Forest City Grant Liberty Associates v. Genro II, Inc.

652 A.2d 948, 438 Pa. Super. 553, 1995 Pa. Super. LEXIS 22
CourtSuperior Court of Pennsylvania
DecidedJanuary 12, 1995
StatusPublished
Cited by27 cases

This text of 652 A.2d 948 (Forest City Grant Liberty Associates v. Genro II, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forest City Grant Liberty Associates v. Genro II, Inc., 652 A.2d 948, 438 Pa. Super. 553, 1995 Pa. Super. LEXIS 22 (Pa. Ct. App. 1995).

Opinion

WIEAND, Judge:

In this dispute over an insurer’s duty to indemnify, the principal issue makes it necessary that we construe a clause in the policy which requires the insured to “cooperate” with the insurer.

When the owners of the Liberty Center discovered defects in the roofing on their several buildings, 1 they commenced an action against Carlisle SynTec Systems, which had designed the several roofs, and General Roofing Company, which had installed the same. Joined as an additional defendant was RMax, Inc., which had supplied foam insulation for the project. It was alleged that the facer sheet on each side of the foam insulation had separated from insulation, a process known as delamination. Alliance Insurance Group was the liability carrier for RMax. At trial, RMax was represented by Terry Cavanaugh, Esquire.

During trial, extended negotiations resulted in a settlement., on February 20, 1991. Based on a report by Robert McNeil, an employee of Carlisle SynTec Systems, it was agreed that at least 27,000 square feet of roofing insulation had delaminated, resulting in damaged roofing. This area, it was agreed, should be repaired for $155,000. Because delamination, once begun, tends to migrate, it was also agreed that if repairs to the roof were found to be necessary in adjacent areas, they would be made at a cost of $7 per square foot. Finally, it was *557 agreed that additional areas, not adjacent to identified areas but which were later discovered to be defective, would only be repaired if RMax agreed that delamination had occurred because of a defect in its product. Before these additional, non-adjacent areas could be repaired, however, the parties were to submit an amendment of the settlement agreement to Alliance. Universal Roofing Company was selected to perform the repairs. Both Alliance and RMax consented to the terms of the settlement.

After the settlement agreement had been approved, McNeil revisited the Liberty Center Complex in May, 1991, and determined that at least 14,085 additional square feet of insulation had delaminated and needed to be repaired. McNeil attributed this increased square footage to the migratory nature of delamination. As a result, McNeil amended his initial report and drawings. A copy of the amended report was submitted to RMax and Alliance.

Prior to the commencement of repairs, Cavanaugh contacted Alliance and suggested that Alliance hire an expert to monitor the work so as to prevent any overreaching on the part of Universal. Alliance rejected this suggestion and said that it would rely upon RMax to inspect the project from time to time. Although RMax agreed to visit the work site on occasion, it did not agree to monitor or supervise the project.

In August, 1991, Universal began work on the hotel roof. It repaired the hotel roof and the roof of the podium in areas which had been identified by McNeil and also in areas adjacent thereto. It also replaced the roof in some areas which had not been damaged by delamination. By the time it completed its work, almost the entire hotel and podium roofs had been replaced, and the cost had exceeded greatly the estimates contained in the McNeil report, which had formed the basis for the agreed settlement.

During the repair process Universal sent periodic invoices to Alliance. Although these invoices did not distinguish between areas identified by the McNeil reports and other areas in which repair work had been done, Alliance paid each invoice *558 without question or objection. In November, 1991, after paying $232,100.93, Alliance became aware that it had paid for roof repairs in areas not contemplated by the McNeil reports.

In December, 1991, McNeil visited the Liberty Center complex for a third time and discovered delamination of an additional 27,964 square feet on the office tower roofs. It was estimated that this additional damage would cost $195,748 to repair. On February 4, 1992, Alliance informed RMax that it would not indemnify it for this work.

RMax agreed with McNeil that the newest delamination had been caused by migration of the original damage and stipulated that it should be repaired pursuant to the settlement agreement. Therefore, after Alliance had refused further indemnification, RMax paid $160,062 to Universal for additional repairs. While performing the repair work, Universal replaced 4,350 square feet of undamaged roof at a cost of $37,750. Because RMax had not assigned a representative to supervise the project, it was unaware of Universal’s continued overreaching.

In a proceeding for declaratory judgment, RMax contended that Alliance was liable for all costs of making roof repairs, as well as counsel fees. Alliance contended, inter alia, that it was excused from liability because of RMax’s failure to cooperate by having its personnel oversee the repair work done by Universal. The trial court held that Alliance was liable for all repairs made pursuant to the settlement agreement and for counsel fees in the amount of $38,908. It was not liable, however, for unnecessary repairs of $37,750 made to the roofs of the office tower, which RMax had already paid and to which it had improperly consented. Both parties appealed.

Generally, where the terms of an insurance contract are ambiguous, they should be construed liberally in favor of the insured and strictly against the insurer. Miller v. Prudential Ins. Co. of Amer., 239 Pa.Super. 467, 472, 362 A.2d 1017, 1020 (1976). Where the policy language is unambiguous, however, words are given their plain and ordinary meaning. *559 Techalloy Co., Inc. v. Reliance Ins. Co., 338 Pa.Super. 1, 7, 487 A.2d 820, 823 (1984).

RMax’s duty to cooperate, as set forth in its policy with Alliance, was as follows:

(4) Insured’s Duties in the Event of Occurrence, Claim or Suit:
(c) The insured shall cooperate with the company and, upon the company’s request, assist in making settlements, in the conduct of suits and in enforcing any right of contribution or indemnity against any person or organization who may be liable to the insured because of injury or damage with respect to which insurance is afforded under this policy; and the insured shall attend hearings and trials and assist in securing and giving evidence and obtaining the attendance of witnesses. The insured shall not, except at his own cost, voluntarily make any payment, assume any obligation or incur any expense other than for first aid to others at the time of the accident.

The purpose of a cooperation clause in an insurance contract is to protect the insurer’s interest and to prevent collusion between the insured and the injured party. 8 Appleman, Insurance Law and Practice § 4741. Although a breach of a duty to cooperate will relieve the insurer from liability under the policy, a failure to cooperate must be substantial and will only serve as a defense where the insurer has suffered prejudice because of the breach. Id. at § 4773.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marion, D. v. Bryn Mawr Trust Co.
2021 Pa. Super. 18 (Superior Court of Pennsylvania, 2021)
Mader, S. v. Duquesne Light
199 A.3d 1258 (Superior Court of Pennsylvania, 2018)
John Duda v. Standard Insurance Co
649 F. App'x 230 (Third Circuit, 2016)
Mt. McKinley Insurance v. Pittsburgh Corning Corp.
518 B.R. 307 (W.D. Pennsylvania, 2014)
Goddard v. State Farm Mutual Automobile Insurance
992 F. Supp. 2d 473 (E.D. Pennsylvania, 2014)
Brown v. Grass
544 F. App'x 81 (Third Circuit, 2013)
State Farm Fire & Casualty Co. v. Steffen
948 F. Supp. 2d 434 (E.D. Pennsylvania, 2013)
Michael Verdetto v. State Farm Fire & Casualty Co
510 F. App'x 209 (Third Circuit, 2013)
SCW West LLC v. Westport Insurance
856 F. Supp. 2d 514 (E.D. New York, 2012)
Williams v. Allstate Insurance
595 F. Supp. 2d 532 (E.D. Pennsylvania, 2009)
Leonard v. Sunset Mortgage
Tenth Circuit, 2007
Graziani v. Randolph
887 A.2d 1244 (Superior Court of Pennsylvania, 2005)
Atlantic States Insurance v. Hunt
77 Pa. D. & C.4th 417 (Philadelphia County Court of Common Pleas, 2005)
Utilities, Inc. v. Blue Mountain Lake Associates, L.P.
121 F. App'x 947 (Third Circuit, 2005)
Upright Material Handling Inc. v. Ohio Casualty Group
74 Pa. D. & C.4th 305 (Lackawanna County Court of Common Pleas, 2005)
Resource America Inc. v. Certain Underwriting Members of Lloyd's Subscribing to Policy No.
69 Pa. D. & C.4th 496 (Philadelphia County Court of Common Pleas, 2004)
Ania v. Allstate Insurance
161 F. Supp. 2d 424 (E.D. Pennsylvania, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
652 A.2d 948, 438 Pa. Super. 553, 1995 Pa. Super. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forest-city-grant-liberty-associates-v-genro-ii-inc-pasuperct-1995.