Fox v. Fifth West, Inc.

454 P.2d 612, 153 Mont. 95, 1969 Mont. LEXIS 404
CourtMontana Supreme Court
DecidedMay 14, 1969
Docket11521
StatusPublished
Cited by9 cases

This text of 454 P.2d 612 (Fox v. Fifth West, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fox v. Fifth West, Inc., 454 P.2d 612, 153 Mont. 95, 1969 Mont. LEXIS 404 (Mo. 1969).

Opinions

MR. JUSTICE JOHN C. HARRISON

delivered the Opinion of the Court.

Appeal from the district court of Lincoln County. George H. Fox, plaintiff-respondent, instituted this action against Fifth West Inc., a Washington corporation, alleging breach of a valid [97]*97oral contract for employment. The cause was tried by a jury and a verdict was rendered in favor of the plaintiff-respondent in the amount of $6,037.50 ($5,400 wages; $350 expenses; $278.50 hauling a trailer). From this judgment the defendant-appellant employer appeals.

The appellant successfully bid a government construction contract for the sum of $1,044,500 to construct a resident engineers’ and visitors’ facility on a mountainside overlooking the Libby Dam near Libby, Montana. The contract required that the job was to begin in August 1966 and was to be completed in 360 days. This was the appellant’s first work in Montana.

The respondent is an experienced construction man with well over 30 years of experience. He had considerable foreman-superintendent experience on large construction projects and had built a number of homes in the Billings area. Much of his experience involved working with concrete and reinforcing steel.

In August 1966 he was looking for work and saw in the local paper the announcement that the appellant was the low bidder on the aforementioned work at the Libby Dam. He called the appellant’s home office in Seattle and at the request of appellant sent in a resume of his background and work experience. Within a week or 10 days he received a call from Mr. Hedreen, president of appellant corporation, and according to the respondent he told Mr. Hedreen he wanted $200 per week and expenses. He testified that the $200 was agreed upon and that the expense item could be decided upon when he got to Libby. The respondent then went immediately to Libby and the next morning early he met with Mr. Hedreen when the salary was reaffirmed and a $50 per month living allowance was arranged. This $50 was paid once though appellant Hedreen denied any expense arrangement with respondent. The respondent also testified that on the basis of conversation he had with Hedreen he had his wife purchase a trailer house in Billings and Hedreen agreed to pay for the hauling from Billings to Libby (1150 miles at [98]*98.50 per mile=$575). This agreement also was denied by Hedreen.

Respondent worked 7 weeks as a carpenter foreman and was then fired. The appellant contends he had respondent fired due to his inability to get along with his crew and due to mistakes made in setting certain footings. "The respondent testified that he was fired because after telling his supervisor Calhoun that half the steel rebars had been left out of a concrete retaining wall that measured 189 feet in length and varied from 16 feet to 23 feet high, and being told to mind his own business, that he had reported the omission to the inspector for the Army Corps of Engineers. This conversation with the inspector was verified at the trial. The appellant acknowledged the omission in the wall, some 8 tons, and admitted that when the omission was disclosed he talked with Calhoun, Jack Mack, a supervisor, and respondent about what should be done with the remaining steel. The respondent’s version of the above incident was that Hedreen mentioned the possibility of burying the steel and this was not denied. However, appellant’s president, Hedreen, contends that he had discovered the omission, not respondent, and when the Army inspector brought it to his attention he rebuilt ■the wall and put in the required steel.

Though the appellant set forth some ten issues for consideration, each of which has been given careful consideration, we find that a number are interconnected and we therefore will consider them as follows:

Concerning the first issue the appellant made a motion (prior to trial) to limit the argument with reference to the omission of the steel from the building and the court had ordered that no reference to such omission or alleged omission should be made without the laying of a sufficient evidentiary basis for the admission of evidence concerning such omission. Despite this preliminary order of the court the respondent’s counsel in his opening statement said: ‘ ‘ Our evidence will show by Mr. Fox that he felt that one of the retaining walls was not ade[99]*99quately reinforced by steel rebars. He complained about this to Mr. Calhoun; his complaints were ignored; finally they had a meeting about this and Mr. Fox will testify that Mr. Hedreen suggested burying some steel rebars * * Appellant’s counsel objected and moved for a mistrial, and the court sustained his objection but denied a mistrial. We find no error in the court’s ruling at this early stage of the trial and note later that the respondent as well as appellant did submit evidence concerning the incident to the jury for their consideration. In addition we note that the court’s pre-trial order restricting counsel on an evidentiary point that went to the issue of the entire case was itself error.

Concerning the second issue, the defense of the statute of frauds, we find no error. It must be noted that the respondent was hired by the appellant almost immediately after the contract was given the appellant and by Hedreen’s own admission the original contract was for 360 days. The fact that appellant’s contract was amended later does not affect respondent’s rights. Too, one reason for the extension was that the wall had to be rebuilt which most certainly was not contemplated in the original contract. See Awberry v. Schmidt, 65 Mont. 265, 211 P. 346; Miles v. Miles, 76 Mont. 375, 380, 247 P. 328; 49 Am.Jur. Sec. 51, p. 409.

Also, the respondent’s part performance of the contract removes the case from the statute of frauds defense. Cobban v. Hecklen, 27 Mont. 245, 70 P. 805; Kettlekamp v. Watkins, 70 Mont. 391, 225 P. 1003; 49 Am.Jur. Sec. 421, pp. 725-726.

The appellant takes issue over the admission of evidence of statements made by the appellant’s president relative to hiding and burying the rebar steel. We find no error, for this admission against interest goes to the very heart of the matter. Here we have an experienced construction man hired for a supervisory spot in the appellant’s construction firm who was fired early in the job history and just after bringing to the attention of a government inspector the failure of the appellant to prop[100]*100erly reinforce its concrete with steel. None was given here that satisfied either the statutory requirements — or the jury.

Concerning the appellant’s fourth issue — the admission of an unsigned, unauthenticated, incomplete listing on a sheet of paper and contending that it had to do with the appellant’s hiring practices was error. Appellant properly objected to its admission, however, we do find such admission was harmless error for it neither proved or disproved any issue in the cause.

We find too that the court erred in not allowing the appellant to use the original complaint to cross-examine the respondent on certain admissions of the respondent. The trial court took the position that because of the pre-trial order the allegations of the complaint had been superseded and the complaint was no longer relevant. Clearly it was in error for it has been this Court’s position since Johnson v. Butte & Superior Copper Co., 41 Mont. 158, 165, 166, 108 P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gatzke v. Christian (In Re Gatzke)
365 B.R. 138 (D. Montana, 2007)
Rollins v. Blair
767 P.2d 328 (Montana Supreme Court, 1989)
Easterday v. Canty
712 P.2d 1305 (Montana Supreme Court, 1986)
Rosecrans v. Intermountain Soap & Chemical Co.
605 P.2d 963 (Idaho Supreme Court, 1980)
Brown v. North American Manufacturing Co.
576 P.2d 711 (Montana Supreme Court, 1978)
Brothers v. Town of Virginia City
558 P.2d 464 (Montana Supreme Court, 1976)
Strong v. Williams
460 P.2d 90 (Montana Supreme Court, 1969)
Fox v. Fifth West, Inc.
454 P.2d 612 (Montana Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
454 P.2d 612, 153 Mont. 95, 1969 Mont. LEXIS 404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fox-v-fifth-west-inc-mont-1969.