McClary v. Midland Land & Development Co.

109 F. Supp. 847
CourtDistrict Court, E.D. Tennessee
DecidedMay 29, 1952
DocketCiv. A. No. 1566
StatusPublished
Cited by2 cases

This text of 109 F. Supp. 847 (McClary v. Midland Land & Development Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McClary v. Midland Land & Development Co., 109 F. Supp. 847 (E.D. Tenn. 1952).

Opinion

ROBERT L. TAYLOR, District Judge.

This action was commenced by plaintiff, McClary, subcontractor, to recover the balance due for painting houses under contract with the defendant, Midland, contractor with Roane-Anderson Company, a contracting agent, or maintenance contractor, of the United States Government. Items of recovery sought are damages for alleged breach of the contract by Midland, [849]*849compensation for items of work added during performance of the contract, and items in excess of estimates, herein called overruns. Damages alleged are described as overtime wages paid by McClary to painters, made necessary by failure of Midland to have three houses per day ready for painting during the performance of the contract.

On two occasions during the performance period McClary caught up with Midland, and during the early weeks of performance Midland did not have three houses per day ready for painting. Midland’s contract with Roane-Anderson provided for rehabilitation of 253 houses in Oak Ridge. Painting of the houses was sub-contracted by Midland to McClary, a pertinent provision of the McClary contract being the following: “McClary agrees that he will commence work under this contract within one week after receiving notice from Midland to proceed with the performance of this contract, and after McClary commences work he agrees to complete the aforesaid work at the rate of three houses a day.”

The quoted language is all the contract contains relative to three houses per day. Had Midland sued McClary for failure to paint three houses per day, McClary could have pleaded impossibility of performance by reason of Midland’s default in not having three houses ready. Any cause of action in favor of McClary, however, would have to rest upon an implied promise by Midland to have three houses ready each day. No reason is suggested why such promise should be implied, except that Mc-Clary asserts that he organized his painting crew on the assumption that three houses per day would be ready. When he caught up with Midland’s rehabilitation forces he says he had to lay off some of his painters, in consequence of which he later got over a hundred houses behind and had to work his men overtime and on Saturdays and pay them overtime wages.

Assuming, without so holding, that there was an implied promise by Midland to have three houses ready, the Court finds that McClary has not made out a case for damages for breach of contract. The evidence shows that he could have recruited more painters whenever he wanted them and that he worked his men overtime because from a purely business consideration he expected to fare better than would have been the case with a larger force of painters. Some pressure was put on him to employ more painters when he fell behind. He was also urged to work on Saturdays. There was no compulsion upon him in the matter of choice between employing more painters and avoiding overtime and Saturday work on the one hand, and retaining his small force and working overtime. He chose the latter course.

His second item of recovery has more merit. After he had entered upon his contract with Midland, a modification was made in his contract by addition of handrails, stiffeners and posts. This addition required painting 5,742 additional board feet, consisting chiefly of two-by-fours. The above board footage would amount to 8,613 square feet of surface to be painted. From conflicting proof the Court concludes that the claimed eight cents per square foot, or the resultant amount of $689.04, is reasonable compensation for this extra work. On account of this extra work, Midland has voluntarily paid into Court $459.36, 'which leaves still to be paid the' sum of $229.69.

Other work which plaintiff asserts was additional consisted of repainting where doors had been hung wrong and had to be hinged on their other sides, gables where green lumber had shrunk upon drying and left unpainted streaks, installation of additional doors, door screen frames and window screen frames. The repaint work where doors were rehung consisted of puttying screw holes and painting the spots where the hinges had been located. The number of rehung doors may have been three or four, or from twelve to fifteen, the proof here being quite indefinite. The time required per door may have been one minute or one hour. The same indefiniteness attaches to the repainting of gable streaks. While there was this extra work caused by repainting, there was more than an offset for the reason that the sides of at [850]*850least one, and possibly three houses did not have to be painted at all, due to substitution of stained-shingle siding.

Additional doors, door screen frames and window screen frames are referred to as overruns. Examination of the modifications to the rehabilitation contract discloses that there were more underruns than overruns, the net result being a gain to plaintiff in the surface required to be painted. Accordingly, no case has been made out by plaintiff for compensation for the extras and overruns, it being conceded by McClary that Midland should have credit for under-runs on the same theory that McClary claims he should be compensated for painting overruns.

Another item to which passing reference should be made relates to a lumber deal involving $603.57. The foreman of Midland, without the knowledge of Midland, told McClary that he would pay him for half of a work day on a Saturday. This Saturday work required payment of overtime. The foreman of Midland, in order to keep his boss from knowing about the unauthorized agreement with McClary, paid McClary with lumber belonging to Midland. The foreman made no record of this particular lumber that was delivered Mc-Clary. When the Midland officials found out about the transaction they deducted $603.57 from the account that they owed McClary. McClary claims that Midland had no right to make this deduction and that he is entitled to a recovery in this suit for this $603.57. This claim cannot be sustained. The foreman’s acts in relation to this item did not bind Midland. There is nothing in the record to show that Midland authorized or ratified this unauthorized act of its foreman. Rather, the proof shows that McClary was fully advised as to the foreman’s lack of authority in this particular. Accordingly, if McClary has a right of action on this claim, -it is against the foreman, not against Midland.

Upon being sued by McClary, Midland, being pressed also by creditors of McClary, deposited in the registry of the Court the sum of $13,187.66, which sum it admits owing to McClary under the painting contract To this Midland should add the further sum of $229.68, the unpaid portion of the amount due McClary on account of the handrails, stiffeners and posts, additional items for which Midland admits McClary should be paid. When this additional sum is paid, there should be in the registry of the Court $13,417.34.

Although this began as a simple lawsuit between McClary and Midland, Midland converted it into an action in the nature of interpleader by depositing in the registry of the Court an amount equal to what Midland then admitted to be its indebtedness to McClary on account of the painting contract. In its cross-action Midland named as defendants Burks-Hallman Company, Graning Paint Company, W. E. Biggs, and Union-Peoples Bank, creditors of McClary, and Hartford Accident and Indemnity Company, surety on the bond of McClary in favor of Midland.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First National Bank of Paonia v. K.N.J., Inc.
867 P.2d 152 (Colorado Court of Appeals, 1993)
Winkler Construction Co. v. Hornor & Co.
580 S.W.2d 401 (Court of Appeals of Texas, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
109 F. Supp. 847, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcclary-v-midland-land-development-co-tned-1952.