Ferguson Electric Co. v. Department of General Services

3 A.3d 681, 2010 WL 3419511
CourtCommonwealth Court of Pennsylvania
DecidedAugust 31, 2010
Docket2041 C.D. 2009
StatusPublished
Cited by5 cases

This text of 3 A.3d 681 (Ferguson Electric Co. v. Department of General Services) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferguson Electric Co. v. Department of General Services, 3 A.3d 681, 2010 WL 3419511 (Pa. Ct. App. 2010).

Opinion

OPINION BY

Judge McCULLOUGH.

Ferguson Electric Co., Inc. (Ferguson) appeals from the September 23, 2009, order of the Board of Claims (Board), which sustained the preliminary objections filed by the Department of General Services (DGS) and dismissed Ferguson’s claim for lack of jurisdiction. We affirm.

On January 14, 1994, DGS and Ferguson entered into a contract for the performance of electrical work in the construction of the state correctional institution at Houtzdale, Pennsylvania. The contract provides, among other things, that disputes arising between a contractor and DGS are to be resolved in accordance with the following three-step procedure: (1) a construction conference; (2) a pre-claim hearing, and (3) a claim filed with the Board pursuant to the Act of May 20, 1937, P.L. 728, as amended, formerly 72 P.S. §§ 4651-1— 4651-10 (the Board of Claims Act). (Reproduced Record (R.R.) at 702a-04a.) This “three-tiered” dispute resolution procedure was in effect until 1998, when the Commonwealth Procurement Code (Code) was enacted. 1

During the course of construction, Ferguson sought payment from DGS for the cost of additional work associated with numerous change orders. On December 5, 1996, in accordance with the contract, the parties participated in a construction conference on the outstanding change orders. 2 (R.R. at 320a-36a.) At the conclusion of the conference, DGS granted Ferguson the opportunity to submit evidence of the actual costs it incurred in performing the work for each of the change orders. DGS advised Ferguson that it could not address the change orders until evidence of actual costs was submitted. (R.R. at 321a-22a.)

By letter dated September 12, 1997, DGS informed Ferguson that DGS had not yet received any additional information and asked Ferguson to confirm that it still intended to submit evidence of actual costs. (R.R. at 338a.) Ferguson did not respond to the correspondence and did not *684 submit any additional evidence. Believing that it was Ferguson’s responsibility to advance its own claim, DGS did not make a second request for additional evidence or initiate any further communication with Ferguson.

Ferguson took no action for approximately five years. Then, on May 20, 2002, Ferguson submitted a claim to DGS, which included a demand for payment of the change orders. (R.R. at 346a — 58a.) By letter dated May 24, 2002, DGS returned the claim to Ferguson’s legal counsel, explaining that the claim should have been filed with the Board, and not DGS. However, Ferguson did not file the claim with the Board; instead, via a series of letters in 2002, Ferguson ultimately informed DGS that it wished to resolve this matter in accordance with the procedures established by the Code. Ferguson promised to provide DGS with supporting documentation but never did. 3 (R.R. at 363a, 364a, 371a, and 475a.) On October 1, 2003, Fer *685 guson filed a Right-to-Know Act 4 request with DGS demanding the production of numerous documents related to the construction project. 5 (R.R. at 373a-75a.)

Approximately five years later, on April 23, 2007, Ferguson sent a letter to DGS, asking it to schedule a construction claims conference. By letter dated August 1, 2007, and sent certified mail, DGS responded as follows:

[T]he Department deems that Ferguson Electric Company breached their duty to submit the information in a timely manner, thereby prejudicing the Department’s ability to conduct a meaningful review of any claim. In fact, the Construction Inspection Manager on the project has passed away.
The claim has had several attorneys of record working for various law firms that have, for the past ten years, issued unfulfilled assurances to submit documentation of actual costs ‘shortly’ and ‘in an expeditious fashion,’ following the December 5, 1996 Construction Conference. Now, 127 months after the Construction Conference and almost 12 years after Final Inspection on the project, your firm is attempting to continue the claim, which is disingenuous at best. Ferguson’s failure to submit the information constitutes a waiver of the right to pursue the claim.

(R.R. at 377a.) (Emphasis added.) On August 15, 2007, Ferguson sent a letter to DGS, objecting to the rejection of its claims and requesting another construction conference. (R.R. at 476a.) DGS did not respond.

On March 12, 2008, Ferguson filed a claim with the Board, which contained counts for breach of contract, unjust enrichment, and quantum meruit. Ferguson averred that its total damages on the construction project were $1,607,415.90. The claim was filed more than seven months, approximately 224 days, after DGS’s August 1, 2007, letter.

In response, DGS filed preliminary objections to the claim asserting: (1) lack of jurisdiction; (2) insufficient specificity of the pleading; (3) legal insufficiency of the pleading; and (4) failure to exhaust a statutory remedy.

The Board conducted evidentiary hearings on November 5, 2008, and December 4, 2008. After review, the Board found that DGS’s August 1, 2007, letter constituted definitive and affirmative notice to Ferguson that its claim would not be paid. Applying section 1712.1 of the Code, the Board concluded that Ferguson’s March 12, 2008, claim was untimely filed, and, therefore, the Board lacked jurisdiction. Accordingly, the Board sustained the preliminary objection regarding lack of jurisdiction and dismissed Ferguson’s claim. 6

On appeal to this Court, 7 Ferguson first contends that the Board erred as *686 a matter of law by determining that its claim accrued on August 1, 2007. Under the 1998 and 2002 versions of the Code, as well as the repealed Board of Claims Act, the limitation period on a claim commences when it “accrues.” A claim accrues when (1) a claimant is first able to litigate his or her claim, e.g., when the amount due under the claim is known and the claimant is capable of preparing a concise and specific written statement detailing the injury, and (2) the claimant is affirmatively notified that he or she will not be paid by the Commonwealth. Darien Capital Management, Inc. v. Public School Retirement System, 549 Pa. 1, 700 A.2d 395 (1997). The denial of a claim must be unequivocal, id., and both prongs of the Dañen test must be satisfied before a claim may be considered to have accrued. Knorr.

Ferguson argues that the August 1, 2007, letter from DGS did not affirmatively and unequivocally deny any of its claims because the letter does not expressly state that the claims would not be paid. In its August 1, 2007, letter, DGS unequivocally stated that Ferguson waived its right to pursue its claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lobar Assoc., Inc. v. PA Turnpike Comm.
Commonwealth Court of Pennsylvania, 2019
Roe v. Pennsylvania Game Commission
147 A.3d 1244 (Commonwealth Court of Pennsylvania, 2016)
Lake Erie Promotions, Inc. v. Erie County Board of Assessment Appeals
60 A.3d 194 (Commonwealth Court of Pennsylvania, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
3 A.3d 681, 2010 WL 3419511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferguson-electric-co-v-department-of-general-services-pacommwct-2010.