First Sealord Surety, Inc. v. TLT Construction Corp.

765 F. Supp. 2d 66, 2010 U.S. Dist. LEXIS 101627, 2010 WL 3810856
CourtDistrict Court, D. Massachusetts
DecidedSeptember 27, 2010
DocketCivil Action 10-11048-JLT
StatusPublished
Cited by3 cases

This text of 765 F. Supp. 2d 66 (First Sealord Surety, Inc. v. TLT Construction Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Sealord Surety, Inc. v. TLT Construction Corp., 765 F. Supp. 2d 66, 2010 U.S. Dist. LEXIS 101627, 2010 WL 3810856 (D. Mass. 2010).

Opinion

MEMORANDUM

TAURO, District Judge.

I. Introduction

This action arises out of an agreement between Plaintiff Sealord Surety, Inc. (“Sealord”) and Defendant TLT Construction Corp. (“TLT”), under which Plaintiff provided performance and payment bonds for a subcontractor on one of Defendant’s construction projects. In its Amended Complaint, Plaintiff seeks declaratory relief along with damages. Presently at issue are Defendant’s Motion to Dismiss [# 4] and Plaintiffs Motion to Stay Arbitration [# 9]. For the reasons set forth below, this court reserves judgment on Defendant’s Motion to Dismiss [# 4], and Plaintiffs Motion to Stay Arbitration [# 9] is DENIED.

II. Background 1

Plaintiff is a Pennsylvania corporation that is licensed to issue surety bonds in Massachusetts. 2 Defendant is a Massachusetts corporation that on April 30, 2007 submitted a bid for the construction of a new middle-high school to be built in Manchester-by-the-Sea, Massachusetts (the “Project”), after NEED Construction LLC (“NEED”) had submitted a $1,725,984 subcontract proposal to perform portions of the work for the Project. 3 Defendant was chosen as the lowest bidder for the Project, became the general contractor, and entered into subcontract negotiations with NEED. 4 NEED provided additional proposals in May 2007 for between approximately $1,725,984 and $1,950,000 to perform subcontract work, but Defendant divided NEED’S subcontract work into two components. 5 On May 18, 2007, Defendant and NEED entered into the Phase I Subcontract for a value of $964,800 and the Phase II Subcontract for *69 a value of $643,200 (the “NEED Subcontracts”), for a total of $1,608,000. 6

Before executing the NEED Subcontracts, Defendant prepared its own estimates for the work covered by the NEED Subcontracts in connection with developing its costs for the general contract for the Project. 7 Defendant’s total estimate for the work identified in the NEED Subcontracts was $3,070,225. But, it entered into the NEED Subcontracts for a total of approximately $1,608,000. 8 Prior to entering into the NEED Subcontracts, Defendant never disclosed to NEED or Plaintiff the substantial discrepancies in value between its estimates and the estimates provided by NEED. 9

Defendant required NEED to obtain performance and payment bonds for the NEED Subcontracts before NEED could begin its subcontract work. 10 NEED was unsuccessful in obtaining such bonds. Defendant’s bonding agent, Dick Caruso of Curtain International, then contacted Plaintiff with a proposal to bond the NEED Subcontracts. 11

Defendant knew that Plaintiff would obtain an independent engineering review of the scope and value of the work to be performed under a subcontract only if the subcontract’s value were greater than $1,000,000. 12 Plaintiff alleges that Defendant, to avoid that independent engineering review, drafted and executed the Phase I Subcontract and the Phase II Subcontract in amounts less than $1,000,000. 13 Additionally, Plaintiff claims that Defendant had reason to know that information about the substantial discrepancy in estimates was critical to Plaintiffs determination of whether to undertake the risk involved with issuing performance and payment bonds for the NEED Subcontracts. 14 In reliance on the Phase I Subcontract, which would pay $964,800, Plaintiff issued performance and payment bonds on July 30, 2007 for the Phase I Subcontract (“the Bonds”). 15 The Bonds identified NEED as the principal and Defendant as the obligee. 16

NEED began to perform the Phase I Subcontract in July 2007. Shortly thereafter, various disputes arose between Defendant and NEED over the scope of the Phase I Subcontract work. 17 NEED be *70 gan to experience significant difficulties in performing its subcontract work. Those difficulties included completing its work according to the Project schedule and paying its material and equipment suppliers. 18 Defendant, through its bonding agent, Curtain International, approached Plaintiff to request a modification of and increase in the amount of the Bonds. 19 Plaintiff also claims that Defendant did not disclose information concerning the problems with NEED’S performance of its subcontract work, nor did it disclose the dispute between NEED and Defendant as to the scope of the Phase I Subcontract. 20 Relying on the information available to it, Plaintiff agreed to modify the Bonds. 21

Shortly after Plaintiff increased the limit of the Bonds, Defendant notified NEED that it was terminating the Phase II Subcontract and replacing it with a “change order” to be added to the Phase I Subcontract. 22 On June 10, 2008, approximately three months after Plaintiff increased the amount of the Bonds, Defendant notified NEED that NEED was not completing its subcontract work in a timely fashion. 23 At that time, Defendant also notified NEED that Defendant would begin supplementing NEED’S workforce and backcharging the costs of supplementation to NEED. 24 Defendant knew that if NEED could not pay for the cost of Defendant’s supplementation of NEED’S workforce, then Plaintiff would be responsible for those costs under the terms of the Bonds. 25 Plaintiff has incurred costs of approximately $1,241,490 in connection with its performance of NEED’S subcontract work on the Project. 26

Plaintiff seeks declaratory relief and damages arising out of its issuance of the performance and payment bonds. 27

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
765 F. Supp. 2d 66, 2010 U.S. Dist. LEXIS 101627, 2010 WL 3810856, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-sealord-surety-inc-v-tlt-construction-corp-mad-2010.