Foley Co. v. Walnut Associates

597 S.W.2d 685, 1980 Mo. App. LEXIS 2469
CourtMissouri Court of Appeals
DecidedApril 7, 1980
DocketKCD 30541
StatusPublished
Cited by21 cases

This text of 597 S.W.2d 685 (Foley Co. v. Walnut Associates) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foley Co. v. Walnut Associates, 597 S.W.2d 685, 1980 Mo. App. LEXIS 2469 (Mo. Ct. App. 1980).

Opinion

DIXON, Judge.

The appeal in the instant case is from a judgment of the trial court, sitting in equity, which: found that J. H. Mackay Electric Company, Inc. was entitled to payment from the owner for construction work upon the Mercantile Bank Building, declared the amount due to be secured by a mechanic’s lien, and imposed prejudgment interest upon a portion of the judgment.

The issues are the validity of the lien, the propriety of the prejudgment interest, the construction of the contract as it relates to the amount due, and a claim of offset or recoupment based upon the lien claimant’s alleged delay in performance.

The trial court made specific findings of fact and conclusions of law, albeit in a somewhat unusual but effective fashion. At the conclusion of the evidence, the court indicated it would like an oral statement by counsel for the lien claimant as to each requested finding. As each such finding was stated, the court permitted a response and then announced the court’s ruling upon the requested finding or conclusion. Despite this informality, these recorded findings and conclusions pinpoint the essential issues on this appeal.

This appeal involves only New York Life Insurance, as the present owner of the Mercantile Bank Building, and Chicago Title Insurance Company, as the title insurer of the building. These parties are the appellants and will, for convenience, be referred to as New York Life. The lien claimant, J. H. Mackay Electric Company, Inc., was a cross claimant in the original litigation and is the sole respondent on this appeal.

Walnut Associates, a Missouri limited partnership, was the developer and equitable owner of the Mercantile Bank Building. The legal title during construction was in an entity called Bok, Inc., a Maryland corporation. Concordia Project Management, Limited, was an agent for Walnut Associates, and the contract in question was between Concordia, as such agent, and Mack-ay. Concordia’s function appears to be a cross between an owner’s agent and a general contractor: soliciting bids, negotiating contracts, supervising performance, and generally expediting the work. There is no question that Mackay was a general contractor having an original contract with the owner, Walnut Associates.

*687 There is no dispute in this case as to the timely filing of the lien and suit to enforce the lien or the sufficiency of the legal description. The dispute centers initially on the amount of the lien which turns on the contract issues and the validity of the lien because of the inclusion of nonlienable items.

Mackay’s contract was to perform certain electrical work and to install electrical fixtures and materials in the building. This contract, executed on July 20, 1973, called for a lump-sum payment to Mackay in the amount of $460,355.00. In its lien statement filed March 14, 1975, Mackay claimed a further sum of $79,118.79 for additions to the contract, which, after deducting for payments received in the amount of $498,-358.59, left a net claim of $41,115.20.

Subsequent to the filing of the lien statement, on April 9, 1975, Mackay issued a credit memo in the amount of $1,437.00, reflecting a charge that had been included in the lien statement for certain lighting fixtures called for by the contract that had not been installed. As a result of this credit, the claim was reduced to $39,678.20, the amount demanded in the Mackay cross claim filed September 4, 1975.

The trial court entered a judgment for Mackay in the amount of $37,618.11. The parties say this was arrived at by adding $10,300.48 of the $12,360.57 claimed for “labor escalation” in its mechanic’s lien statement to what they refer to as an “undisputed” sum of $25,257.54 found by the trial court. These two figures add to $35,558.02 which is $2,060.09 less than the judgment entered. No one on this appeal even notes, much less complains of this miscalculation.

Based upon the exhibits, the fact appears to be that the undisputed amount of the Mackay claim was $27,317.63 which, when added to the $12,360.57 claimed for labor escalation, amounts to the final lien claim of $39,678.20.

The first issue raised is the validity of the labor escalation charges. Mackay submitted invoices reflecting the increase in direct labor costs and fringe benefits on all labor on the project after April 1, 1974. These increased costs resulted from labor contracts binding Mackay and entered into in September, 1973, and September, 1974. The original bid had assumed some increase from September, 1973, to April 1974, the initially scheduled completion date. To the calculation of labor charges, out of pocket, Mackay added 20% for overhead and profit. The trial court found against Mackay on the 20% for overhead and profit, and it no longer figures in the contract dispute. The trial court, however, found for Mackay on the basic charge for labor escalation.

The hinge of the dispute as to the remainder of the labor escalation charges, the $10,300.48 figure, is a single contract provision. The construction contract agreed upon by the parties provided: “Labor escalation after April 1, 1974 to be negotiated.” New York Life contends the contract provision is a clear and unambiguous “agreement to agree.” Mackay claims the provision is ambiguous and, when properly construed, means that labor prices after April, 1974, were to be based upon the negotiated contract wage rates in effect on that date. There is no dispute that Mackay’s labor costs were determined upon an annual in-dustrywide labor negotiation between an association of electrical contractors and the labor unions. The trial court found the contract was ambiguous and construed it as contended by Mackay. The court explicitly based this finding upon its consideration of two precontract documents — the Instructions to Bidders and the Mackay bid — which were received in evidence over objections and which provided: “Prices are to be good to April 1, 1974, with percent labor escalation thereafter.”

This poses the initial issue on the appeal: Was Mackay entitled to the labor escalation charges in the amount of $10,300.48 as the trial court found? It is the position of New York Life that the contract has but one meaning, that the parties “agreed to agree,” and that such an agreement is unenforceable. From this premise, New York Life argues that the trial court was in error in receiving the two precontract documents, the instructions to bidders and the bid of *688 Mackay. New York Life asserts that these are parol evidence offered to vary the terms of “a clear and unambiguous contract clause.”

There can be no dispute as to the principle announced by the cases cited by New York Life that the parol evidence rule prohibits the introduction of parol evidence to alter or vary the terms of a contract. But before the rule can be applied, the contract must be interpreted to determine its meaning. Without doubt, the court is entitled to consider more than the express language of the agreement when making this original determination. Much of the dispute in this case centers upon the issue of ambiguity or lack of ambiguity in the disputed language. The trial court found the language to be ambiguous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D.T. v. M.S.
W.D. Missouri, 2023
Joyce Elaine Bozarth v. Edgar Forshe Bozarth
Missouri Court of Appeals, 2022
Belton Chopper 58, LLC v. North Cass Development, LLC
496 S.W.3d 529 (Missouri Court of Appeals, 2016)
Good Hope Missionary Baptist Church v. St. Louis Alarm Monitoring Co.
306 S.W.3d 185 (Missouri Court of Appeals, 2010)
J.R. Waymire Co. v. Antares Corp.
975 S.W.2d 243 (Missouri Court of Appeals, 1998)
Schnucks Carrollton Corp. v. Bridgeton Health & Fitness Inc.
884 S.W.2d 733 (Missouri Court of Appeals, 1994)
Mel-Lo Enterprises, Inc. v. Belle Starr Saloon, Inc.
716 S.W.2d 828 (Missouri Court of Appeals, 1986)
Scullin Steel Co. v. Paccar, Inc.
708 S.W.2d 756 (Missouri Court of Appeals, 1986)
Bartlow-Hope Electrical Corp. v. Stanley
692 S.W.2d 404 (Missouri Court of Appeals, 1985)
Nika Corp. v. City of Kansas City, Mo.
582 F. Supp. 343 (W.D. Missouri, 1984)
Twin River Construction Co. v. Public Water District No. 6
653 S.W.2d 682 (Missouri Court of Appeals, 1983)
Shaffer v. Terrydale Management Corp.
648 S.W.2d 595 (Missouri Court of Appeals, 1983)
St. Joseph Light & Power Co. v. Zurich Insurance Co.
698 F.2d 1351 (Eighth Circuit, 1983)
Phipps v. School District of Kansas City
645 S.W.2d 91 (Missouri Court of Appeals, 1982)
Kramer v. Fallert
628 S.W.2d 671 (Missouri Court of Appeals, 1981)
Spychalski v. MFA Life Insurance Co.
620 S.W.2d 388 (Missouri Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
597 S.W.2d 685, 1980 Mo. App. LEXIS 2469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foley-co-v-walnut-associates-moctapp-1980.