FORESIGHT CONSTRUCTION LLC v. VALLEY RENAISSANCE URBAN RENEWAL ENTITY, LLC (L-0040-21, ESSEX COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided August 22, 2022·No. A-2039-20·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-2039-20

FORESIGHT CONSTRUCTION LLC,

Plaintiff-Appellant,

v.

VALLEY RENAISSANCE URBAN RENEWAL ENTITY, LLC,

Defendant-Respondent.

Argued May 24, 2022 – Decided August 22, 2022 Before Judges Currier and Smith.

On appeal from the Superior Court of New Jersey, Law Division, Essex County, Docket No. L-0040-21.

Martin P. Skolnick argued the cause for appellant (Skolnick Legal Group, PC, attorneys; Martin P.

Skolnick and Scott H. Bernstein, on the briefs).

Karim G. Kaspar argued the cause for respondent (Lowenstein Sandler LLP, attorneys; Karim G. Kaspar and Craig Dashiell, on the brief).

PER CURIAM I.

In 2015, Valley Renaissance Urban Renewal Entity, LLC (VRURE) hired Foresight Construction, LCC (Foresight) as its general contractor to convert an abandoned factory into condominiums. The parties executed a contract whereby VRURE agreed to pay $5,190,000 for Foresight's services. The parties anticipated that project completion time was twelve months. The contract contained other relevant terms language including: a liquidated damages clause for delay; an arbitration clause to settle any disputes stemming from the project; and language awarding attorney's fees to the prevailing party in a dispute. The agreement contained additional language designating the Federal Arbitration Act (FAA) as the law governing the proceedings. Procedurally, the arbitration was to be conducted using the American Arbitration Association's (AAA) Construction Industry Arbitration rules.

Project delays occurred, but by June 2017, VRURE had paid Foresight $5,115,552.78 for construction services rendered. The parties disputed the cause of the delays and who would be responsible for paying related damages. Eventually, VRURE terminated Foresight as general contractor, due to its failure to complete the work.

A-2039-20

In August 2018, Foresight filed suit against VRURE seeking an additional $1.2 million in payments. VRURE moved to compel arbitration, and its motion was granted by the court. Foresight then initiated arbitration proceedings. At arbitration, VRURE counterclaimed against Foresight, seeking damages for Foresight's alleged failure to finish the job. The parties mutually selected Harry E. McLellan, III (McLellan) as their arbitrator. Prior to the hearing, McLellan convened the parties for an initial conference, then had a series of follow-up pre- hearing conferences by phone. McLellan gave the parties three options for rendering an award: a simple abbreviated award, a reasoned award, or an award containing detailed findings of fact and conclusions of law. The parties agreed that McClellan would submit a reasoned award at the conclusion of the arbitration. Further, the parties agreed that expert 1 witnesses could not attend the arbitration hearings during witness testimony and that the hearings would be conducted without a stenographer.

The arbitration hearings took place over five days and were conducted in August and September 2020. At the conclusion of witness testimony, McLellan asked the parties "if they believed that they were afforded a full and fair

1 The parties agreed that only they and their legal representatives could attend the hearings.

A-2039-20

opportunity to present their respective cases." Both parties answered in the affirmative and neither party raised any objections.

In October 2020, McLellan issued a reasoned award, granting Foresight's claim of $343,852.41, representing the balance owed under the contract, and $90,000, representing Foresight's delay damages. McLellan also granted VRURE's set-off claims totaling $426,000. He denied VRURE's claims for liquidated damages and payment under the agreement. Therefore, Foresight's net award was $7,852.41. McLellan denied both parties' requests for attorney's fees and costs because he found no party prevailed.

Foresight filed an order to show cause to vacate the arbitration award.

VRURE cross-moved to confirm the award. Prior to argument on the cross- motions, VRURE submitted a certification from McLellan. McLellan stated that he made "complete" professional experience and affiliation disclosures as required by AAA construction arbitration rules. He then detailed the procedural history of the arbitration, from initial conference to issuance of the reasoned award.

In February 2021, the Law Division denied Foresight's motion and granted VRURE's cross-motion. The court made several findings: the contract between the parties called for binding arbitration in the event of a dispute, with no

A-2039-20

provision for judicial review; McLellan acted "within his discretion and authority" when he barred the parties' experts from attending the arbitration hearings; neither McLellan's experience in construction law and arbitration nor his alleged failure to disclose his current work or professional affiliations were evidence of bias or corruption; McLellan's certification was not improper, and was "a recitation of events and not a submission in favor of or against either party"; and finally, neither party was a prevailing party and therefore not entitled to fees and costs.

Foresight raises multiple points on appeal, contending the trial court erred by not: overturning certain evidential decisions made by McLellan; finding McLellan exceeded his powers by misinterpreting the parties' agreement and failing to issue a reasoned award; finding McLellan disregarded the law by accepting certain testimony and failing to award attorney's fees to Foresight; determining that McLellan committed misconduct or showed partiality; and in not striking McLellan's certification.

II.

In reviewing the order confirming the award, we owe no special deference to the trial court's interpretation of the law and the legal consequences that flow from the established facts. Yarborough v. State Operated Sch. Dist. of City of

A-2039-20

Newark, 455 N.J. Super. 136, 139 (App. Div. 2018) (citing Manalapan Realty, L.P. v. Twp. Comm. of Manalapan, 140 N.J. 366, 378 (1995)). Therefore, we review the trial court's decision on a motion to vacate an arbitration award de novo. Ibid. (citing Minkowitz v. Israeli, 433 N.J. Super. 111, 136 (App. Div. 2013)). This standard is consistent with federal arbitration law, which the parties agreed would apply in the event they had a dispute. See Metromedia Energy, Inc. v. Enserch Energy Servs., 409 F.3d 574, 579 (3d Cir. 2005) (applying the de novo standard of review in reviewing an order vacating an arbitration award under the FAA).

We defer to a trial court's factual findings if they are supported by substantial, credible evidence in the record. Lee v. Brown, 232 N.J. 114, 126- 27 (2018); Zaman v. Felton, 219 N.J. 199, 215 (2014). When we compare our use of deference to the federal standard, we find that judicial review of arbitration awards under the FAA is "extremely deferential." Metromedia Energy, Inc, 409 F.3d at 578 (citation omitted). "Vacatur is appropriate only in 'exceedingly narrow' circumstances . . . ." Ibid. (quoting Dluhos v. Strasberg, 321 F.3d 365, 370 (3d Cir. 2003)). The "exclusive" grounds for vacating an arbitration award are provided in 9 U.S.C. § 10. Hall St. Assocs., L.L.C. v.

A-2039-20

Mattel, Inc., 553 U.S. 576, 584 (2008). Thus, where the FAA controls, an award may be vacated only:

a. where the award was procured by corruption, fraud, or undue means;

b. where there was evident partiality or corruption in the arbitrators, or either of them;

Free access — add to your briefcase to read the full text and ask questions with AI

FORESIGHT CONSTRUCTION LLC v. VALLEY RENAISSANCE URBAN RENEWAL ENTITY, LLC (L-0040-21, ESSEX COUNTY AND STATEWIDE), (N.J. Ct. App. 2022).

FORESIGHT CONSTRUCTION LLC v. VALLEY RENAISSANCE URBAN RENEWAL ENTITY, LLC (L-0040-21, ESSEX COUNTY AND STATEWIDE) (FORESIGHT CONSTRUCTION LLC v. VALLEY RENAISSANCE URBAN RENEWAL ENTITY, LLC (L-0040-21, ESSEX COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United Steelworkers v. Enterprise Wheel & Car Corp.
363 U.S. 593 (Supreme Court, 1960)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Richlin Security Service Co. v. Chertoff
553 U.S. 571 (Supreme Court, 2008)
Dluhos v. Strasberg
321 F.3d 365 (Third Circuit, 2003)
Oxford Health Plans LLC v. Sutter
133 S. Ct. 2064 (Supreme Court, 2013)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Major League Baseball Players Assn. v. Garvey
532 U.S. 504 (Supreme Court, 2001)
Tahir Zaman v. Barbara Felton (072128)
98 A.3d 503 (Supreme Court of New Jersey, 2014)
Minkowitz v. Israeli
77 A.3d 1189 (New Jersey Superior Court App Division, 2013)
Lee v. Brown
178 A.3d 701 (Supreme Court of New Jersey, 2018)