Foley-Wismer & Becker and Shurtleff & Andrews Construction v. National Labor Relations Board

695 F.2d 424, 112 L.R.R.M. (BNA) 2417, 1982 U.S. App. LEXIS 23010
CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 28, 1982
Docket80-7272
StatusPublished
Cited by6 cases

This text of 695 F.2d 424 (Foley-Wismer & Becker and Shurtleff & Andrews Construction v. National Labor Relations Board) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foley-Wismer & Becker and Shurtleff & Andrews Construction v. National Labor Relations Board, 695 F.2d 424, 112 L.R.R.M. (BNA) 2417, 1982 U.S. App. LEXIS 23010 (9th Cir. 1982).

Opinions

SKOPIL, Circuit Judge:

Petitioners, Foley-Wismer & Becker and Shurtleff & Andrews, seek review of a decision and order of the National Labor Relations Board quashing notice of hearing under section 10(k) of the NLRA (“the Act”), 29 U.S.C. § 160(k). We deny the petition for review.

I.

Shurtleff & Andrews Constructors (“Shurtleff”) and Foley-Wismer & Becker (“Foley-Wismer”) (together, “the Companies”) each employed members of the Teamsters, Operating Engineers, and other unions. The Companies both utilize large cranes to pull 40-foot flatbed trailers which are loaded with construction material from the storage yard to the construction site. Both Companies had previously awarded the operation of the cranes to a member of Operating Engineers, and the craft employ[426]*426ees whose materials were being transported customarily assisted the crane operator by signaling the operator, tying down loads and hooking and unhooking the trailer.

On July 31, 1979 the Teamsters and the Operating Engineers executed a jurisdictional agreement providing that the work of pulling flatbed trailers would be manned by a composite crew consisting of an Operating Engineer and a Teamster, with the Operating Engineer operating the crane and the Teamster assisting by rigging or signaling the driver, directing the loading to ensure a balanced load, tying down the load, hooking and unhooking the trailer and dolly, landing the crane in proper position for the loading, and performing certain light maintenance tasks. The Unions notified the Companies of their jurisdictional agreement and requested that the Companies reassign crane operation to a composite crew. The Companies refused. The Teamsters struck and picketed Shurtleff for ten days, and after Shurtleff filed unfair labor practice charges gave assurances that it would not engage in further strikes. The Teamsters threatened Foley-Wismer with strike action, but later gave assurances against such strikes.

The Companies separately filed charges with the National Labor Relations Board (“the Board”) alleging that the Teamsters had violated section 8(b)(4)(D) of the Act by picketing, striking, and threatening to picket and strike the Companies to force them to reassign crane operation work to a composite crew. The Companies also charged that the Teamsters’ demand for the employment of composite crews constituted an unlawful attempt at featherbedding in violation of section 8(b)(6). The Board’s Regional Office found insufficient evidence to support the allegations of a violation of section 8(b)(6) and dismissed the charges. The Board’s regional director issued an order consolidating the cases filed by each Company and scheduled a hearing pursuant to section 10(k).

After the hearing, the Board found that the Companies had failed to establish the existence of a jurisdictional dispute between the unions since the two unions had not made rival claims to the same work. The Board, with one member dissenting, concluded there was no reasonable cause to believe that section 8(b)(4)(D) had been violated, and issued an order quashing the notice of hearing in the section 10(k) proceeding. 249 NLRB No. 10. This petition for review was filed challenging the Board decision and order.

The Board petitioned this court for an original en banc hearing, asserting that this court lacks appellate jurisdiction because the order to quash is not a final order subject to review by this court1 and that prior Ninth Circuit precedent to the contrary should be overruled. See StrombergCarlson Communications, Inc. v. NLRB, 580 F.2d 939 (9th Cir.1978); Waterway Terminals Co. v. NLRB, 467 F.2d 1011 (9th Cir. 1972). No judge requested a vote on the original en banc hearing suggestion, and thus the suggestion was deemed denied. General Order 5.2(a).

After argument, the panel requested en banc review to determine whether the Board’s order quashing notice of hearing of the section 10(k) proceeding was reviewable and whether Waterway Terminals should be overruled. This court en banc determined that such a quashing order was reviewable. Foley-Wismer & Becker v. NLRB, 682 F.2d 770 (9th Cir.1982) (en banc). The case was accordingly returned to this three-judge panel for a decision of the merits.

II.

The issue presented for review is whether there was substantial evidence to support the Board’s finding that no jurisdic[427]*427tional dispute existed within the meaning of section 10(k) of the Act.2

III.

The Board’s findings of facts must be upheld if supported by substantial evidence, 29 U.S.C. § 160(e); NLRB v. ILWU, 378 F.2d 33, 35 (9th Cir.), cert. denied, 389 U.S. 1004, 88 S.Ct. 562, 19 L.Ed.2d 599 (1967), and the Board’s legal conclusions as to the jurisdictional dispute must be upheld unless arbitrary and capricious. NLRB v. International Ass’n of Ironworkers, Local 433, 549 F.2d 634, 640 (9th Cir.), cert. denied, 434 U.S. 832, 98 S.Ct. 116, 54 L.Ed.2d 92 (1977); NLRB v. ILWU, Local 50, 504 F.2d 1209, 1214 (9th Cir.1974), cert. denied, 420 U.S. 973, 95 S.Ct. 1393, 43 L.Ed.2d 652 (1975); NLRB v. ILWU, 413 F.2d 30, 33 (9th Cir.1969).

Section 10(k) empowers the Board to hear and determine a jurisdictional dispute when it finds reasonable cause to believe that such a dispute exists. A jurisdictional dispute is defined as “a dispute between two or more groups of employees over which is entitled to do certain work.” NLRB v. Radio & Television Broadcast Engineers Union, 364 U.S. 573, 579, 81 S.Ct. 330, 334, 5 L.Ed.2d 302 (1961). A jurisdictional dispute cannot by definition exist unless there are rival claims to the same work. NLRB v. Plasterers Union, 404 U.S. 116, 134, 92 S.Ct. 360, 371, 30 L.Ed.2d 312 (1971). Accordingly, in the absence of active and competing claims section 10(k) is not applicable. For example, under the Safeway rule announced by the Board in 1962 and followed since, if one of the unions claiming work effectively renounces its claim, section 10(k) proceedings are aborted, even where the employer maintains an interest in securing a Board decision on the merits of the dispute. NLRB v. Plasterers Union, supra, at 134, 92 S.Ct. at 371, approving Highway Truckdrivers Local 107 (Safeway Stores, Inc.), 134 NLRB 1320 (1961).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
695 F.2d 424, 112 L.R.R.M. (BNA) 2417, 1982 U.S. App. LEXIS 23010, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foley-wismer-becker-and-shurtleff-andrews-construction-v-national-ca9-1982.