Fort Sumter Tours, Inc. v. Andrus

564 F.2d 1119, 24 Cont. Cas. Fed. 81,817
Court of Appeals for the Fourth Circuit·Decided November 3, 1977·No. No. 77-8308·Published·Cited by 42 cases

Opinion

WINTER, Circuit Judge:

Gray Line Water Tours, Inc. (Gray Line) sought a stay pending appeal of the district court’s preliminary injunction preventing the Secretary of the Interior and his designates from entering into any contract to provide boat transportation to and from Fort Sumter National Monument until further order of court. The litigation had been instituted by Fort Sumter Tours, Inc. (Fort Sumter) which sued the Secretary to prevent him from entering into a concession contract in derogation of Fort Sumter’s statutory right of preference and to require the Secretary to enter into a contract with Fort Sumter. Gray Line had intervened, and it appeals. The Secretary did not appeal. By agreement of the parties, we decide the appeal and not merely the granting or withholding of a stay pending appeal, and we affirm.

I.

Gray Line is engaged in conducting tours and excursions on the waters of Charleston Harbor. Prior to 1968, it provided boat transportation between Charleston and the Fort Sumter National Monument, an island in the Charleston Harbor under the jurisdiction of the National Park Service (Service), pursuant to a concession contract with Service. Since January 1, 1968, this boat-transportation concession has been held by Fort Sumter. The existing contract between Fort Sumter and Service is due to expire December 31, 1977. On or about July 23, 1976, Service determined to negotiate a new ten-year concession contract, commencing January 1, 1978.

The Secretary, through the National Park Service, is authorized by 16 U.S.C. § 20a to enter into concession contracts with private corporations for the provision and operation of facilities and services necessary to the administration of the National Park System, of which Fort Sumter National Monument is a part. At the heart of the present controversy is 16 U.S.C. § 20d, the text of which is set forth in the margin.1 In essence, § 20d grants preferential renewal rights to those existing'concessioners who have performed their obligations under pri- or contracts in a manner satisfactory to the Secretary. It is conceded by all parties to this litigation that Fort Sumter has performed its obligations during the last ten years to the satisfaction of the Secretary and is, therefore, entitled to preferential rights in the negotiation of the new contract. The dispute concerns the meaning and scope of this preferential right and [1122]*1122whether, in the particular case, Service gave Fort Sumter the full measure of its statutory right.

The dispute arose in the following manner: On July 23, 1976, the Regional Director of Service was authorized to negotiate a new concession contract for the provision of boat transportation to and from Fort Sumter. Consistent with existing practice, the Regional Director and Fort Sumter negotiated a document referred to as the “Fact Sheet,” at once both the bid specifications and Fort Sumter’s preliminary working proposal. Pursuant to the requirements of § 20d, Service published notice on December 9, 1976, in the Federal Register, advising the public that Fort Sumter had performed the existing contract in a satisfactory manner, that it was Service’s current intention to negotiate a new contract with Fort Sumter, but that it would consider and evaluate any other proposals from interested parties submitted within thirty days. In response to this notice, Gray Line submitted its proposal on January 4, 1977.

On March 1, 1977, the Regional Director informed both parties that Fort Sumter’s proposal was clearly superior and that the new concession contract would be negotiated with Fort Sumter. Following informal protests by Gray Line, the Office of Audit and Investigation in the Interior Department reviewed the documentation supporting the Regional Director’s decision and concluded, in a report dated May 19, 1977, that the decision to enter into negotiations with Fort Sumter should be rescinded and the process begun anew.2

On August 9, 1977, the Regional Director advised Fort Sumter of Service’s intention to negotiate the new contract with Fort Sumter, conditioned, however, on Fort Sumter’s agreeing to modify its proposal to meet certain items in the Gray Line proposal which Service considered clearly superi- or.3 By letter dated August 12, the Regional Director further advised Fort Sumter that it had until the close of business on August 26 to make its decision. Fort Sumter was further advised that its failure to accept the additional terms would operate as an automatic waiver of Fort Sumter’s preferential negotiating rights and would result in Service’s entering into negotiations with Gray Line.

On August 24, 1977, two days before the deadline set by Service, Fort Sumter filed this suit against the Secretary, complaining that Service’s conditional offer to negotiate and accompanying ultimatum constituted an arbitrary and capricious denial of Fort Sumter’s statutory preferential negotiating rights. On the same day, Fort Sumter advised Service that it was accepting Service’s conditional offer to negotiate and would meet the specified additional terms but would do so only if the instant litigation proved unsuccessful. By letter dated September 8, Service construed this conditional acceptance as a rejection and a waiver of preferential negotiating rights.

[1123]*1123II.

The district court exercised jurisdiction pursuant to 28 U.S.C. § 1331(a).4 While conceding that this statute grants the federal court general equity jurisdiction in a case brought by an aggrieved person against a federal administrative agency, Gray Line contends that Service’s decision to deny Fort Sumter its statutory preference and to negotiate exclusively with Gray Line is not “final agency action” within the meaning of the Administrative Procedure Act § 10(c), 5 U.S.C. § 704,5 and, therefore, is not ripe for judicial review.

While it is generally true that judicial^ review awaits the issuance of a formal administrative order enforceable against a person or class of persons, such action is not an absolute prerequisite to judicial review. Abbott Laboratories v. Gardner, 387 U.S. 136, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967); Medical Committee for Human Rights v. Securities and Exchange Commission, 139 U.S.App.D.C. 226, 432 F.2d 659 (1970), vacated as moot, 404 U.S. 403, 92 S.Ct. 577, 30 L.Ed.2d 560 (1972). In Abbott Laboratories, the Supreme Court admonished lower federal courts to take a functional approach in resolving ripeness questions. The goals are: “to prevent the courts . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Fort Sumter Tours, Inc. v. Andrus, 564 F.2d 1119, 24 Cont. Cas. Fed. 81,817 (4th Cir. 1977).

564 F.2d 1119 (Fort Sumter Tours, Inc. v. Andrus) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Long Term Care Partners, LLC v. United States
516 F.3d 225 (Fourth Circuit, 2008)
AES Sparrows Point LNG, LLC v. Smith
470 F. Supp. 2d 586 (D. Maryland, 2007)
Miller v. Brown
462 F.3d 312 (Fourth Circuit, 2006)
In Re Tubular Technologies, LLC
348 B.R. 699 (D. South Carolina, 2006)
GTE North Inc. v. McCarty
978 F. Supp. 827 (N.D. Indiana, 1997)
Eilertson v. United States
211 B.R. 526 (D. South Carolina, 1997)
Arch Mineral Corporation v. Babbitt
104 F.3d 660 (Fourth Circuit, 1997)
Clark Pacific v. Krump Construction, Inc.
942 F. Supp. 1324 (D. Nevada, 1996)
Waters v. LAND RESOURCES CONS. COM'N
467 S.E.2d 913 (Supreme Court of South Carolina, 1996)
Robishaw Engineering, Inc. v. United States
891 F. Supp. 1134 (E.D. Virginia, 1995)
Lewis v. Lujan
826 F. Supp. 1302 (D. Wyoming, 1992)
Hamilton Stores, Inc. v. Hodel
925 F.2d 1272 (Tenth Circuit, 1991)
Darr v. Massinga
838 F.2d 118 (Fourth Circuit, 1988)
L.J. ex rel. Darr v. Massinga
838 F.2d 118 (Fourth Circuit, 1988)
Burlington Industries, Inc. v. Edelman
666 F. Supp. 799 (M.D. North Carolina, 1987)
Barnett v. District of Columbia Department of Employment Services
491 A.2d 1156 (District of Columbia Court of Appeals, 1985)
Current-Jacks Fork Canoe Rental Ass'n v. Clark
603 F. Supp. 421 (E.D. Missouri, 1985)
Johnson v. Halifax County
594 F. Supp. 161 (E.D. North Carolina, 1984)