Ferguson Contracting Co. v. State

70 Misc. 472, 126 N.Y.S. 808
CourtNew York Court of Claims
DecidedJanuary 15, 1911
DocketNo. 9640
StatusPublished

This text of 70 Misc. 472 (Ferguson Contracting Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferguson Contracting Co. v. State, 70 Misc. 472, 126 N.Y.S. 808 (N.Y. Super. Ct. 1911).

Opinions

Swift, J.

This claim is for damages arising out of a contract for the construction of a portion of the Barge canal, pursuant to chapter 147 of the Laws of 1903 and the amendments thereto.

The contract was entered into between the claimant and the State April 3, 1905. The contract provided for the construction of about seven-eighths of a mile of the improved Champlain canal from the Mohawk river, near the village of Waterford, N. Y., and westerly therefrom, and was known as contract FTo. 2. Under this contract the claimant was to be paid for the performance of the work, according to the plans and specifications accompanying the contract, the sum of $852,330.

The claimant asks judgment against the State for $420,-375.36, and the claim contains twenty-four separate causes of action for delays claimed to have been caused by the State in failing to furnish plans for different parts of the work, and for failure to give entire possession of the land upon which the work was to he done, and for loss in rentals of machinery during such delays, and including an item of $69,-439.93, which was the ten per cent, of the estimated work [474]*474completed which was retained by the State under the provisions of the contract until the work should be finally completed and approved by the State Engineer and the 'Superintendent of Public Works.

There is a large mass of testimony in this case covering the different causes of action set forth in claimant’s claim; and, before passing upon such testimony and the amount of damages which is claimed to be proven by such evidence, it is best to consider whether the claimant'is entitled to recover any damages or not.

During the progress of the work, several alterations to the plans and specifications were made by the State which increased the expense of the work and also the amount to be ■paid to the claimant, by about $35,88-0', which the claimant assented to.

On or' about the 14th day of April, 190-9, the State Engineer and Surveyor issued to the claimant an order, known as alteration ETo. 7. The claimant refused to comply with this order; -and, under section 12 of the contract, the contract with claimant was canceled, and the unfinished work relet in the manner provided by chapter 147 of- the Laws of 1903.

The claimant abandoned the contract, refusing to perform the work required by alteration ETo. 7, and files this claim for damages.

The question of the State’s liability depends upon the construction to be given to paragraph 7 of the contract. This paragraph provides as follows: “ It is mutually agreed that the State reserves the right, until the final completion and acceptance of the wrork, to make such additions to or changes in the plans and specifications covering the work as may be necessary, and the contract -shall not be invalidated thereby, and no claims shall be made by the contractor for any loss of profits because -of any such change, or by reason of any variation between the quantities of the approximate estimate and the quantities of the work as done.”

Ordinarily, -contracts mean just what they say; and, where parties execute a contract with full knowledge of its terms and conditions, they are bound thereby, even though it may result in a hardship for one of the parties.

[475]*475I think^the fair interpretation of this clause of the contract to he this: That the State, in the construction of such an important work as the improved Barge canal involving an immense detail of plans and construction, knowing the fact that in practical experience in the progress of work it is often found that .some changes in the original plans of construction and in the details thereof would be for the better interest of the State, intended to and did reserve to the State the right to make such changes in the plans and specifications whenever it became necessary so to do.

I am aware that the courts hold that such reservation does not include the right to make such a radical and fundamental change in the plans and specifications as would compel the contractor to perform a different work, or in a substantially different manner from that which he had contracted to do; and the real question here is whether such alteration Ho. 7 was such a radical and fundamental change of contract Ho. 2 that the State had no right to make such order, and that ’ claimant was not required by law to continue the contract as changed by alteration Ho. 7.

Alteration Ho. 7 provided for the following changes in the construction of the work under contract Ho. 2:

(1) To change the plans for retaining wall at the head of lock Ho. 2 from station 182+63 to station 184.
(2) To extend the wall at the crossing of the present Champlain canal so as to form a junction with sides of same between station 184+55 and station 186+95.
(3) To substitute a concrete lining for the puddle lining in the bottom of the canal from the head of lock Ho. 2 to the west end of the present dock walls, station 182+63 to station 194+40.
(4) To substitute concrete retaining walls for piled dock-. ing on each side of the canal from the west end of the present dock wall to the lower end of lock Ho.- 3, station 3 84+14 to station 201+79.
(5) To eliminate the puddle lining on the sides and bottom of the canal from the west- end of the present dock wall to lower end of lock Ho. 3; station 184+40 to station 202+50.
[476]*476(6) To raise the grade of by-pass channel around lock No. 3, station 200+18 to station 2'06+2‘5.
(7) To change the specifications for crushed stone to he -used in concrete.

These were the changes and alterations ordered by alteration No. 7.

Were the changes reasonable and necessary ?

The reasons why these alterations were to be made were stated in said order, issued to the claimant, as follows: For the first change proposed: “ The section of the Canal at the head of Lock No. 2 has been eroded by the flow of water in Cemetery Greek. This erosion has taken place along the line of the retaining walls on each side of the Canal. It will therefore be necessary to carry the foundation of these Avails to a lower level, -so that the base of the walls will rest" in undisturbed material. It is therefore -proposed to change the plans of the retaining walls from the head of Lock No. 2, Station 182+63 to Station 184.”

The reason for the second change was as follows: “At the crossing of the present Champlain Canal, the walls along the sides of the new Canal were not carried sufficiently far to form a good connection with bulkheads and masonry aa'uIIs of the old Canal. These walls have been extended slightly so as to remedy this defect.”

The reason given for the third change Avas as follows: “ The original plans provided for -a puddle lining one foot thick on the bottom of the Canal to prevent seepage of Aváter into the sand and gravel through Avhich the channel is excavated. A clay puddle lining is not thought to be satisfactory, as it would be subject to erosion by the currents stirred up by the propellers of boats, and a concrete lining nine inches thick has been substituted, extending from the head of Lock No. 2 to west end of the present dock wall, Station 182+63 to Station 194+40. Suitable concrete cut-off walls.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicago v. Sheldon
76 U.S. 50 (Supreme Court, 1870)
Topliff v. Topliff
122 U.S. 121 (Supreme Court, 1887)
McMaster v. . the State of New York
15 N.E. 417 (New York Court of Appeals, 1888)
Kingsley v. . City of Brooklyn
78 N.Y. 200 (New York Court of Appeals, 1879)
National Contracting Co. v. Hudson River Water Power Co.
84 N.E. 865 (New York Court of Appeals, 1908)
Woolsey v. . Funke
24 N.E. 191 (New York Court of Appeals, 1890)
Clark v. . the Mayor, C. of New-York
4 N.Y. 338 (New York Court of Appeals, 1850)
Winne v. Mehrbach
130 A.D. 329 (Appellate Division of the Supreme Court of New York, 1909)
Jacquin v. Boutard
35 N.Y.S. 496 (New York Supreme Court, 1895)
Jerome v. Ross
7 Johns. Ch. 315 (New York Court of Chancery, 1823)
County of Cook v. Harms
108 Ill. 151 (Illinois Supreme Court, 1883)
Smith v. Sanitary District
108 Ill. App. 69 (Appellate Court of Illinois, 1903)
Williams v. Chicago, Santa Fe & California Railway Co.
54 S.W. 689 (Supreme Court of Missouri, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
70 Misc. 472, 126 N.Y.S. 808, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferguson-contracting-co-v-state-nyclaimsct-1911.