Forristal v. City of Milwaukee

15 N.W. 769, 57 Wis. 628, 1883 Wisc. LEXIS 337
CourtWisconsin Supreme Court
DecidedMay 31, 1883
StatusPublished

This text of 15 N.W. 769 (Forristal v. City of Milwaukee) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forristal v. City of Milwaukee, 15 N.W. 769, 57 Wis. 628, 1883 Wisc. LEXIS 337 (Wis. 1883).

Opinion

Cole, C. J.

The charter of the defendant contains this provision: The board of public works “ shall reserve in every [631]*631contract the right to determine finally all performance of such contract, or doing of the work specified therein; and the right, in case of the improper or imperfect performance thereof, to suspend such work at any time, or to order the entire reconstruction of the same if improperly done, or to relet the same to some other competent party; and also the right, in case such work shall not be prosecuted with such diligence and with such number of men as to insure its completion within the time limited by the contract, to suspend such work and relet the same to some other competent party, or employ men and secure material for the completion of the same, and charge the cost thereof to the contractor. And power is hereby given to the said board to adjust and determine all questions as to the amount earned under any contract, by the contractor or contractors, according to the true intent and meaning of the contract; cmd such adjustment and determination l>y said hoard shall he final between the parties and binding upon them? Sec. 20, subch. 5, ch. 184, Laws of 1874. The charter further enacts that every contract with the city shall be made expressly subject to the powers given the board in the above section; and the sprinkling contract entered into by plaintiff contained the provision ipsissimis verbis. It will be observed that by the charter, and by the contract itself, the board of public works were made the arbiters to adjust and determine all questions as to the amount earned by a contractor under his contract; and such adjustment and determination were made final and binding upon the parties. If this provision of the charter and of the contract is sustained, it is evident there can be no recovery, because the evidence conclusively shows that the board did determine the amount which the plaintiff had earned under his contract, and the officers of the city had issued an order for the same.

The learned counsel for the plaintiff did-not insist that the provision which made the board arbiters to determine the [632]*632amount earned under a contract with the city was invalid as being contrary to public policy, or because it was in violation of any sound legal principle. It was doubtless entirely competent for the legislature to vest such a power in the board, and the provision is a wholesome one in many respects. It tends to secure the prompt performance of contracts which may affect the convenience, good order, and welfare of the citizens, and will often tend to prevent expensive litigation. The fact that the members of the board are officers of the city constitutes no valid objection to the provision. Of course, contractors consent that the board shall determine the amount which they have earned, and shall decide other questions of law and fact arising upon their contracts with the city. But where the board acts in good faith, is guilty of no fraud or misconduct, and makes no mistake, there is no reason why its determination and award should not bind the parties as in ordinary cases of arbitration. The parties expressly agree to submit matters of difference to that tribunal for decision, and, having done so, there is no hardship in holding them bound by the result. For, as observed by the counsel for the city, there is no more objection to a law requiring the board, whose duty it is to superintend the work, to act as arbiters in matters arising under a city contract, than there is to allowing an owner of a building, or a railroad corporation, to stipulate that Ms architect, or its engineer, shall conclusively decide disputes with contractors arising upon contracts. In this last class of cases the award of the umpire chosen by the parties to decide the matters of difference, when fairly made, has been held binding. Hudson v. McCartney, 33 Wis., 331; Tetz v. Butterfield, 54 Wis., 242; Smith v. Brady, 17 N. Y., 173; Boston Water Power Co. v. Gray, 6 Met., 131; Herrick v. Belknap’s Estate, 27 Vt., 673. In this case the legislature may have deemed.it necessary to vest such an umpirage in the board, and as the plaintiff expressly agreed in his con[633]*633tract to make the determination of the board as to the amount earned on his contract final, he must abide by it. He can no more set it aside, unless he offers something to impeach its correctness or good faith, than he could the award of an arbitrator by whose decision of the controversy he had agreed to abide.

But the plaintiff’s counsel says it did not appear from the evidence offered on the trial that the board ever determined, in a proper way, the amount which the plaintiff had earned on his contract. This position is not sustained by the record. Exhibit C, offered . in evidence, showed that the board had made an equitable adjustment of the amount due the plaintiff on his contract. It is true, this exhibit is not very formal, and does not set forth all matters which Blodgett and Cas-grain say the board considered in making its award or decision. But it clearly shows that the board made an equitable adjustment of what was due the plaintiff on his contract, in view; of the fact that he failed to perform in every particular. The above witnesses, who were members of the board in 1881, clearly explain just how that body reached the conclusion it did in making its final estimate or allowance. The record itself which was made does not show all these matters, but it is sufficiently full to answer the requirements of the law. It was suggested on the argument, by plaintiff’s counsel, that the board only had the power to adjust and determine all questions as to the amount earned under a contract where the contract was terminated and the work was relet to other contractors. But this construction of the provision is clearly wrong. The language used gives the board power to adjust, etc., all questions under any contract with the city. The words used are comprehensive, and vest the power in the board to adjust in case of all contracts. It was further said that the trial court erred in allowing, against objection, oral testimony of the proceedings of the board. But, as we understand the bill of exceptions, the records of [634]*634the board were in. fact' introduced in evidence, and were used and referred to by the witnesses in their testimony relative to -the action of the board.

The contract stated that the work was to be done according to the rules and specifications of the board on file in the office of said board. These specifications provided that no allowance would be made for. sprinkling street cross-walks. The intersections of the roadway were to be paid for at the regular contract price per lineal foot. In estimating the lineal feet sprinkled, the board omitted fifteen feet for every sidewalk crossing, allowing nothing for street cross-walks, but only for roadway intersections. This was because the sidewalks on each side of the street are fifteen feet wide. Mr. Blodgett explained to bidders that the object of this rule of measurement was to have the sidewalk spaces between the curb line and the lot line free from water; therefore only the intersections of the streets proper between the curbs would be estimated. The county court charged that this method adopted by the board of - estimating what was included in the street crossings, with regard to lineal feet which the plaintiff was required to sprinkle, was correct. This charge was excepted to by plaintiff’s counsel, but we think it was in accordance with the terms of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. . Brady
17 N.Y. 173 (New York Court of Appeals, 1858)
Herrick v. Estate of Belknap
27 Vt. 673 (Supreme Court of Vermont, 1854)
Hudson v. McCartney
33 Wis. 331 (Wisconsin Supreme Court, 1873)
Tetz v. Butterfield
11 N.W. 531 (Wisconsin Supreme Court, 1882)

Cite This Page — Counsel Stack

Bluebook (online)
15 N.W. 769, 57 Wis. 628, 1883 Wisc. LEXIS 337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forristal-v-city-of-milwaukee-wis-1883.