OSHA proposed a penalty of $49,500. Lili contested the citation and on April 14, 2002 the Secretary issued a complaint alleging that Lili had violated section 1926.501(b)(1) as described in the citation. Following an evidentiary hearing, the ALJ issued a decision, docketed January 9, 2003, which affirmed OSHA’s citation but amended it from “willful” to “serious” and imposed a $5,000 fine.

Lili filed a petition for discretionary review by the Commission. When no Commissioner directed review within 30 days of the ALJ’s decision, that decision became the Commission’s final order on February 10, 2003. See Notice of Final Order, OSHRC Docket No. 02-0564 (dated Feb. 11, 2003) (citing 29 C.F.R. §§ 2200.90(d), 661©).

Lili filed a timely petition for review on April 3, 2003.

II.

Lili first challenges the substance of the ALJ’s violation finding and then raises three additional legal arguments. We address Lill’s contentions in order.

A. The Finding of Violation

First, Lili challenges the ALJ’s finding of a violation on four grounds: (1) it is contrary to the evidence because the wire rope stretched along the platform perimeter qualifies as a “guardrail system” within the meaning of section 1926.501(b)(1); (2) the interpretation of the statutory term “guardrail system” adopted by the Secretary is unreasonable; (3) the ALJ erred in finding that anyone other than Gross and *844 Savoy was exposed to fall hazard and (4) the ALJ erred in finding Lili had constructive and actual notice of the violative conditions.

We conclude that the last three challenges have not been preserved for review because they were not raised in the petition for discretionary review (PDR) before the Commission. The Occupational Safety and Health Act expressly states: “No objection that has not been urged before the Commission shall be considered by the court, unless the failure or neglect to urge such objection shall be excused because of extraordinary circumstances.” 29 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New River Electrical Corp. v. OSHC
25 F.4th 213 (Fourth Circuit, 2022)
Secretary of Labor v. Walmart Stores East
919 F.3d 1073 (Eighth Circuit, 2019)
Johnson, Garry Wayne v. Alloy Fabrication, Inc.
2016 TN WC 254 (Tennessee Court of Workers' Comp. Claims, 2016)
Sea World of Florida, LLC v. Thomas Perez
748 F.3d 1202 (D.C. Circuit, 2014)
W.G. Yates & Sons Construction Co. v. Safety
459 F.3d 604 (Fifth Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
362 F.3d 840, 360 U.S. App. D.C. 398, 20 OSHC (BNA) 1673, 2004 U.S. App. LEXIS 6494, 2004 WL 725367, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frank-lill-son-inc-v-secretary-of-labor-cadc-2004.