Foehr v. New York Short Line Railroad

40 Pa. Super. 7, 1909 Pa. Super. LEXIS 558
CourtSuperior Court of Pennsylvania
DecidedJuly 14, 1909
DocketAppeal, No. 1
StatusPublished
Cited by7 cases

This text of 40 Pa. Super. 7 (Foehr v. New York Short Line Railroad) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foehr v. New York Short Line Railroad, 40 Pa. Super. 7, 1909 Pa. Super. LEXIS 558 (Pa. Ct. App. 1909).

Opinion

Opinion by

Rice, P. J.,

The plaintiff’s right of way, which he claims was the only available way he had for hauling the products of his farm to the public highway and thence to market, was derived by grant from Clara Murray of “the free use and privilege of a roadway as now laid out about fifty feet wide between and from the farm land of said William Foehr,” beginning at the plaintiff’s land at a point on the north side of Pennypack creek, “thence up the said creek the several courses on the brink thereof” to a certain mill ?ace and thence “up the several courses thereof” to the public highway known as the Krewstown road. This private road had been used by the owners and occupiers of the plaintiff’s farm for a number of years prior to his purchase. Several years after he became owner of the farm and received the grant [16]*16above referred to, the defendant company acquired title to the Murray farm over which the private road was laid, and constructed a railroad and a bridge therefor which crossed Penny-pack creek and the private road. The plaintiff brought this action to recover damages for alleged obstructions of his right of way, and on the trial claimed that part of the permanent pier encroaches thereon; that part of the temporary trestle and other temporary structures were erected and maintained thereon and materially obstructed it; and that it was further obstructed by the temporary deposit thereon of sand, lumber, stone and other materials used in the construction of the bridge.

We cannot agree with the defendant’s counsel in his contention that there was no evidence that any part of the permanent pier of the railroad bridge was built upon the traveled roadway, the use of which was granted to the plaintiff. Throughout his testimony the plaintiff persisted in his claim that the pier encroaches somewhat upon his right of way. It is true, some expressions in his testimony upon that subject, taken by themselves, tend to show that this claim was based on his erroneous supposition that irrespective of the width to which the roadway was actually laid out, as indicated by the travel and other marks on the ground, his grant gave him a right of way over the entire strip of ground fifty feet wide along the brink of the creek, yet the court would scarcely have been warranted in charging the jury that his testimony taken as a whole would not support a finding that the pier encroaches upon the roadway as actually laid out and existing at the time of the grant to him. Furthermore, that allegation of fact does not rest on his unsatisfactory testimony alone. Another witness testified moré clearly that it encroaches on the traveled roadway about five or six feet, as near as he could judge. The question was one of fact, and although the evidence adduced by the defendant seems to us more satisfactory and convincing than that adduced by the plaintiff, it was the province of the jury to decide it under instructions from the court as to the law applicable to the facts, and subject to the salutary power of the court to award a new trial if it should deem the verdict contrary to the weight of the evidence: Reel v. Elder, 62 Pa. 308; Perkiomen R. R. Co. v. [17]*17Kremer, 218 Pa. 641. The fourth and fifth assignments of error are overruled.

The objection that the fact above considered was not relevant under the pleadings, because no mention is made in the statement of claim of the encroachment of the pier, was not raised in the court below, so far as the record shows, and is not distinctly raised here by any assignment of error. Moreover, a perusal of the defendant’s points and the report of the trial shows very clearly, we think, that the case was tried on the theory that it was a material and relevant fact. The defendant not only did not object to the evidence upon the subject adduced by the plaintiff, but on its own part introduced much evidence upon the same subject. Its counsel did not specifically request instructions to the jury that there could be no recovery on the ground of the encroachment of the pier, if the jury should find that fact, but did request the court to charge that if the jury found that fact, the plaintiff could only recover for the actual loss shown by him to have been caused by the encroachment from the time it was placed there to the date of bringing suit. The learned judge affirmed the point, and could not have gone further without being more zealous than counsel. He might well have inferred that the defendant deemed the statement of claim broad enough to sustain recovery for en-. croachment of the pier, or did not desire to raise the technical objection that it was not. After a trial judge has submitted a question to a jury from the standpoint from which both parties to the issue manifestly have tried it, the one against whom the verdict is rendered should not ordinarily be permitted on appeal to question the correctness of the submission, except in cases where manifest injustice results from it: Carpenter v. Lancaster, 212 Pa. 581. See also Hartley v. Decker, 89 Pa. 470; Taylor v. Sattler, 6 Pa. Superior Ct. 229.

But apart from the question of the sufficiency of the declaration to sustain a recovery of nominal or actual damage the encroachment of the pier may have caused, the plaintiff’s counsel are right in saying that it was a relevant fact, because it would materially aid the jury in determining the proximity and extent of the encroachment upon and obstruction of the road by [18]*18the other branches of the work incidental to the construction of the bridge, including the excavation for the pier, the erection of the false work and the like.

The next question to be considered is as to the applicability of the rule relative to the immunity of an employer from responsibility for the acts of his independent contractor. The bridge was constructed for the defendant by certain construction companies under written contracts, and the court was requested to charge that under the terms of these contracts the defendant was not responsible for any obstruction of plaintiff’s highway by the contractors during the construction of the bridge, caused by the manner in which they did the work, or, as expressed in another point, for the acts of the contractors in depositing dirt, stone or materials in the right of way claimed by the plaintiff, or for allowing engines or machinery to remain thereon. The refusal of these points is the subject of the sixth and seventh assignments of error. Wherever the contract prescribes the manner in which the work is to be done, or wherever the building or other structure contracted for cannot be erected at the place designated without actionable injury to the property of third persons, the other party to the contract is responsible for the acts of the contractor, thus injurious to others, which compliance with the provisions of the contract renders necessary. The general proposition, which scarcely needs the citation of decisions for its support, has been thus stated: “Where the act which causes the injury is one which the contractor was employed to do and the injury results, not from the manner of doing the work but from the doing of it at all, the employer is liable for the acts of his independent contractor: ” 26 Cyc. of Law & Proc. 1557. The subject is elaborately treated in the notes to Thomas v. Harrington, 72 N. H. 45; s. c., 65 L. R. A. 742. Having regard to sound principle, the saíne rule must be held to apply where the injury results from the doing of the work in the manner expressed in the contract, or directed by the employer or by one acting for him who has authority under the contract to direct it. In First Presbyterian Congregation v. Smith, 163 Pa. 561, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weldon v. Steiner
10 A.2d 19 (Superior Court of Pennsylvania, 1939)
Baier Et Ux. v. Glen Alden Coal Co.
200 A. 190 (Superior Court of Pennsylvania, 1938)
Silveus v. Grossman
161 A. 362 (Supreme Court of Pennsylvania, 1932)
Silveus v. Grossman
156 A. 716 (Superior Court of Pennsylvania, 1931)
Clouse v. Crow
68 Pa. Super. 248 (Superior Court of Pennsylvania, 1917)
Norris v. Philadelphia
49 Pa. Super. 641 (Superior Court of Pennsylvania, 1912)
Hollidaysburg Male & Female Seminary Co. v. Gray
45 Pa. Super. 426 (Superior Court of Pennsylvania, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
40 Pa. Super. 7, 1909 Pa. Super. LEXIS 558, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foehr-v-new-york-short-line-railroad-pasuperct-1909.