Forelaws On Board v. Johnson

743 F.2d 677
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 21, 1985
Docket82-7319
StatusPublished
Cited by31 cases

This text of 743 F.2d 677 (Forelaws On Board v. Johnson) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forelaws On Board v. Johnson, 743 F.2d 677 (9th Cir. 1985).

Opinion

743 F.2d 677

21 ERC 1850, 14 Envtl. L. Rep. 20,839,
15 Envtl. L. Rep. 20,186

FORELAWS ON BOARD, an unincorporated association; and Lloyd
Marbet, Plaintiffs,
v.
Peter JOHNSON, as Administrator of the Bonneville Power
Administration, Department of Energy; James
Edwards, as Secretary of the Department
of Energy and the United
States of America, Defendants.

No. 82-7319.

United States Court of Appeals,
Ninth Circuit.

Argued and Submitted March 6, 1984.
Decided Sept. 25, 1984.
As Amended Jan. 21, 1985.

Linda K. Williams, Portland, Or., for plaintiffs.

George M. Galloway, Washington, D.C., for Pacific Power & Light Co.

Eric Redman, Seattle, Wash., for Martin Marietta Aluminum.

Frank W. Ostrander, Portland, Or., for Northwest Power Planning Council.

David J. Adler, Portland, Or., for Peter Johnson, Dept. of Energy.

Original Proceeding to Review the Bonneville Power Administration Offer of Initial Contracts Pursuant to the Pacific Northwest Electric Power Planning and Conservation Act.

Before SCHROEDER, FARRIS, and REINHARDT, Circuit Judges.

SCHROEDER, Circuit Judge.

This is a challenge to the Bonneville Power Administration's offers of long term contracts for power delivery pursuant to the Pacific Northwest Electric Power Planning and Conservation Act (Regional Act), 16 U.S.C. Sec. 839-839h (1982), without compliance with the requirements of the National Environmental Policy Act of 1969 (NEPA), 42 U.S.C. Secs. 4321-4361 (1976). We have previously held that this is a review of final agency action which, under the Regional Act, must be filed originally in this court rather than in the district court. Forelaws on Board v. Johnson, 709 F.2d 1310 (9th Cir.1983) (Forelaws I).

Plaintiffs seek an order compelling the preparation of an Environmental Impact Statement and enjoining operation of the contracts. We hold that an Environmental Impact Statement is required and should be utilized in connection with consideration of any further amendments, to which NEPA will also apply and for which additional EIS's may be required. We decline, however, to enjoin operation of the contracts pending completion of the initial EIS.

Statutory Background

On December 5, 1980, the Regional Act became law. It is a "unique piece of energy legislation" designed to allocate the finite supply of inexpensive hydroelectric power, generated on the Columbia River System, among competing consumers as well as to provide for the acquisition of new energy resources. See Central Lincoln Peoples' Utility District v. Johnson, 735 F.2d 1101, 1106 (9th Cir.1984). In the early 1970's, BPA, faced with increasing demand for low-cost hydroelectric power and possible power shortfalls, notified its nonpreference customers that their power contracts would not be renewed and informed its preference customers that it could not satisfy any load growth after 1983. Aluminum Co. of America v. Central Lincoln Peoples' Utility District, --- U.S. ----, 104 S.Ct. 2472, 2477-78, 81 L.Ed.2d 301 (1984). In response to the resulting confusion, Congress passed the Regional Act, which was designed to avert "regional civil war" by allocating BPA's finite supply of hydroelectric power between competing consumers and by providing for the acquisition of new energy resources. See Central Lincoln Peoples' Utility District v. Johnson, 735 F.2d 1101, 1106 (9th Cir.1984). The Regional Act required BPA to offer new long-term contracts to both preference and nonpreference customers "[a]s soon as practicable within nine months after December 5, 1980." 16 U.S.C. Sec. 839c(g)(1). Each customer was given one year from the date of the offer to accept the contract. 16 U.S.C. Sec. 839c(g)(2). Thus, within 21 months of the Act's effective date, a new system of contracts allocating BPA's supply of hydropower was to be in place.

The Act also required BPA to encourage energy conservation by its customers as well as to take measures to protect the environment of the Pacific Northwest. 16 U.S.C. Sec. 839b, d, f(j). Congress said the Act was to be "construed in a manner consistent with applicable environmental laws." 16 U.S.C. Sec. 839. The questions presented in this case thus implicate two of the Acts' most important objectives: a new system of contracts governing BPA's delivery of power to its customers and an energy program for the Pacific Northwest that is sensitive to environmental concerns.

Procedural Objections to this Suit

Before reaching the merits of the case, there are two preliminary procedural objections by the defendant BPA, and intervenors Martin Marietta Aluminum, Public Power Council, and Pacific Power & Light Company, relating to plaintiffs' standing and the timeliness of the action.

Intervenor Martin Marietta contends that Forelaws lacks standing because it has not alleged that BPA's contract offers caused it any injury within the zone of interest to be protected by NEPA, citing Port of Astoria, Oregon v. Hodel, 595 F.2d 467, 474 (9th Cir.1979). The complaint, however, alleges that plaintiff Forelaws is an environmental group whose members live in the Pacific Northwest and that one of its members, Mr. Marbet, is a resident of that region and a consumer of electric power there.1 Those allegations coupled with the allegations of the environmental consequences of the contract are sufficient to establish standing. See United States v. SCRAP, 412 U.S. 669, 683-90, 93 S.Ct. 2405, 2414-17, 37 L.Ed.2d 254 (1972) (even general allegations of potential harm by one who lives in or uses an area demonstrate standing); Pacific Legal Foundation v. State Energy Resources, Etc., 659 F.2d 903, 911-12 (9th Cir.1981), cert. denied, 457 U.S. 1133, 102 S.Ct. 2956, 73 L.Ed.2d 1348 (1982). See also Sierra Club v. Morton, 405 U.S. 727, 739, 92 S.Ct. 1361, 1368, 31 L.Ed.2d 636 (1972) ("[A]n organization whose members are injured may represent those members in a proceeding for judicial review.").

The timeliness question arises from the confusion generated by the statute's provision that suits challenging final actions of the BPA administrator "shall be filed within the United States court of appeals for the region ... within ninety days ...." 16 U.S.C. Sec. 839f(e)(5). The complaint in this case was not actually filed with the clerk of this court until more than 90 days after the action being challenged. However, it is undisputed that Forelaws attempted to file a complaint the day before the expiration of the 90-day period, but the clerk of this court rejected the complaint because normally this court does not have jurisdiction of original complaints. In fact the plaintiffs had also filed a complaint in the district court, and jurisdictional issues were still in litigation. See Forelaws I, 709 F.2d at 1311-13. Our clerk's mistaken rejection of the complaint when it was timely offered should not bar its consideration, and it should be deemed timely filed. See Loya v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jamul Action Committee v. Jonodev Chaudhuri
837 F.3d 958 (Ninth Circuit, 2016)
Cactus Corner, LLC v. U.S. Dept. of Agriculture
346 F. Supp. 2d 1075 (E.D. California, 2004)
Hawaii Longline Association v. National Marine Fisheries Serv.
281 F. Supp. 2d 1 (District of Columbia, 2003)
Kootenai Tribe of Idaho v. Veneman
313 F.3d 1094 (Ninth Circuit, 2002)
Kandra v. United States
145 F. Supp. 2d 1192 (D. Oregon, 2001)
Natural Resources Defense Council v. Houston
146 F.3d 1118 (Ninth Circuit, 1998)
National Wildlife Federation v. Espy
45 F.3d 1337 (Ninth Circuit, 1995)
Jones v. Gordon
792 F.2d 821 (Ninth Circuit, 1986)
Conservation v. Johnson
783 F.2d 858 (Ninth Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
743 F.2d 677, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forelaws-on-board-v-johnson-ca9-1985.