First National Bank of Paonia v. K.N.J., Inc.

867 P.2d 152, 17 Brief Times Rptr. 1621, 1993 Colo. App. LEXIS 269, 1993 WL 427272
CourtColorado Court of Appeals
DecidedOctober 21, 1993
DocketNos. 92CA1798, 92CA1799 and 92CA1838
StatusPublished
Cited by1 cases

This text of 867 P.2d 152 (First National Bank of Paonia v. K.N.J., Inc.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First National Bank of Paonia v. K.N.J., Inc., 867 P.2d 152, 17 Brief Times Rptr. 1621, 1993 Colo. App. LEXIS 269, 1993 WL 427272 (Colo. Ct. App. 1993).

Opinion

Opinion by

Judge HUME.

In this interpleader action concerning the distribution of funds on a United States Forest Service contract, defendants, Advanced Pipe and Supply, Inc. (APS), Engineering and Construction Products, Inc. (ECPI), Inland/Riggle Oil Company (Inland), Trustees of the Colorado Cement Masons Pension Trust Fund, and several other trust fund entities (Trustees) filed separate appeals from a summary judgment in favor of defen[154]*154dants Joe Fisher and Cecil Farnsworth d/b/a Farnsworth Construction Company (Farns-worth). The judgment gaye Fisher and Farnsworth a prior right to all funds inter-pled into court superior to the rights of appellants and other intervenors. The separate appeals have been consolidated by order of this court. We affirm in part and reverse in part.

In April 1989, defendant, K.N.J., Inc. (KNJ), a Colorado corporation, and the Forest Service entered into a contract for an improvement on Stevens Gulch Road in Delta County. KNJ hired various subcontractors to supply materials and services for the project, including defendants APS, ECPI, and Inland. Each of these subcontractors has a judgment against KNJ related to this project. The Trustees also have a judgment against KNJ, although stemming from obligations unrelated to the Stevens Gulch Road project.

Because the Stevens Gulch Road project was a contract for improvements upon federal lands, the Miller Act, 40 U.S.C. § 270a, et seq. (1988), applies. The purpose of the Miller Act is to provide security for those who furnish labor and material in the performance of government contracts. Fanderlik-Locke v. United States ex rel. Morgan, 285 F.2d 939 (10th Cir.1960).

Here, subcontractors APS and ECPI supplied materials for the project. They made several attempts to collect from KNJ or its sureties. When those attempts failed, APS and ECPI filed suit against KNJ and its sureties in federal district court under the Miller Act.

One month later, on September 19, 1990, KNJ contracted with Farnsworth for crushed gravel needed to complete the Stevens Gulch Road project. Because Farnsworth was concerned with the financial reliability of KNJ, their agreement provided that payments made by the Forest Service under its contract with KNJ would be made to the First National Bank of Paonia (Bank). KNJ assigned its rights to the Forest Service progress payments to the Bank. By agreement, the Bank would pay Farnsworth “before any other amounts [we]re paid to any other person or entity.”

In early July 1991, KNJ contracted with Fisher, who was to work with Farnsworth in completing the project. The September 1990 agreement between KNJ and Farnsworth was amended so that the Bank would distribute funds received from the Forest Service first to Farnsworth, then to Fisher, and any excess to KNJ and KNJ’s owner. By July 15, 1991, the Bank had received from the Forest Service and disbursed approximately $176,000 to Fisher and Farnsworth;

On December 20, 1991, APS and ECPI filed a motion for summary judgment in their Miller Act suit against KNJ and its surety. This motion was granted on February 7, 1992. Only six days later, the Forest Service issued its final check on this project to the Bank. By this time, the Bank was on notice that several parties, including the Trustees, who had issued a writ of garnishment on the Bank, claimed a right to the fund. As a result, the Bank filed this interpleader action and paid into court the sum of $71,396.86.

Fisher and Farnsworth filed a motion for summary judgment in the interpleader action, claiming that their contractual relationship with KNJ and the Bank entitled them to a prior right to the funds. On the information available, the trial court determined “that Fisher entered into the contract with KNJ in reliance on this arrangement ... and that in the absence of such an arrangement to assure payment for his services, he would not have contracted to haul the gravel.” Accordingly, it granted Fisher’s and Farns-worth’s motion for summary judgment. The remaining defendants initiated the appeals that are now consolidated here, all claiming a right to the funds interpled into court.

I.

Defendants APS and ECPI contend that, as a matter of law, their Miller Act judgment and their equitable lien as material suppliers or laborers are superior to the rights of the other claimants and that, therefore, summary judgment in favor of Fisher and Farnsworth was improper. We agree that summary judgment in favor of Fisher and Farnsworth was inappropriate..

[155]*155Summary judgment is a drastic remedy and is never warranted except on a clear showing that there exists no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law. Churchey v. Adolph Coors Co., 759 P.2d 1336 (Colo.1988).

Under the Miller Act, a general contractor is required to furnish sufficient bond to insure payment in full for all materials and labor supplied. See 40 U.S.C. § 270a. If a subcontractor is not paid, the subcontractor may sue the contractor’s surety on the payment bond. See, e.g., United States ex rel. B’s Co. v. Cleveland Electric Co., 373 F.2d 585 (4th Cir.1967).

APS and ECPI were awarded summary judgment on their Miller Act claim and should have been paid by the surety out of the payment bond funds. The surety was unable to pay their claims. That judgment, however, does not give APS and ECPI priority over other material suppliers and laborers here who are pursuing equitable remedies.

In addition to a remedy under the Miller Act, a material supplier or laborer holds an equitable lien in any earned, yet unpaid contract funds. Active Fire Sprinkler Corp. v. United States Postal Service, 811 F.2d 747 (2d Cir.1987). Such a lien is superior to the rights of general creditors of the contractor and any assignees of the contractor. See National Surety Corp. v. United States, 133 F.Supp. 381 (Ct.Cl.1955); Martin v. National Surety Co., 85 F.2d 135 (8th Cir.1936), aff'd, 300 U.S. 588, 57 S.Ct. 531, 81 L.Ed. 822 (1937).

Under equitable principles, the question of priority of claimants turns upon the respective equities of the parties. See Henningsen v. United States Fidelity & Guaranty Co., 208 U.S. 404, 28 S.Ct. 389, 52 L.Ed. 547 (1908).

Here, Fisher and Farnsworth are both subassignees and subcontractors of KNJ. They argue that those eases which gave priority to a material supplier or laborer over an assignee or subassignee are distinguishable because they did not involve an assignee who was also a material supplier or laborer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Olson v. McRae
389 P.2d 576 (Alaska Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
867 P.2d 152, 17 Brief Times Rptr. 1621, 1993 Colo. App. LEXIS 269, 1993 WL 427272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-national-bank-of-paonia-v-knj-inc-coloctapp-1993.