Brothers v. Town of Virginia City

558 P.2d 464, 171 Mont. 352, 1976 Mont. LEXIS 550
CourtMontana Supreme Court
DecidedDecember 28, 1976
Docket13283
StatusPublished
Cited by19 cases

This text of 558 P.2d 464 (Brothers v. Town of Virginia City) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brothers v. Town of Virginia City, 558 P.2d 464, 171 Mont. 352, 1976 Mont. LEXIS 550 (Mo. 1976).

Opinion

*354 MR. JUSTICE DALY

delivered the opinion of the Court.

This is an appeal from a final judgment following a jury verdict rendered in favor of plaintiff Bill Brothers in the district court, Madison County.

On July 21, 1972, Bill Brothers Construction entered into a contract with the Town of Virginia City, Montana, whereby the contractor agreed to construct a sanitary sewer system and lagoon for the contract price of $139,681.50. Virginia City subsequently requested changes in the sewer system which reduced the contract price to $138,629.20. These changes were approved by the contractor and Virginia City’s supervising engineer.

The contractor commenced performance of the contract in accordance with a “notice to proceed” and continued to perform under the contract except during those periods when inclement weather caused the suspension of work. The contractor received periodic payments under the contract as the construction progressed until September 5, 1973, when the contractor gave notice performance of the contract was complete.

In the district court the contractor contended the following sums remained due, owing and unpaid under the original contract or subsequent contracts:

Count One — $17,197.15, together with interest, as the final payment due under the original construction contract.

Count Two — $3,829.55, together with interest, as payment for work requested and authorized by Virginia City in the repair of wash-out conditions caused by a ruptured water line.

Count Three — $468.60, together with interest, as payment for part performance on a contract for extra work performed in connection with the lagoon.

At the conclusion of the presentation of evidence, the district court granted plaintiff’s motion for directed verdict on Count Two, ruling that defendant was indebted to plaintiff but leaving the amount of indebtedness to the jury. The jury returned verdicts for the plaintiff and in the sums prayed for by the plaintiff *355 with the exception of Count Three for which the jury returned a verdict in the amount of $400.

Defendant presents five issues for review:

1. Whether the district court erred in granting.plaintiff’s motion in limine which restricted defendant from questioning plaintiff regarding, litigation between plaintiff and defendant’s supervising engineer?

2. Whether the district court erred in not granting defendant’s motion for directed verdict on Counts One and Three?

3. Whether the district court erred in not granting defendant’s motion for a new trial on Counts One, Two and Three?

4. Whether the district court erred in not granting defendant’s motion for judgment notwithstanding the verdict on Count Three?

5. Whether the district court erred in giving Instruction No. 10 and refusing to give defendant’s proposed instructions No. 2, 10 and 11?

Defendant’s first allegation of error concerns the district court’s granting of plaintiff’s motion in limine. Defendant contends that evidence of pending litigation between plaintiff and defendant’s engineer was relevant and material in proving the bad faith of the engineer and thus wrongly withheld from the jury. Defendant concludes that plaintiff would not have recovered had defendant been allowed to establish the engineer’s bad faith in issuing extensions of time for performance and in his determination that the contract had been completed.

We believe defendant has incorrectly interpreted the law of Montana regarding the effect of decisions of a supervising engineer. Clifton, Applegate & Toole v. Big Lake Drain District No. 1, 82 Mont. 312, 327, 330, 267 P. 207, 211, 212, correctly states the Montana rule:

“The law appears to be definitely settled that: ‘the decision, estimate, or certificate of an architect, engineer, or superintendent, in approving or disapproving the work as a performance *356 of a contract, or in passing on questions relating thereto, is, in the absence of fraud, bad faith, or mistake, conclusive and binding on the parties, where the contract, either in express terms provides that it shall be final and conclusive, or in plain language shows that it was the intention of the parties that the person to whom the question is submitted should be the arbiter thereof.’
* s}s * * sfc *
“An honest mistake in measurement or in judgment is not a ground for impeachment of the engineer’s estimates. It is not sufficient to say that the engineer came to a conclusion of fact erroneously. Although the court might have made a different estimate, it may not substitute its judgment for that of the engineer.”

See: Polley’s Lumber Co. v. United States, 9 Cir., 115 F.2d 751; United Pacific Insurance Co. v. County of Flathead, 9 Cir., 499 F.2d 1235.

Absent a showing of fraud, the decisions of the supervising engineer are binding upon the contracting parties. We fail to perceive how the introduction of evidence regarding litigation between plaintiff and the supervising engineer would establish such fraud. The issue to be resolved was whether or not plaintiff could recover from defendant under a construction contract. Evidence of pending claims and counterclaims between plaintiff and defendant’s supervising engineer were not material in resolving such a question of law and fact.

This Court reviewed the applicability of the motion in limine in Wallin v. Kenyon Estate, 164 Mont. 160, 164, 519 P.2d 1236, 1238:

“Authority for the granting of a motion in limine rests in the inherent power of the court to admit or exclude evidence and to take such precautions as are necessary to afford a fair trial for all parties. * * *
“The decision of the district court in excluding questions at trial of the proponent’s alleged practice of law was conducive to *357 the prevention of irrelevant, immaterial and prejudicial evidence being heard by the jury. The purpose, and effect, of the court’s granting the motion in limine was to0 prevent that which occurred in the case of In the Matter of the Estate of Powers, 163 Mont. 67, 515 P.2d 368, where many diverse issues were allowed ‘* * * to divert the trial court from the single issue * * * ’ ”

The advantages of the motion in limine are many. It speeds, simplifies and purifies the process of obtaining just verdicts by excluding prejudicial evidence which lacks probative value.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Giambra v. Kelsey
2007 MT 158 (Montana Supreme Court, 2007)
Hunt v. K-Mart Corp.
1999 MT 125 (Montana Supreme Court, 1999)
Barrett v. Asarco Inc.
799 P.2d 1078 (Montana Supreme Court, 1990)
Finstad v. Montana Power Co.
785 P.2d 1372 (Montana Supreme Court, 1990)
Krueger v. General Motors Corp.
783 P.2d 1340 (Montana Supreme Court, 1989)
Hanzel v. Marler
774 P.2d 426 (Montana Supreme Court, 1989)
Feller v. Fox
772 P.2d 842 (Montana Supreme Court, 1989)
Gunlock v. Western Equipment Co.
710 P.2d 714 (Montana Supreme Court, 1985)
Wilhelm v. City of Great Falls
685 P.2d 350 (Montana Supreme Court, 1984)
Kuhnke v. Fisher
683 P.2d 916 (Montana Supreme Court, 1984)
Rock Springs Corp. v. Pierre
615 P.2d 206 (Montana Supreme Court, 1980)
Wolfe v. Schulz Refrigeration
614 P.2d 1015 (Montana Supreme Court, 1979)
Lyndes v. Scofield
589 P.2d 1000 (Montana Supreme Court, 1979)
Yerkich v. Opsta
577 P.2d 857 (Montana Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
558 P.2d 464, 171 Mont. 352, 1976 Mont. LEXIS 550, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brothers-v-town-of-virginia-city-mont-1976.