Fitzgerald v. Benner

76 N.E. 709, 219 Ill. 485
CourtIllinois Supreme Court
DecidedFebruary 21, 1906
StatusPublished
Cited by10 cases

This text of 76 N.E. 709 (Fitzgerald v. Benner) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fitzgerald v. Benner, 76 N.E. 709, 219 Ill. 485 (Ill. 1906).

Opinion

Mr. Justice Magruder

delivered the opinion of the court:

In this case the evidence shows that the labor and material, for the price of which this suit is brought, were furnished by the appellees; and the defense of the appellant rests upon substantially two grounds. The first ground of defense is, that there can be no recovery, because the certificate of the architect was not produced, as required by the contract, and because the certificate was not shown to have been withheld fraudulently, or by reason of fraud on the part of the architect. The second ground of defense is, that there can be no recovery, because the damages, alleged to have been sustained by the appellant by reason of defective material and delay in completing the work, exceeded the amount claimed by appellees. That is to.say, according to the claims of appellant, the appellees were continuously in default from September 29, 1892, until February 15, 1893, a period of 139 days, and the liquidated damages for the delay, at the rate of $50.00 a day for 139 days, would amount to $6950.00, which exceeds the sum of $6408.63, claimed by the appellees to have been due them. The main contention of the appellees in regard to the delay was, that they were delayed in the performance of the contract by the fault of other contractors. The objections made by appellant,' which range themselves under, and bear upon, the general defenses above stated, will be considered in their order.

First—Appellant contends that the court below erred in the admission and exclusion of evidence.

It is said that the court erred in permitting appellees to prove, that the interest on the claim against appellant from December 15, 1892, up to the date of the trial amounted to $3407.00. It is claimed that there is no evidence, showing the completion of the work on December 15, 1892. We have examined the testimony, and find that there was evidence, consisting of the testimony of several witnesses introduced by the appellees, showing that the work was completed about the middle of December, 1892. It is true that testimony, introduced by the appellant, tended to show that the work was not completed until February 15, 1893, but the court, under its instructions, properly submitted the evidence to the jury upon this question, and it was for them to determine which was the correct date of the completion of the work. It is also insisted that the court erred in allowing this testimony in regard to interest, upon the alleged ground that the appellees did not make out a case of vexatious and unreasonable delay of payment. It is undoubtedly true that, in order to justify a recovery of interest, the claim must be liquidated, and it must be shown that the parties figured upon a definite amount as being due, and that payment has been vexatiously and unreasonably withheld. (Haight v. McVeagh, 69 Ill. 624; Imperial Hotel Co. v. Claflin Co. 175 id. 119.)

There was evidence, introduced by the appellees, tending to show that appellee, Kent, after January 18, 1893, went to the office of the architect, Warren, and submitted the account, which was checked up, and the sum of $6000.00 was agreed upon as being due appellees, and that a certificate of that amount was made out under the direction of the architect, Kent consenting to throw off the $408.63 rather than have any quarrel or dispute. The evidence tends further to show that the architect put off the payment of the amount, thus agreed to be due, at one time by asking that it be allowed to rest for a day or two until the architect could see appellant; at another time, several weeks thereafter, when Kent demanded the certificate, the architect said that he had had a talk with the appellant, and asked that it be allowed to rest a while longer as appellant was pressed for money; again, after the lapse of several weeks, Kent was told by the architect that appellant had instructed him not to give appellees a certificate; and the architect told Kent that he had better see the appellant, and have a talk with him, and fix it up; Kent thereupon went to see Fitzgerald, who told him to go to the architect, saying: “You get a certificate from the architect, and I will pay it;” when Kent went back to the architect, he was informed by him again that Fitzgerald had told him (the architect) not to give the certificate. When Kent returned to the architect after the fourth or fifth visit, the latter told him that he was entitled to his money, but that he would have to see Fitzgerald, the owner of the building, who had given him an order not to issue the certificate ; thereupon, on seeing Fitzgerald, he was again told by the latter, “You get a certificate and I will pay it;” and thereafter, when Kent attempted again to see the architect, he found that the office of the latter was closed, and he had left for Europe. This evidence tended to show a vexatious and unreasonable delay of payment, and therefore justified the introduction of testimony in regard to the amount of interest. Independently, however, of any other consideration, it sufficiently appears that the jury did not allow the appellees any interest, and, therefore, the introduction of the testimony in question could not have done the appellant any harm. If the sum of $3407.00 had been allowed for interest, the verdict would have been $9407.00. As, however, the verdict was only for the sum of $6000.00, being the amount of principal agreed upon by the parties, it is clear that there was no allowance of interest.

The court is said to have erred in permitting a witness for the appellees, named Anderson, to state what he said over the telephone at a certain time. Anderson appears to have been a sub-contractor under appellees, who was to furnish certain of the iron work. He was put upon the stand for the purpose of showing that the delay in the putting up of the iron work was the fault of appellant. Anderson states, that he was at the building from the 5th to the 30th of September almost every day, but was unable to go ahead, stating that the iron was lying all around the street, and they were kicking about it blocking up the street. He then makes the following statement: “I asked every day, telephoned every day, ‘Can’t I start?’ because I had a gang idle.” The objection is, that this was a conversation by telephone between Anderson and appellees, at which the appellant was not present, and that, therefore, the evidence was mere hearsay and should have been excluded by the court. The only language, shown to have been used over the telephone, are the words “Can’t I start?” These words were a mere exclamation, which constituted a part of the res gestee, as being calculated to illustrate or picture the condition of affairs then existing at the building. It tended to show the reason why appellees could not go ahead with the work. The words were not the narration or history of a past event, but threw light upon the reason why it was impossible to proceed with the work. In Maher v. City of Chicago, 38 Ill. 266, where certain city officials made statements during the prosecution of work for a corporation to persons engaged on the work, it was said (p. 273) : “Counsel for the city contend that the statements of the city officials were improperly received as evidence. These statements were made at the commencement and during the progress of the work to persons engaged upon it, and are admissible as showing the manner and circumstances, under which it was begun and prosecuted. They are part of the res gestee.” In Kyner v. Boll, 182 Ill. 171, it was said (p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson-Ross Floors, Inc. v. Scherrer Construction Co.
379 N.E.2d 786 (Appellate Court of Illinois, 1978)
Roberts v. Carlson
8 N.W.2d 175 (Nebraska Supreme Court, 1943)
Bailey v. Babcock
185 N.E. 602 (Illinois Supreme Court, 1933)
Crosby v. State
106 So. 741 (Supreme Court of Florida, 1925)
Hopkins v. Whelan
217 Ill. App. 248 (Appellate Court of Illinois, 1920)
Bates v. Estate of Cronin
196 Ill. App. 178 (Appellate Court of Illinois, 1915)
Marrone v. Ehrat
175 Ill. App. 649 (Appellate Court of Illinois, 1912)
Masek v. Chmelik
169 Ill. App. 589 (Appellate Court of Illinois, 1912)
People ex rel. Zimmer v. Pacific Surety Co.
155 Ill. App. 586 (Appellate Court of Illinois, 1910)
Dwyer v. Chicago City Railway Co.
153 Ill. App. 463 (Appellate Court of Illinois, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
76 N.E. 709, 219 Ill. 485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fitzgerald-v-benner-ill-1906.