Lobar Assoc., Inc. v. PA Turnpike Comm.

CourtCommonwealth Court of Pennsylvania
DecidedAugust 1, 2019
Docket1038 C.D. 2018
StatusPublished

This text of Lobar Assoc., Inc. v. PA Turnpike Comm. (Lobar Assoc., Inc. v. PA Turnpike Comm.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lobar Assoc., Inc. v. PA Turnpike Comm., (Pa. Ct. App. 2019).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Lobar Associates, Inc., : Petitioner : : v. : No. 1038 C.D. 2018 : Argued: March 12, 2019 Pennsylvania Turnpike Commission, : Respondent :

BEFORE: HONORABLE MARY HANNAH LEAVITT, President Judge HONORABLE P. KEVIN BROBSON, Judge HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge

OPINION BY PRESIDENT JUDGE LEAVITT FILED: August 1, 2019

Lobar Associates, Inc. (Contractor) petitions for review of an order of the Board of Claims (Board) that sustained the preliminary objections of the Pennsylvania Turnpike Commission (Commission) and dismissed Contractor’s claim for lack of jurisdiction. The Board held that Contractor’s claim was barred by the six-month statute of limitations set forth in Section 1712.1(b) of the Commonwealth Procurement Code, 62 Pa. C.S. §1712.1(b).1 Contractor argues that the Board erred in its determination of when Contractor’s claim accrued. Discerning no such error by the Board, we affirm. Background On June 18, 2014, Contractor agreed to construct a 2,431-square-foot material testing laboratory at mile marker 113.82 of the Pennsylvania Turnpike (the

1 Section 1712.1(b) of the Procurement Code states: (b) Filing of claim.--A claim shall be filed with the contracting officer within six months of the date it accrues. If a contractor fails to file a claim or files an untimely claim, the contractor is deemed to have waived its right to assert a claim in any forum. Untimely filed claims shall be disregarded by the contracting officer. 62 Pa. C.S. §1712.1(b). Somerset Project) for the Commission. Contractor completed the work in June 2016. On July 27, 2016, Contractor submitted a “supplemental work order” to the Commission, requesting additional compensation of $150,925.19 for changes to the project made by the Commission during construction. Reproduced Record at 676a (R.R. __). On September 21, 2016, the Commission responded that it would pay $35,233.05 for the supplemental work. Contractor responded with a request for further review, which was denied by the Commission on October 17, 2016. On March 27, 2017, Contractor submitted an administrative claim to the Commission’s contracting officer, seeking $418,767.42 for the supplemental work and delay damages attributable to the Commission’s project design changes. The Commission conducted an administrative hearing. It denied Contractor’s claim as untimely because it was not submitted within six months of the Commission’s September 21, 2016, determination that it would pay $35,233.05 for the supplemental work. Thereafter, on September 14, 2017, Contractor filed a three-count claim against the Commission with the Board asserting breach of contract, unjust enrichment, and violation of the Contractor and Subcontractor Payment Act, 73 P.S. §§501-516.2 Contractor sought a judgment in excess of $418,767.42, plus interest, costs of suit and attorney fees. Contractor’s claim stated that the Somerset Project began as a publicly bid project. However, the Commission then made an “unwieldy and confusing

2 Act of February 17, 1994, P.L. 73, as amended, 73 P.S. §§501-516. The Contractor and Subcontractor Payment Act sets guidelines for prompt payment. Section 9 of the Contractor and Subcontractor Payment Act, 73 P.S. §509. Interest may be assessed on payments unreasonably held. Section 9(d) of the Contractor and Subcontractor Payment Act, 73 P.S. §509(d). A contractor that withholds payment in bad faith can be subjected to a one percent penalty and attorney fees. Section 12 of the Contractor and Subcontractor Payment Act, 73 P.S. §512. 2 attempt to convert [the] publicly bid project into a JOC [job-order contract] project.” Claim, ¶2 at 1; R.R. 8a.3 The claim alleged that this conversion resulted in “an incomplete design to start the [p]roject and thus one that changed and morphed as the [p]roject proceeded.” Claim, ¶3 at 2; R.R. 9a. The design changes required Contractor to perform work beyond the scope of the contract. Claim, ¶5 at 2; R.R. 9a. In addition, Contractor sought delay damages for expenses it incurred due to delays caused by the design changes. Claim, ¶6 at 2; R.R. 9a. Contractor’s claim asserted damages of $150,925.19 for the supplemental work and delay damages of $267,842.23. Claim, ¶7 at 2: R.R. 9a. The Commission filed preliminary objections, asserting that the Board lacked jurisdiction because Contractor’s claim was barred by the six-month statute of limitations in Section 1712.1(b) of the Procurement Code. The Commission also asserted that Contractor failed to exhaust its administrative remedy and failed to state a claim for unjust enrichment. The Board held an evidentiary hearing on the question of its jurisdiction. Contractor presented the testimony of Carl Barker, its project manager for the Somerset Project.4 He has worked with hundreds of job order contracts, but the Somerset Project was his first with the Commission. The contract established a fixed price for the completion of the Somerset Project, but it also authorized

3 A “job order” is defined by Section 101.03 of the Contract as the “contractor’s authorization issued by the Commission, in conjunction with a Purchase Order, to perform all work required to complete the Detailed Scope of Work for the amounts in the Price Proposal within the agreed upon schedule.” R.R. 54a. 4 Barker was employed by Contractor from April 2015 through January 2018. 3 supplemental job orders that would add work credits to, or deletions from, the contract’s fixed price. 5 Barker’s contact at the Commission was Robert Kleimenhagen, the project manager. At the outset, Kleimenhagen instructed Barker to keep an Excel spreadsheet to document extra work Contractor performed on the Somerset Project. Rather than address each project change as it arose, Kleimenhagen explained that the Commission would review the spreadsheet at the end of construction. Barker thought this was unusual for such a large project, but he complied with Kleimenhagen’s directive. At the conclusion of the project, Contractor submitted a supplemental job order and spreadsheet seeking $150,925.19 for additional work. Barker testified that he sent the supplemental job order request via email on July 27, 2016, to Gary Madey, the Commission’s construction manager. Barker explained that the spreadsheet had to be uploaded using the Commission’s collaborative software, known as “Kahua,” and Madey was the person who handled this software. Notes of Testimony, 3/12/2018, at 53 (N.T. __); R.R. 388a. Barker copied Kleimenhagen on the email to Madey. On August 26, 2016, Kleimenhagen responded that he hoped to complete the review by September and requested additional information from Barker. Barker did not respond to Kleimenhagen’s email. On September 21, 2016, Kleimenhagen sent Barker an email with an attached spreadsheet. The email explained that the Commission’s entire construction management team had reviewed Barker’s spreadsheet and compared it to the project design drawings, specifications, special provisions and on-site

5 The Commission describes the job order contract between the Commission and Contractor as an “umbrella contract” from which individual “job orders” or “projects” could be awarded. Commission Brief at 9. 4 construction inspections. The email concluded that Contractor was owed $35,233.05, and not $150,925.19. Contractor was advised to submit a supplemental job order for the work items for which the Commission was willing to pay. On October 6, 2016, Barker sent Kleimenhagen an email requesting further review because Contractor did not accept the amount of $35,233.05. Barker did not specifically request, but expected, a meeting. On October 17, 2016, Kleimenhagen responded with an email that reiterated the line-by-line account of what the Commission agreed to pay pursuant to the September 21, 2016, email.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Darien Capital Management, Inc. v. Commonwealth
700 A.2d 395 (Supreme Court of Pennsylvania, 1997)
Wayne Knorr, Inc. v. Department of Transportation
973 A.2d 1061 (Commonwealth Court of Pennsylvania, 2009)
Buchart Horn, Inc. v. Department of Transportation
1 A.3d 960 (Commonwealth Court of Pennsylvania, 2010)
Ferguson Electric Co. v. Department of General Services
3 A.3d 681 (Commonwealth Court of Pennsylvania, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Lobar Assoc., Inc. v. PA Turnpike Comm., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lobar-assoc-inc-v-pa-turnpike-comm-pacommwct-2019.