Fox v. Velocity Solar Power, Inc.

District Court, E.D. California·Decided February 6, 2024·No. 2:23-cv-01319·Unknown

Opinion

ERIK FOX, No. 2:23-cv-1319-KJN Plaintiff, ORDER v. (ECF No. 5.) VELOCITY SOLAR POWER, INC., et al., Defendants. Plaintiff alleges multiple claims related to the marketing and construction of an additional structure and the installation of a solar power system on plaintiff’s land; plaintiff executed three contracts with defendant Velocity Solar Power, with the remaining defendants acting as alleged agents of Velocity.1 (ECF No. 1.) Defendants now move to compel arbitration based on language in the contracts. (ECF No. 5.) Plaintiff maintains these contracts were rescinded under California law as illegal home solicitation contracts and are unconscionable. (See ECF No. 9.) Defendants dispute plaintiff’s rescission contentions and maintain, regardless, that the Federal Arbitration Act preempts state law, as well as that the contracts delegate the issue of arbitrability to the arbitrator. (ECF No. 10.) For the reasons stated below, this matter is sent to arbitration. 1 This case proceeds before the undersigned on the consent of all parties, pursuant to 28 U.S.C. § 636(c). (ECF Nos. 9, 11, 12, 15.) General Factual Background In August of 2022, plaintiff hired Velocity to construct a freestanding building on his property (living space for his elderly mother), to provide a solar energy system, and to install that energy system on the building. (ECF No. 1 at ¶¶ 25-35.) Velocity and plaintiff entered three separate contracts: one for construction of the building (the “General Contract”), one for the sale of the solar system (the “Solar Contract”), and one for install of the solar system (the “Installation Contract”). (Id. at ¶¶ 52-53 and Exs. D, F, and G.) Excavation work for the new building began a month later. (Id. at ¶ 56.) However, problems and disputes between plaintiff and Velocity quickly arose and continued through April of 2023. (Id. at ¶¶ 57-80.) This resulted in plaintiff’s attempt to rescind all his contracts with Velocity. (Id. at ¶ 80.) Velocity disputed the validity of the rescission, leading plaintiff to file this lawsuit. Procedural Background On May 23, 2023, plaintiff filed suit in Placer County Superior Court, asserting 16 claims against defendants Velocity Solar Power, Inc; an Idaho corporation; Velocity Solar Power Installations, LLC, an Idaho LLC; as well as Darin Dowd, Jennifer Dowd, Ron Riisager, Dana Riisager, Emmett Edward Wyrick, Erika Wyrick, Joe Loomis, Molly Loomis, Heather Silvis, Granite Bay Excavating, Inc., a California corporation; and American Contractors Indemnity Co., a California corporation. (ECF No. 1-1.) Plaintiff alleges claims under the Racketeer Influenced and Corrupt Organizations Act (18 U.S.C. § 1961(c)); as well as fifteen contract- and misrepresentation-style claims under California law. (Id.) Defendants answered and removed to this court on federal question grounds. (ECF No. 1.) Approximately one month later, defendants moved to compel arbitration of all claims in the complaint against the “Velocity defendants” (all defendants save Granite Bay and American Contractors). (ECF No. 5.) Plaintiff opposed, defendant replied, the case was reassigned to the undersigned, and the court took the matter under submission without a hearing pursuant to Local Rule 230(g). (ECF Nos. 8, 10, 15, 20.) Plaintiff then requested judicial notice, which defendants opposed. (ECF Nos. 22, 24.) Legal Standards “[T]he federal law of arbitrability under the Federal Arbitration Act (“FAA”) governs the allocation of authority between courts and arbitrators.” Cox v. Ocean View Hotel Corp., 533 F.3d 1114, 1119 (9th Cir. 2008); see also AT&T Mobility LLC v. Concepcion, 131 S. Ct. 1740, 1742 (2011) (noting that the FAA represents “a liberal federal policy favoring arbitration [], and the fundamental principle that arbitration is a matter of contract”). “[T]he FAA limits courts’ involvement to determining ‘(1) whether a valid agreement to arbitrate exists and, if it does, (2) whether the agreement encompasses the dispute at issue.’” Id. If a valid agreement exists, “the FAA specifically directs federal district courts to stay proceedings and compel arbitration of ‘any issue referable to arbitration under an agreement in writing for such arbitration.’” Ziober v. BLB Res., Inc., 839 F.3d 814, 817 (9th Cir. 2016) (quoting 9 U.S.C. § 3); see also 9 U.S.C. § 4 (allowing a party to an arbitration agreement to petition a district court for an order directing arbitration). Additionally, parties can agree to expressly delegate any gateway issues to an arbitrator, in which case an arbitrator, rather than a court, must decide the arbitrability of the dispute. Brennan v. Opus Bank, 796 F.3d 1125, 1130 (9th Cir. 2015) (internal quotation marks and citation omitted). If the parties delegate the threshold issues to an arbitrator, the FAA leaves no place for the exercise of discretion by a district court, but instead mandates that the district court direct the parties to proceed to arbitration on those issues. See Brennan, 796 F.3d at 1130; see also, e.g., Gillette v. First Premier Bank, 2013 WL 3205827, at *2 (S.D. Cal. June 24, 2013) (explaining that “[g]iven the parties’ agreement to arbitrate gateway issues of arbitrability, there is actually very little here for the Court to decide” and compelling arbitration as to all gateway issues); Roszak v. U.S. Foodservice, Inc., 628 Fed. Appx. 513, 514 (9th Cir. 2016) (affirming order compelling arbitration because “the parties incorporated the [AAA] rules into their agreement and therefore agreed to arbitrate the question of arbitrability.”); Bank of America, N.A. v. Michiletti Family P'ship, 2008 WL 4571245, at *6 (N.D. Cal., Oct. 14, 2008) (where parties agreed to arbitrate the issue of arbitrability, the court was divested of its authority and compelled arbitration). To make this determination, the court must analyze the underlying contract to decide whether the parties have “clearly and unmistakably” committed the question of arbitrability to the arbitrator. Brennan, 796 F.3d at 1130 (cleaned up). Parties’ incorporation of the American Arbitration Association Arbitration Rules (“AAA Rules”) into an agreement constitutes clear and unmistakable evidence that the parties agreed to arbitrate arbitrability. Id. Fundamentally speaking, a party can only be compelled to arbitrate a dispute if they agreed to submit that dispute to arbitration. AT&T Techs., Inc. v. Comm. Workers of Am., 475 U.S. 643, 648-49 (1986). “[A] party may challenge the validity or applicability of [an] arbitration provision by raising the same defenses available to a party seeking to avoid the enforcement of any contract” under the applicable state law. Cox, 533 F.3d at 1121 (citations omitted); see also 9 U.S.C. § 2 (providing that contractual arbitration clauses are “valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract”). “Under California law, a contractual provision is unenforceable if it is both procedurally and substantively unconscionable.” Kilgore v. KeyBank, Nat. Ass'n, 718 F.3d 1052, 1058 (9th Cir. 2013) (citing Armendariz v. Found. Health Psychcare Servs., Inc., 24 Cal.4th 83, 114 (2000)); see also Concepcion, 131 S. Ct. at 1746

Free access — add to your briefcase to read the full text and ask questions with AI

Fox v. Velocity Solar Power, Inc., (E.D. Cal. 2024).

Fox v. Velocity Solar Power, Inc. (Fox v. Velocity Solar Power, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Matthew Kilgore v. Keybank, National Association
718 F.3d 1052 (Ninth Circuit, 2013)
Peng v. First Republic Bank CA1/1
219 Cal. App. 4th 1462 (California Court of Appeal, 2013)
Armendariz v. Found. Health Psychcare Servs., Inc.
6 P.3d 669 (California Supreme Court, 2000)
Carey Brennan v. Opus Bank
796 F.3d 1125 (Ninth Circuit, 2015)
Phillip Roszak v. U.S. Foodservice Inc
628 F. App'x 513 (Ninth Circuit, 2016)
Kevin Ziober v. Blb Resources, Inc.
839 F.3d 814 (Ninth Circuit, 2016)
Abraham Bielski v. Coinbase, Inc.
87 F.4th 1003 (Ninth Circuit, 2023)