Dox Planks v. Ohio Farmers Insurance

621 A.2d 132, 423 Pa. Super. 311, 1993 Pa. Super. LEXIS 624
CourtSuperior Court of Pennsylvania
DecidedFebruary 17, 1993
Docket00631
StatusPublished
Cited by6 cases

This text of 621 A.2d 132 (Dox Planks v. Ohio Farmers Insurance) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dox Planks v. Ohio Farmers Insurance, 621 A.2d 132, 423 Pa. Super. 311, 1993 Pa. Super. LEXIS 624 (Pa. Ct. App. 1993).

Opinion

ROWLEY, President Judge:

Ohio Farmers Insurance Company (hereinafter “appellant Ohio”) and Tri-State Asphalt Corporation (hereinafter “TriState”) appeal from the judgment rendered against them, and in favor of Dox Planks (hereinafter “appellee”), in this breach of contract and surety bond action brought by appellee Dox Planks to recover for concrete road barriers it had supplied to appellant Tri-State in connection with a Pennsylvania Department of Transportation highway construction contract which appellant Tri-State had been awarded. Appellants contend that the trial court erred in the following respects: (1) by making its factual finding that a sale rather than a lease of the concrete barriers had occurred between the parties, and in making its corresponding legal conclusion that the concrete barricades in question were “materials substantially used” rather than “capital equipment,” within the meaning of the instant construction bond, (2) by failing to take into consideration an alleged duty on the part of appellee to mitigate its damage, (3) by finding that appellants owe interest to appellee as of October 31, 1989, and (4) by admitting certain exhibits over the objection of defense counsel. Appellee asserts that the trial court’s factual findings, legal conclusions and evidentiary rulings are all well-supported by the record and the law. Following a careful review of both, we affirm.

The factual background of this case is as follows. In preparation for the submission of its bid for a Pennsylvania Department of Transportation (hereinafter “PennDOT”) highway paving contract, appellant Tri-State, by its agent Charles *314 Taylor, contacted appellee Dox Planks, a concrete product supplier, to inquire about the cost of pre-cast concrete barricades to be used on the highway construction project. Mr. John Romani, as owner and chief executive officer of appellee Dox Planks, quoted appellant Tri-State a price of $15.25 per lineal foot for the sale of its pre-cast concrete barrier. Mr. Taylor, who was in charge of handling the bidding on the barrier segment of the project, testified that he had received appellee’s quotation, and that on the night the bids were entered on the project in Harrisburg, PA, he put all the barrier purchase quotations on a spreadsheet which revealed that appellee was the lowest bidder 1 .

When appellant Tri-State was awarded the paving contract by the state, appellee Dox Planks was informed by appellant Tri-States’s estimator, Mr. Taylor, that appellee Dox Planks would be the sub-contractor on the project and that a John McDevitt would be purchasing the barriers directly from the job site. Thereafter, Mr. McDevitt issued purchase order Number 10614, dated August 10, 1989, and purchase order Number 11303, dated October 31,1989, to appellee Dox Planks for the barriers which would be used by appellant Tri-State on its highway paving project. The testimony at trial revealed that Mr. McDevitt had been duly authorized, both by Mr. Taylor, and by the Vice-President of Construction, Mr. George Sipe, to order the materials on behalf of appellant TriState, at the quoted sales price, for this project. The materials were then delivered to appellant Tri-State.

*315 Appellee Dox Planks claims that, in the normal course of business, it mailed invoices for payment to appellant Tri-State and that when payment was not received, Mr. Romani phoned Mr. McDevitt to inquire as to the reason for non-payment 2 . After researching the inquiry, Mr. McDevitt advised Mr. Romani that the checks had been written by the accounting department but remained unsigned due to the unwillingness of appellant Tri-State’s owner, Mr. Straub, to pay the bills. At this point, Mr. Romani claims he had his one and only discussion with Mr. Straub, wherein he was told that “he [Mr. Straub] was not concerned” about the bills and would not be submitting payment thereof to appellee Dox Planks. (Reproduced Record, p. 27a). Whereupon, Mr. Romani informed Mr. Straub that appellee Dox Planks would file a lien against him, the Pennsylvania Department of Transportation, and appellant Ohio for payment. The lien was then filed by appellee.

At the bench trial held in this case, the chief factual issue for the trial court to resolve was whether, from the supplier’s point of view, the concrete barriers were an item reasonably expected to be consumed or substantially consumed in performance of the project. United States for the Use of Sunbelt Pipe v. United States Fidelity and Guaranty Company, 785 F.2d 468 (4th Cir.1986). If they were, under the relevant case law, the supplies were “materials furnished” within the meaning of the bond in question and the Public Work Contractors Bond Law of 1967, 8 P.S. § 195, such that the bond covered the amounts owed by appellant Tri-State to appellee Dox Planks for the barriers. If, under that same law, the barriers could reasonably be expected to be reused on other non-government jobs, appellee Dox Planks could not recover on the bond because the barriers would not be considered “materials furnished,” but rather, would be deemed “capital equipment.”

*316 Following considerable testimony, the trial court found as a fact that the pre-cast concrete barriers supplied to appellant Tri-State by appellee Dox Planks were of such a nature that appellee Dox Planks, as supplier, could reasonably have expected that they would be substantially used up in the project underway inasmuch as they were made specifically according to PennDOT requirements and were indispensable to the prosecution of the project. Commonwealth v. Natural Union Fire Insurance Company, 434 Pa. 235, 252 A.2d 593 (1969). As such, the trial court made the conclusion of law that the barriers were “materials furnished,” under the terms of the bond and therefore, rendered the judgment that appellants Tri-State and Ohio were jointly and severally liable to appellee Dox Planks for $36,662.32, plus interest at the rate of 6% per annum. Appellant’s primary claim of trial court error is that this factual finding, and its corresponding conclusion of law, are against the weight of the evidence.

In addressing these claims, we note initially that:

“findings of a trial judge sitting without a jury carry the same weight as a verdict, and th[e appellate courts] will not disturb those findings on appeal absent an error of law or an abuse of discretion, [citation omitted]. We will respect a trial court’s findings with regard to the credibility and weight of the evidence unless the appellant can show that the [trial] court’s determination was manifestly erroneous, arbitrary, and capricious or flagrantly contrary to the evidence. [citation omitted].”

Ecksel v. Orleans Construction Co., 360 Pa.Super. 119, 133, 519 A.2d 1021, 1026 (1987). Furthermore:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Independent Enterprises v. JD Fields
Superior Court of Pennsylvania, 2015
XTO Energy v. Dominion Field v. Linn Energy
Superior Court of Pennsylvania, 2014
TruServ Corp. v. Morgan's Tool & Supply Co.
39 A.3d 253 (Supreme Court of Pennsylvania, 2012)
Forest City Grant Liberty Associates v. Genro II, Inc.
652 A.2d 948 (Superior Court of Pennsylvania, 1995)
Woodin v. JC Penney Co., Inc.
629 A.2d 974 (Superior Court of Pennsylvania, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
621 A.2d 132, 423 Pa. Super. 311, 1993 Pa. Super. LEXIS 624, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dox-planks-v-ohio-farmers-insurance-pasuperct-1993.