Florida Power & Light Company v. Federal Energy Regulatory Commission, City of Homestead, Florida, Intervenor. Florida Power & Light Company v. Federal Energy Regulatory Commission, Lake Worth Utilities Authority of Lake Worth, Florida, Intervenor. Florida Power & Light Company v. Federal Energy Regulatory Commission

617 F.2d 809, 199 U.S. App. D.C. 227, 1980 U.S. App. LEXIS 21115
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 24, 1980
Docket79-1260
StatusPublished

This text of 617 F.2d 809 (Florida Power & Light Company v. Federal Energy Regulatory Commission, City of Homestead, Florida, Intervenor. Florida Power & Light Company v. Federal Energy Regulatory Commission, Lake Worth Utilities Authority of Lake Worth, Florida, Intervenor. Florida Power & Light Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Power & Light Company v. Federal Energy Regulatory Commission, City of Homestead, Florida, Intervenor. Florida Power & Light Company v. Federal Energy Regulatory Commission, Lake Worth Utilities Authority of Lake Worth, Florida, Intervenor. Florida Power & Light Company v. Federal Energy Regulatory Commission, 617 F.2d 809, 199 U.S. App. D.C. 227, 1980 U.S. App. LEXIS 21115 (D.C. Cir. 1980).

Opinion

617 F.2d 809

199 U.S.App.D.C. 227

FLORIDA POWER & LIGHT COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
City of Homestead, Florida, Intervenor.
FLORIDA POWER & LIGHT COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Lake Worth Utilities Authority of Lake Worth, Florida, Intervenor.
FLORIDA POWER & LIGHT COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent.

Nos. 78-1884, 78-2249, 78-2302 and 79-1260.

United States Court of Appeals,
District of Columbia Circuit.

Argued Oct. 24, 1979.
Decided Jan. 24, 1980.

[199 U.S.App.D.C. 229] Petitions for Review of an Order of the Federal Energy Regulatory commission.

Robert T. Hall, III, Washington, D. C., with whom Richard M. Merriman, Floyd L. Norton, IV, and John R. Schaefgen, Jr., Washington, D. C., were on the brief, for petitioner.

Andrew M. Zack, Washington, D. C., Atty., with whom Robert R. Nordhaus, Gen. Counsel, and Howard E. Shapiro, Sol., Federal Energy Regulatory Commission, Washington, D. C., were on the brief, for respondent.

Robert A. Jablon, Washington, D. C., with whom Daniel J. Guttman, Washington, D. C., was on the brief, for intervenors.

Harry A. Poth, Jr. and Robert S. Medvecky, Washington, D. C., also entered appearances for petitioner.

Lynn N. Hargis, Atty., Federal Energy Regulatory Commission, Washington, D. C., also entered an appearance for respondent.

Before J. EDWARD LUMBARD,* Senior Circuit Judge for the Second Circuit, and TAMM and MIKVA, Circuit Judges.

Opinion for the court filed by Senior Circuit Judge LUMBARD.

Opinion concurring in part and dissenting in part filed by Circuit Judge TAMM.

LUMBARD, Circuit Judge:

Florida Power & Light (FPL) petitions this court for the review of five orders issued by the Federal Energy Regulatory Commission (FERC or Commission) in four dockets.1 FPL argues that the Commission deviated from the guidelines of the Federal Power Act, 16 U.S.C. § 791a et seq., and from the prior interpretation of its own regulations, by classifying as "changed" rates, rather than as "initial" rates, the rate schedules FPL filed in each docket, and that the Commission exceeded its authority by issuing one of those orders after the statutory deadline for FERC action. We disagree.

I.

Section 205(c) of the Federal Power Act, 16 U.S.C. § 824d(c), requires that public utilities file with the Commission the [199 U.S.App.D.C. 230] rate schedule for each agreement to provide a service which is subject to the Commission's jurisdiction. If the Commission finds that any filed rate is "unjust, unreasonable, unduly discriminatory or preferential," § 206(a) of the Act, 16 U.S.C. § 824e(a), dictates that the Commission shall determine the just and reasonable rate and shall fix that rate by order. Once a rate has been filed and has taken effect, the utility may not change it, according to § 205(d), 16 U.S.C. § 824d(d), except after thirty days notice to the Commission and the public. The utility gives such notice by filing with the Commission a new schedule "stating plainly the change or changes to be made in the schedule or schedules then in force." Whenever a utility files any such new schedule as described in § 205(d), the Commission has the authority, as set out in § 205(e), to conduct hearings concerning the lawfulness of the changed rate, to suspend the operation of the rate for up to five months, and, if it allows the rate to take effect before the hearings conclude, to order the utility to refund any portion of an increase in rates which the utility cannot show to be just and reasonable. Thus, the Act empowers the Commission to scrutinize, and if necessary to change, any rate filed, whether it is a changed rate or the first rate a utility has ever filed. However, only if the filed rate is a changed rate may the Commission also suspend its operation or allow it into effect subject to refund.2 It is the fact that the Commission has greater power over changed rates than it has over initial rates that lies at the heart of this suit.

Between October 1977 and July 1978, each of these four customers TECO and the three cities entered into numerous additional interchange agreements with each other and with other electric utilities.3 [199 U.S.App.D.C. 231] Moreover, because not all of the parties to these additional interchange agreements are directly linked by electric wires, each of the four customers negotiated agreements with FPL, which has direct links to all the parties, for FPL to transmit through its wires the exchanged electricity. Pursuant to § 205(c), FPL filed with the Commission the rate schedules for each of these agreements known as transmission agreements.4

Before these transmission agreements took effect, FPL had only interchange agreements with these four customers, with the exception that it also had had a partial requirements (i. e. a wholesale) agreement with Homestead. Thus, on the theory that transmission service fundamentally differs from either interchange or requirements service, FPL filed its transmission rate schedules as "initial" rates. That term does not appear in the Federal Power Act, but is the label the Commission's regulations give to a schedule that does not change any rate then in force and that is therefore not subject to the Commission's suspension or refund powers under § 205(e). 18 C.F.R. § 35.1(b). The Commission disagreed with that classification, asserting that transmission service does not fundamentally differ from interchange or requirements service because FPL necessarily already transmits electricity to the four customers to execute the interchange and requirements agreements. Thus, the Commission decided, the transmission agreement schedules change or to use the language of the Commission's regulations, "supersede, supplement, cancel or otherwise change," 18 C.F.R. § 35.1(c) a rate then in force, that rate being the rate for transmission necessarily included in the interchange and requirements rate schedules.

Having classified the schedules as changed rather than initial rates, the Commission asserted its § 205(e) authority to suspend the rates for one day and then to put them into effect subject to refund if they are later found to be unjustified increases, and to order a hearing to determine their lawfulness. FPL sought a rehearing in each docket, as § 313(b), 16 U.S.C. § 825l (b), requires it to do before seeking review in a court of appeals. The Commission denied each request, with the exception that it granted a rehearing in the Vero Beach docket for the limited purpose of reconsideration. It later affirmed the denial. FPL filed timely petitions for review and the four dockets were consolidated for briefing and argument.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Securities & Exchange Commission v. Chenery Corp.
332 U.S. 194 (Supreme Court, 1947)
Burlington Truck Lines, Inc. v. United States
371 U.S. 156 (Supreme Court, 1962)
Otter Tail Power Co. v. United States
410 U.S. 366 (Supreme Court, 1973)
Federal Power Commission v. Texaco Inc.
417 U.S. 380 (Supreme Court, 1974)
Trans Alaska Pipeline Rate Cases
436 U.S. 631 (Supreme Court, 1978)
Wyllie Gatewood v. Fiat, S. P. A.
617 F.2d 820 (D.C. Circuit, 1980)
Chisholm v. Federal Communications Commission
538 F.2d 349 (D.C. Circuit, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
617 F.2d 809, 199 U.S. App. D.C. 227, 1980 U.S. App. LEXIS 21115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-power-light-company-v-federal-energy-regulatory-commission-city-cadc-1980.