Fletcher v. Milburn Manufacturing Co.

35 Mo. App. 321, 1889 Mo. App. LEXIS 179
CourtMissouri Court of Appeals
DecidedApril 2, 1889
StatusPublished
Cited by7 cases

This text of 35 Mo. App. 321 (Fletcher v. Milburn Manufacturing Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fletcher v. Milburn Manufacturing Co., 35 Mo. App. 321, 1889 Mo. App. LEXIS 179 (Mo. Ct. App. 1889).

Opinion

Thompson, J.,

delivered the opinion of the court.

This was an action commenced before a justice of the peace for work and labor done. The complaint was as follows :

Plaintiff states for his cause of action that defendants are indebted to him in the sum of thirty dollars, for services rendered for common labor from February 27, 1888, to March 6, 1888, in doing blacksmith work on two vehicles, called mountain wagons, at thirteen dollars per wagon and three dollars extra for brakes, less one dollar for socket. “Plaintiff, therefore, prays judgment for said sum, together with the costs herein.”

The defendant filed the following counter-claim:

“ J. W. Fletcher to Milburn Manufacturing Co.,

Dr.

“To two full circles, 5th wheel, destroyed by J. W. Fletcher, defendant..... $3 80

“To four 3-8 axle clips, destroyed by J. W. Fletcher, defendant.......... 16

“To two seat handles, destroyed by Fletcher......................... 30

“ To coal wasted by Fletcher............ 50

“ To use of tools by Fletcher........... 50

“Touse and loss of foreman’s time..... 2 50

“ To cash paid Charles Kelly, blacksmith, work on two wagons, S. & E. Spring 10 00

“To finisher’s time to complete work---- 2 98

“To loss of time and expense.......... 4 00

“Total............................$24 74.”

On trial anew in the circuit court, the plaintiff recovered a verdict and judgment for the full amount claimed by him. The defendant appeals, and assigns for error the rulings of the court in giving, and refusing instructions.

[325]*325The defendant was engaged in the manufacture of carriages and the plaintiff was a blacksmith employed in the defendant’s shop. The plaintiff’s evidence tended to show that the defendant employed him by the piece to iron off two “ mountain wagons,” so called, at the price of fifteen dollars each ; that the job was a new one to him and to the superintendent; that he performed the job under the direction of the superintendent ; that when the job was done it was defective in a given particular ; that the superintendent required the plaintiff to remedy the defect; that the plaintiff did not refuse to do this, but that, before the plaintiff had time to do it, he was discharged by the defendant from its employ and payment was refused him for the job. The defendant’s evidence tended to show that the plaintiff was employed by the defendant through its superintendent to iron off the two wagons, not at the price of fifteen dollars each, but at the price of $8.50 each ; that, when the plaintiff had finished the job and turned it over for inspection, it was found defective in several particulars, so that the wagons would have been unsalable in the condition in which the plaintiff left them ; that the plaintiff was required by the superintendent to do the job over again, which he refused to do, whereupon he was discharged. The defendant’s evidence also was to the effect that other workmen were employed to do the job over again at a considerable cost to the defendant, the details of which were given by items ; but there was no evidence that the amount thus paid for rectifying the job as the plaintiff had left it was the reasonable value of the work.

The court gave the following instruction at the request of the plaintiff, after modifying it by adding the words in italics: “If the jury find and believe from the evidence that J. W. Fletcher, plaintiff, was employed by the Milburn Manufacturing Company, defendant, as a carriage blacksmith, and that in the [326]*326course of his employment he was to iron the wood work of two wagons, and that he performed the work, they are then to find for the plaintiff in snch sums as the evidence in this cause shows he is entitled to, not exceeding the amount of his claim of thirty dollars, unless you find for defendant on the following instruction.”

The court then gave the following instruction at the request of the defendant: “The court instructs the jury that, if they believe from the evidence that plaintiff was working by the piece and agreed to do the work in controversy at a fixed price ; and if they further believe from the evidence that plaintiff performed the work in a poor, unskilful and unworkmanlike manner, and that defendant' or defendant’s foreman refused to accept the work because of the poor, unskilful and unworkmanlike manner in which said work was done, and that defendant or his said foreman notified plaintiff of said refusal to accept said work, and then and there requested plaintiff to finish his work in a good and workmanlike manner; and if you further believe from the evidence plaintiff refused to finished the work as requested, and in consequence of which defendant had to do the work over, then plaintiff cannot recover, and your verdict should be for the defendant, although you may believe that defendant’s foreman afterward discharged plaintiff from defendant’s employ, provided you believe from the evidence that said discharge took place after plaintiff’s refusal to do said work over as requested.”

The two following instructions were requested by the defendant and refused by the court:

“ 1. The burden of proof is on the plaintiff, and before he can recover he must establish his case by a preponderance of evidence.”

“3. If you believe from the evidence that plaintiff did the work in controversy in a poor, unskilled and [327]*327unworkmanlike manner; that defendant refused to accept said work on account of it being done in such a poor, unskilful and unworkmanlike manner; that defendant notified plaintiff of its refusal to accept said work and requested plaintiff to finish his work in a proper manner, and that the plaintiff after being so requested refused so to do ; and that by reason of said refusal and said work being done in such a poor, unskilful and unworkmanlike manner, defendant was obliged to have the work done over by other parties, then you will find for defendant on his set-off what you may believe from the evidence it cost defendant to have the work finished or completed in a proper and workmanlike manner.”

I. The objection to the instruction given on behalf of the plaintiff is that it does not embrace all the issues. It is a sufficient answer to this objection to say that it refers to the following instruction in express terms, so as to require the jury to read both of them together, and that the two taken together do embrace all the issues. But it should be further added, that, while it is a rule that an instruction is vicious which singles out certain facts in evidence, not in themselves controlling, and makes the entire case turn upon those facts; yet, there is no rule which requires the judge, in framing instructions, to embrace all the issues in a single paragraph. On the contrary, it is in general sufficient if the instructions as a whole present the issues fairly to the jury. Hayner v. Churchill, 29 Mo. App. 676; Karle v. Railroad, 55 Mo. 476, 482; Whalen v. Railroad, 60 Mo. 323. In Karle v. Railroad, supra, it was expressly ruled that it is proper to give a series of instructions, one on each issue presented by the pleadings and evidence.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burger v. Wood
446 S.W.2d 436 (Missouri Court of Appeals, 1969)
Berger v. St. Louis Storage & Commission Co.
116 S.W. 444 (Missouri Court of Appeals, 1909)
Cramer v. Nelson
107 S.W. 450 (Missouri Court of Appeals, 1908)
Simons v. Wittmann
88 S.W. 791 (Missouri Court of Appeals, 1905)
Priest v. Consolidated Tank Line Co.
51 Mo. App. 205 (Missouri Court of Appeals, 1892)
Harkness & Russell v. Briscoe
47 Mo. App. 196 (Missouri Court of Appeals, 1891)
Mackin v. People's Street Railway & Electric Light & Power Co.
45 Mo. App. 82 (Missouri Court of Appeals, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
35 Mo. App. 321, 1889 Mo. App. LEXIS 179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fletcher-v-milburn-manufacturing-co-moctapp-1889.